Professional Documents
Culture Documents
For simplification purposes, the value of the negative & zero sequence impedances will be equal to
the calculated positive sequence impedance of the utility and power transformer. For 15kV XLPE
cable, except for the zero sequence impedance that will be taken from the manufacturer, the
calculated positive sequence impedance is also equal to the negative sequence impedance
Utility (ZUT)
Thus;
ZUT-1 = ZUT-2 = ZUT-0 = 0.100∟86.186°
Power TR (ZTR)
Thus;
ZTR-1 = ZTR-2 = ZTR-0 = 0.400∟80.538°
Where;
Z = Conductor actual impedance value in ohms
Conductor data:
Actual Impedance
Values in Ohms
(Manufacturer Data)
ZCA-1 0.010+j0.013
ZCA-2 0.010+j0.013
ZCA-0 0.015+j0.033
Thus;
ZCA-1 = ZCA-2 = 0.004∟52.431°
Thus;
ZCA-0 = 0.010∟65.556°
General equation;
I3F = I1 x IBASE
Where;
IBASE = 836.740A
I1 = VPU / ZTH
= VPU usually 1 per-unit
= ZTH is the thevenin’s fault point impedance
Note that a three phase fault is considered also as balanced fault, thus, only the positive
sequence were involve. Also, based on the single line diagram, we can see that the fault
contribution is mainly from the utility side, therefore, the impedance coming from XLPE
cable and transformer can be neglected, thus;
Therefore;
I1 = 1.0 / 0.100∟86.186°
I1 = 10∟-86.186°
IBASE = 4183.698A
Therefore;
I1 = 1.0 / 0.500∟81.703°
I1 = 2.002∟-81.703°
I3F = 2.002∟-81.703° x 4183.698A
I3F = 8,373.800∟-81.703°ASYM
IBASE = 4183.698A
Therefore;
I1 = 1.0 / 0.503∟81.444°
I1 = 1.988∟-81.444°
General equation;
Where;
IBASE = 836.740A
I0 = I 1 = I 2
I1 = VPU / ZTH
= VPU usually 1 per-unit
= ZTH is the thevenin’s fault point impedance
If ZUT = Z1 = Z2 = Z0 = ZTH
Therefore;
I1 = 1.0 / 0.300∟86.186°
I1 = 3.333∟-86.186°
Then;
I0 = I1 = I2 = 3.333∟-86.186°
Calculating ISLGF;
ISLGF = 3(3.333∟-86.186°) x 836.740A
ISLGF = 8,366.563∟-86.186° ASYM
IBASE = 4183.698A
If ZTH = Z1 + Z2 + Z0
Then;
Z1 = ZUT + ZTR = 0.100∟86.186° + 0.400∟80.538°
Z1 = 0.500∟81.919°
If Z1 = Z2
Then;
Z1 = Z2 = 0.500∟81.919°
Also, adding the total zero sequence impedance (transformer zero sequence impedance)
going to the fault point and considering the transformer delta-wye construction, yields to;
Z0 = ZTR = 0.400∟80.538°
Z0 = 0.400∟80.538°
Therefore;
ZTH = Z1 + Z2 + Z0
ZTH = 2(0.500∟81.919°) + 0.400∟80.538°
ZTH = 1.400∟81.524°
Calculating ISLGF;
I1 = 1.0 / 1.400∟81.524°
I1 = 0.714∟-81.524°
If I0 = I1 = I2 = 0.714∟-81.524°
Then;
ISLGF = 3(0.714∟-81.524°) x 4183.698A
ISLGF = 8,965.599∟-81.524° ASYM
IBASE = 4183.698A
If ZTH = Z1 + Z2 + Z0
Then;
Z1 = ZUT + ZTR + ZCA = 0.100∟86.186° + 0.400∟80.538° + 0.004∟52.431°
Z1 = 0.503∟81.444°
If Z1 = Z2
Then;
Z1 = Z2 = 0.503∟81.444°
Also, adding the total zero sequence impedance (transformer zero sequence impedance)
going to the fault point and considering the transformer delta-wye construction, yields to;
Therefore;
ZTH = Z1 + Z2 + Z0
ZTH = 2(0.503∟81.444°) + 0.410∟80.176°
ZTH = 1.416∟81.077°
Calculating ISLGF;
I1 = 1.0 / 1.416∟81.077°
I1 = 0.706∟-81.077°
If I0 = I1 = I2 = 0.706∟-81.077°
Then;
ISLGF = 3(0.706∟-81.077°) x 4183.698A
ISLGF = 8,861.072∟-81.077° ASYM
Summary of the calculated short circuit currents
BUS ID kV Three phase fault (I3F) Single phase to ground fault (ISLGF)
Bus1 69 8367.400∟-86.186° ASYM 8,366.563∟-86.186° ASYM
Bus2 13.8 8,373.800∟-81.703° ASYM 8,965.599∟-81.524° ASYM
Bus3 13.8 8,317.491∟-81.444° ASYM 8,861.072∟-81.077° ASYM
Requirements
Then;
CT primary = 5 x 167.348 A / 3.5
CT primary = 239.068 A
Use 300:5
Then;
CT primary = 5 x 836.740 A / 3.5
CT primary = 1,195.342 A
Use 1400:5
3. For CT at Bus3-13.8kV
Use 1400:5
BUS ID kV CT Ratio
Bus1 69 300:5
Bus2 13.8 1400:5
Bus3 13.8 1400:5
For the coordination of Overcurrent relays, the extremely inverse (EI) curve/equation will be used
T = TD x 80 / (M2-1)
Where;
1. Setting of Relay-3
When calculating the settings for the relays situated at the end of the circuit i.e. Relay-3, the
minimum time dial setting can be selected, thus 0.05 will be used
2. Setting of Relay-2
Required TD setting;
M = Fault seen by the relay / Pick-up current
If;
Fault seen by the relay = 8,373.800 A
Pick-up current = 125% x Transformer secondary FLC x CT Ratio
Pick-up current = 125% x 836.740 = 1,045.925 A
TD = T21MJ4 x (M2-1) / 80
TD = 0.248 x (8.0062-1) / 80
TD = 0.196
Calculating operating time (T21MJ4-B) for a line to line fault;
Therefore;
T21MJ4-B = 0.196 x 80 / (5.2752-1)
T21MJ4-B = 0.333
3. Setting of Relay-1
The back-up to Relay-2 is obtained by considering the operating time of a line-to-line fault at
the 13.8kV side of the transformer T 51MJ4 = T21MJ4-B + CTI, thus;
Therefore;
M = 1,674.760 / 209.185 = 8.006
TD = T51MJ4 x (M2-1) / 80
TD = 0.533 x (8.0062-1) / 80
TD = 0.420