You are on page 1of 4

 

1 of 4

 
DEVELOPMENTCONSULTANTS
PRIVATE LIMITED
 
Reviewed for genera all conformance with Contra
act
ct
drawingsand specifications.
 
 ACTION : 5
 
1  Approved 4 Disapproved.

 Approved ex cept as
For information/reference
2 noted. Forward final 5 only.
drawing.
 Approved ex cept as Information category with
3 noted. Resubmission 6 comments. Resubmission

BGR ENERGY SYSTEMS LIMITED required. required.

 Approval of Contract documents by the Cons ultant shall


not relieve the Seller of his responsibility for any errors
and fulfilment of Contract requirements.
 

  POWER PROJECTS DIVISION Digitally signed by Shouvik


Patari
DN: cn=Shouvik Patari,
  PROJECT : 2 X 660 MW IB TPS, JHARSUGUDA o=DCPL, ou=DCPL,
  FIELD INSPECTION AND TEST PLAN & CHECK LIST email=shouvikp@in.dclgroup.
com, c=IN
Date: 2015.01.28 12:06:04
  FOR  +05'30'

  EARTHING SYSTEMS

PREPARED BY  REVIEWED BY   APPROVED BY 

D.ARUN BHARATH K. SUBRAMANIAN K.KALYANARAMAN

P - Perform IR-Inspection Report GRN-Goods receipt note H-Hold

W - Witness S- Surveillance TR- Test Report LB-Log Book 

 V - Verification
Verification S R - Si tte
e re g
giis te
te r P .O
.O - Pu rrc
c ha
ha s
se
e O rd
rd e
err I MI
MI R - I n
nw
waarrd Ma te
te rrii al
al I n
ns
sppe
eccttion R ep
epo rrtt

R - Review S - Surveillance D .C - Delivery Challan IRN - Inspection Release Note

RW-Random Witness PR-Protocol TR-Test report FITP - Field Inspection And Test Plan DOCUMENT NO : BGR/PPD/208/EL/FQP/0553
BGR/PPD/208/EL/FQP/0553

 A - An Activity checked & Cleared by Owner QA/QC /  C - An Activity checked & Cleared by BGRESL Execution
Execution / Sub Contractor REVISION : 00
BGRESL QA/QC

B - An Activity checked & Cleared by Owner Executive Group


Group / BGRESL Execution DATE : 13.01.2015
 

2 of 4

FIELD INSPECTION AND TEST PLAN & CHECK LIST


Package : EARTHING SYSTEM
PROJECT: 2X660 MW IB THERMAL POWER STATION
Doc No :BGR/PPD/208/EL/FQP/0553

Rev No : 00
CUSTOMER: ODISHA POWER GENERATION CORPORATION
Date : 13.01.2015 LIMITED

Inspecting Agency
Quantum/
Class of Ref documents & Format of
S. NO
NO Item /
/C
Component & O p
pe
eration Type of check  Frequency Remarks
Check   Acceptance std Record
of check  SUB
BGRESL OPGCL
Contractor

1.0 Receipt

 Verify MDCC issued by BGR/OPGC(If


 PO,MDCC & LR/All the
applicable), BGR&OPGC verified test
1.1 C  Visual 100% documents shall be IMIR  P
reports,Dispatch documents (LR & packing List
  ….   ….

available
etc )

 Veirfy the Dimesions of the Earthing


Random (3 PO,MDCC,IRN/ Material
1.2 Conductors & Down conductors (MS Rods, C Measurement IMIR  P
samples /lot) shall confirm to IRN
  ….   ….

Galvanised MS Flats, Etc)

 Verify the toatal Quantity in Kg/Mtons in


1.3 weighing Bridge with truck and tally with C Meaurement 100% MDCC,IRN IMIR     … P   ….

packing list

 Veirfy the materials such as welding ele


ectrodes
ctrodes
1.4 C  Visual 100% PO,MDCC/ IRN IMIR  P
and anti corrossion paints
  …   ….

2.0 STORAGE

Ensure that Earthing Conductors are stored in


2.1 a covered space/outdoor in a well-drain
well-drained
ed & C  Visual 100% FITP   … ,,, P   ….

raised area with firrm


m surface

Ensure that the storage area is free from


2.2 C  Visual 100% FITP ,,, P
water logging.
  …   ….

Ensure that the material is stored seperately


2.3 as per the type and dimensions and not mixed C  Visual 100% FITP   … ,,, P   ….

up

Consumables such as welding electrodes and


2.4  Anti corrosive painst shall be stored well C   …. 100% FITP   … ,,, P   ….

ventilated dry indoor area


 

3 of 4

FIELD INSPECTION AND TEST PLAN & CHECK LIST


Package : EARTHING SYSTEM
PROJECT: 2X660 MW IB THERMAL POWER STATION
Doc No :BGR/PPD/208/EL/FQP/0553

Rev No : 00
CUSTOMER: ODISHA POWER GENERATION CORPORATION
Date : 12.01.2015 LIMITED

Quantum/ Inspecting Agency


Class of Ref documents & Format of
S. NO
NO Item /
/C
Component & O p
pe
eration Type of check  Frequency SUB Remarks
Check   Acceptance std Record BGRESL OPGCL
of check  Contractor

3.0 ERECTION /INSTALLATION

Ensure the availability of approved Earthing


3.1 C Visual 100% Check L ist P   ….

layouts of the respective area


  ….

Ensure that the approved materials(type and


3.2 C Visual Random Check Check L ist P   ….

diemensions) are mobilized


  ….

Ensure the availability of "Work permit" for the


3.3 C Visual 100% Check L ist P P   ….

respective area
Ensure that the ground grid of the respective
area is installed at a de
depth
pth of not less than
3.4 B Measurement 100% Check L ist P W RW
1000mm below finished grade during
installation
verify the installation of Earth
OPGC Witness is
3.5 Electrodes(auxiliary) during installation & pits B  Visual 100% Check List P W RW
only for earth pits
after installation at specifed points
 Appd Drg /Method
Ensure that the Ground conductors welded Statement
 joints above and below ground(Before back
3.6 C  Visual Random Check List P W
filling) are coated with 2 coats of anti
  ….

corrosive paintings

3.7 Ensure the availability of riser projecting 300 C Measurement 100% Check L ist P W
mm above ground at specified points
  …

Ensure the availability of two risers for each


3.8 floor and two distinctive earth terminals for B  Visual 100% Check List P W W
each equipments
Ensure the connection of internconnected
3.9 B  Visual 100% Check List P W W
earth flats above ground with risers

Ensure the availabilty


lty of grid extension for
3.10 B  Visual 100% Check List P W W
connecting to the main plant grid

4.0 TESTING OF INSTALLATION

Measurement of Earth pit resistance with and


4.1  A  Testing 100% EF -02 P W W
without grid  Appd Drg /Method
Statement
4.2  Verification of Earthing system continuity  A  Testing 100% EF -03 P W W
 

4 of 4

FIELD CHECK LIST FOR EARTHING SYSTEM

 AREA DATE

ELEVATION REPORT NO

DRAWING NO

SL.No Description of Check  OBSERVATION /  NA Remarks

1  Verify the availability of approved Earthing layouts of the respective area

2 Check that the approved materials(type and diemensions) are mobilized

3  Verify the availability of "Work permit" for the respective area

Check that the ground grid of the respective area is installed at a depth of not less
4
than 1000mm below finished grade during installation

verify the installation of Earth Electrodes during installation & pits after installation at
5
specifed points

 Verify that the Ground conductors welded joints above and below ground(Before back
6
filling) are coated with 2 coats of an
anti
ti corrosive paintings

7 Check the availability of riser projecting 300 mm above ground at specified points

Check the availability of two risers for each floor


floor and two distinctive earth terminals for each
8 equipments

9  Verify the connection of internconnected


internconnected earth flats above ground with risers

10  Verify the availabilty of grid extension for connecting to the main plant grid

Measurement of Earth pit resistance with and without grid (Test report shall be
11
enclosed)

12  Verification of Earthing system continuity (Test report shall be enclosed)

BGRESL OPGCL

You might also like