Professional Documents
Culture Documents
1 of 4
DEVELOPMENTCONSULTANTS
PRIVATE LIMITED
Reviewed for genera all conformance with Contra
act
ct
drawingsand specifications.
ACTION : 5
1 Approved 4 Disapproved.
Approved ex cept as
For information/reference
2 noted. Forward final 5 only.
drawing.
Approved ex cept as Information category with
3 noted. Resubmission 6 comments. Resubmission
EARTHING SYSTEMS
V - Verification
Verification S R - Si tte
e re g
giis te
te r P .O
.O - Pu rrc
c ha
ha s
se
e O rd
rd e
err I MI
MI R - I n
nw
waarrd Ma te
te rrii al
al I n
ns
sppe
eccttion R ep
epo rrtt
RW-Random Witness PR-Protocol TR-Test report FITP - Field Inspection And Test Plan DOCUMENT NO : BGR/PPD/208/EL/FQP/0553
BGR/PPD/208/EL/FQP/0553
A - An Activity checked & Cleared by Owner QA/QC / C - An Activity checked & Cleared by BGRESL Execution
Execution / Sub Contractor REVISION : 00
BGRESL QA/QC
2 of 4
Rev No : 00
CUSTOMER: ODISHA POWER GENERATION CORPORATION
Date : 13.01.2015 LIMITED
Inspecting Agency
Quantum/
Class of Ref documents & Format of
S. NO
NO Item /
/C
Component & O p
pe
eration Type of check Frequency Remarks
Check Acceptance std Record
of check SUB
BGRESL OPGCL
Contractor
1.0 Receipt
available
etc )
packing list
2.0 STORAGE
up
3 of 4
Rev No : 00
CUSTOMER: ODISHA POWER GENERATION CORPORATION
Date : 12.01.2015 LIMITED
respective area
Ensure that the ground grid of the respective
area is installed at a de
depth
pth of not less than
3.4 B Measurement 100% Check L ist P W RW
1000mm below finished grade during
installation
verify the installation of Earth
OPGC Witness is
3.5 Electrodes(auxiliary) during installation & pits B Visual 100% Check List P W RW
only for earth pits
after installation at specifed points
Appd Drg /Method
Ensure that the Ground conductors welded Statement
joints above and below ground(Before back
3.6 C Visual Random Check List P W
filling) are coated with 2 coats of anti
….
corrosive paintings
3.7 Ensure the availability of riser projecting 300 C Measurement 100% Check L ist P W
mm above ground at specified points
…
4 of 4
AREA DATE
ELEVATION REPORT NO
DRAWING NO
Check that the ground grid of the respective area is installed at a depth of not less
4
than 1000mm below finished grade during installation
verify the installation of Earth Electrodes during installation & pits after installation at
5
specifed points
Verify that the Ground conductors welded joints above and below ground(Before back
6
filling) are coated with 2 coats of an
anti
ti corrosive paintings
7 Check the availability of riser projecting 300 mm above ground at specified points
10 Verify the availabilty of grid extension for connecting to the main plant grid
Measurement of Earth pit resistance with and without grid (Test report shall be
11
enclosed)
BGRESL OPGCL