Professional Documents
Culture Documents
https://doi.org/10.1007/s10706-018-0756-8 (0123456789().,-volV)
(0123456789().,-volV)
ORIGINAL PAPER
Abstract The main access road of Mae Mao dam system specially designed to reduce the pore water
hydropower project, Chiang Mai province, Thailand, pressure of the weak plane layer. Rock bolts and rock
has failed during a sunny day. The question has been anchors were found to be uneconomical and unsuit-
raised of what might have triggered the failure. At the able. Probabilistic approach was used to optimize the
day of failure, the precipitation amount was very small engineering safety and construction cost.
and the accumulated rainfall amount in the past days
was also not significant to trigger the failure. Detail Keywords Slope stabilization Rock slope Cut
geotechnical investigations were carried out including slope Weak layer
the geological survey, seismic refraction survey, bore
holes drilling and various laboratory testing. The rock
found at site was Phyllitic and Quartzitic sandstone. It
appears that the engineering properties of Phyllitic 1 Introduction
sandstone are more susceptible for slope failure. Rock
and soil slope stability analysis have been done, Mae Mao hydropower project is located at Fang
however none of them was found to be the cause of district, Chiang Mai province. The general geology
failure. After carefully reexamining the geologic consists of Phyllitic sandstone and Quartzitic sand-
structure, it was found that there is a weak plane layer stone. After 24 years of construction (since 1986), the
that resulted in the failure. A suitable stabilization failure of the main access road to the dam has occurred
method has been selected as the economical remedy of (Figs. 1, 2). The factor causing the failure is unclear.
the slope failure. In this case, flattening the back slope Rainfall and seismic activity are the two possibilities
is the economic method along with the drainage suspected for the failure. However, the precipitation
amount was just 2 mm at the day of failure and the
accumulated rainfall amount for 4 days prior to the
S. Soralump (&) R. Isaroran S. Yangsanphu failure was just 59.2 mm (Fig. 3). The precipitation
Geotechnical Engineering Research and Development
threshold for landslide in Thailand is much larger than
Center Civil Engineering Department, Kasetsart
University, Bangkok, Thailand the records. Another possibility might be credited to
e-mail: soralump_s@yahoo.com the seismic activities around the site which was quite
R. Isaroran active during the past service period of the dam
e-mail: nuk.civil@gmail.com (Fig. 4). The site is located in 2B seismic hazard zone
S. Yangsanphu based on UBC. With the evidence of the seismic
e-mail: sirisartra_y@hotmail.com activities in the area, the seismic slope displacement
123
Geotech Geol Eng
6.0
5.0
MAGNITUDE (RICHTER)
4.0
3.0
2.0
1.0
0.0
77
79
81
83
85
87
89
91
93
95
97
99
01
03
05
07
19
19
19
19
19
19
19
19
19
19
19
19
20
20
20
20
DATE
2 Geologic Structures
123
Geotech Geol Eng
123
Geotech Geol Eng
123
Geotech Geol Eng
123
Geotech Geol Eng
40.0
35.0 13.5 m
10.6 m
5.3 m
Friction Angle (degree)
4.5 m 10.7 m
30.0
8.0 m (Recompact
weak layer)
25.0
9.3 m
4.9 m
20.0
BH1
9.7 m
15.0 BH2
BH3
10.0
0.0 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0
Cohesion (t/m2)
123
Geotech Geol Eng
1 50 20 10 40 14 5.6 26 1 0.26
2 10 20 2 20 14 2.8 22 1 0.22
3 50 20 10 40 14 5.6 26 1 0.26
4 10 20 2 20 14 2.8 22 1 0.22
5 50 20 10 40 14 5.6 26 1 0.26
6 20 20 4 30 14 4.2 22 1 0.22
7 50 20 10 40 14 5.6 26 1 0.26
8 20 20 4 30 14 4.2 22 1 0.22
9 50 20 10 40 14 5. 26 1 0.26
10 20 20 4 30 14 4.2 22 1 0.22
11 50 20 10 40 14 5.6 26 1 0.26
COV (%) from Phoon et al. 1995
123
Geotech Geol Eng
Table 4 Remedial cases Option no. Slope (Ver:Hor) Rock nail (W 9 H, m) Horizontal drain (W 9 H, m)
6 Probabilistic Approach for Remedial Decision and cost optimization. The relationship between
Probability of Failure (Pf, %) and Factor of safety
Probabilistic approach has been used to obtain the final (FS) has been plotted in Fig. 24.
shape of the cut slope to achieve engineering safety
123
Geotech Geol Eng
123
Geotech Geol Eng
the back analysis result in deterministic analysis, Hoek E, Bray JW (1981) Rock slope engineering, Revised 3 edn.
confirming the possible failure plane. The relationship The Institution of Mining and Metallurgy, London,
pp 341–351
between Pf and FS values of repair work in this project Mae Mao Hydropower Project (2006) Rainfall record data of
satisfied the risk level, which can be accepted based on mae mao hydropower project. Fang, Chiangmai
the service of this road. Mairaing M, Isaroranit R (2003) Slope stability analysis with
The probabilistic approach in this project shall KUslope Version 2.0., pp. 95–114. Foundation Engineer-
ing 2003 Past Present and Future. Sub-committee in
promote its use in the practical field and indirectly Geotechnical Engineering, Engineering Institute of Thai-
advocate extensive investigation in order to under- land, Bangkok
stand the uncertainty of geological and geotechnical Markland JT (1972) A useful technique for estimating the sta-
properties of slope. bility of rock slopes when the rigid wedge slide type of
failure is expected. Imperial College Rock Mechanics
Research Reprints, London
Acknowledgements The authors would like to thank Phoon K-K, Kulhawy FH, Grigoriu MD (1995) Reliability-
Department of Alternative Energy Development and based design of foundations for transmission line struc-
Efficiency and also the staff at Mae Mao hydropower project. tures. Report TR-105000, Electric Power Research Insti-
tute, Palo Alto, CA, 380 p
Romana M (1985) New adjustment rating for application of the
References bieniawski classification to slopes. In: Proceedings of the
international symposium rock mechanics mining civil
works. ISRM, Zacatecas, Mexico. pp 59–63
ASTM (2002) ASTM D5607 standard test method for per-
Santamarina JC, Altschaeffl AG, Chameau JL (1992) Reliability
forming laboratory direct shear strength tests of rock
of slopes incorporating qualitative information. Trans-
specimens under constant normal force. ASTM Standards
portation Research Board, Washington
(Vol. 04.08). American Society for Testing and Materials,
Silva F, Lambe TW, Marr WA (2008) Probability and risk of
Philadelphia
slope failure. J Geotech Geoenviron Eng. https://doi.org/
Bieniawski ZT (1973) Engineering classification of jointed rock
10.1061/(asce)1090-0241(2008)134:12(1691). The Mete-
masses. Trans South Afr Instit Civ Eng 15:335–344
orological Department. 2006. Earthquake Report. Avail-
FHWA (2006) Soils and foundations. Referenece manual-vol.1.
able source
US Department of Transportaion, Federal Highway
Thai Meteorological Department (2007). http://www.tmd.go.th/
Administration, Washington
Hagiwara T, Omoto S (1939) Land creep at Mt. Tyausu-yama.
Determination of slip plane by seismic prospecting. Bull
Earthq Res Inst Bull 17:118–137 Publisher’s Note Springer Nature remains neutral with regard
to jurisdictional claims in published maps and institutional
affiliations.
123