INTERNAL (PFCO)

INTERIOR PAINTING WORKS


PAINTER ESTRERA RENATO
PAINTING OF PUNCHLIST WALL AT 9TH FLOOR
PAINTER TESEFORO DINDO
PAINTER ARELLANO SANDINO PREPARATION FOR PAINTING OF CEILING AT 9TH FL
PAINTER RAMOS ROQUE PREPARATION FOR PAINTING OF WALL AT 9TH FLO
PAINTER DICDICAN JAMES ROY SEALANT APPLICATION FOR KITCHEN CABINET AT
PAINTER NABARTEY EDGAR PREPARATION FOR PAINTING OF WALL AT 10TH FLO
PAINTER CERIZO BERNARDO PREPARATION FOR PAINTING OF WALL AT 10TH FLO
PAINTER LERRY ALBERTO CLEANING AND PAINTING OF PVC DOOR JAMB AT
PAINTER ORILLE RONALD PREPARATION AND TERMINATION PAINTING WORKS OF UNIT AN
PAINTER CARINO JOSHUA 1102
PAINTER DEJARME JIMBOY PREPARATION AND TERMINATION PAINTING WORKS OF T&B A
PAINTER JOSOL PEDRO PREPARATION AND TERMINATION PAINTING WORKS OF UNIT AN
PAINTER CARABANO TERRA 1106
PAINTER MANGUERA BENEDICTO PREPARATION AND TERMINATION PAINTING WORKS OF T&B A
PAINTER VALDEZ JAYVE PREPARATION AND TERMINATION PAINTING WORKS OF T&B A
PAINTER LETACIO LEO PREPARATION AND TERMINATION PAINTING WORKS OF UNIT AN
PAINTER DAPITAN EDCEL 1202
PAINTER FORTIN GARY PREPARATION AND TERMINATION PAINTING WORKS OF UNIT AN
PAINTER ABRIGO JENNIE 1205
PAINTER BUTIHIN LINO
PREPARATION AND TERMINATION PAINTING WORKS OF UNIT AN
PAINTER PAPISTOL JAYSON 1206
PAINTER MORETE RUTHER
PAINTER DAGOC JUNMAR PREPARATION AND TERMINATION PAINTING WORKS OF UNIT AN
PAINTER OMAPAS RENEBOY 1209
PAINTER MAURICIO JEFFREY PREPARATION AND TERMINATION PAINTING WORKS OF UNIT AN
PAINTER GAMALO RODRIGO 1210
PAINTER SENIDO JERICK PREPARATION AND TERMINATION PAINTING WORKS OF UNIT AN
PAINTER RECOTE REX 1212
PAINTER LANETE MARIANO PREPARATION AND TERMINATION PAINTING WORKS OF UNIT AN
PAINTER DEINLA RONELO 1215
PAINTER SUBANG LORENZO PREPARATION FOR PAINTING OF WALL AT 12TH FLO
PAINTER HITALIA RONALD PREPARATION AND TERMINATION PAINTING WORKS OF UNIT A

CARPENTRY WORKS
3 CARPENTER BABO SOKIB
4 CARPENTER BUGAAY ARCHIE
5 CARPENTER DAJARME OSCAR INSTALLATION OF PVC DOOR 10TH TO 11TH FLOO
CARPENTER MARCIAL JUVY
CARPENTER RIVERA RONALD
6 CARPENTER HADJIRUDDINHELMAN ABSENT
CARPENTER MANAYUBA GONZALO
7 CARPENTER PASCUAL MICHAEL INSTALLATION OF BOARD UP AT 12TH FLOOR UNIT
CARPENTER BONGAO EDGE ROY
CARPENTER NAVARRO FERDINAN INSTALLATION OF BOARD UP AT 11TH FLOOR H
2 CARPENTER ABUNIDAR ARABANI

VINYL WORKS
211 VINYL INSTALLER BARADAS JOHN ERIC PREPARATION FLOORING AT 12TH FLOOR U
212 VINYL INSTALLER CASICO FLORO GROUT APPLICATION BALCONY AND T&B AT 10TH F
214 VINYL INSTALLER GANATE MITCHELE
PREPARATION FLOORING AT 11TH FLOOR UN
217 VINYL INSTALLER MARK JOSEPH CAMO
213 VINYL INSTALLER DAWENG JON JON PREPARATION FLOORING AT 12TH FLOOR U
216 VINYL INSTALLER LUMONGSOD JEFFREY PREPARATION FLOORING AT 12TH FLOOR U
218 VINYL INSTALLER ROCA MARK ANTHONY PREPARATION FLOORING AT 12TH FLOOR U
215 VINYL INSTALLER GARZON SHELA ABSENT

TILE WORKS
104 TILES SETTER QUINTERO FELIX RECTIFICATION OF TILES T&B AT 9TH FLOOR
105 TILES SETTER SANTISAS SAMMIE RECTIFICATION OF TILES BALCONY AT 10TH FLOO
107 TILES SETTER VICTORIA JULLIUS RECTIFICATION OF TILES BALCONY AT 11TH FLOO
TILES SETTER GANOZA SAMMY RECTIFICATION OF TILES T&B AT 10TH FLOOR
TILES SETTER LIBANDING REYNAN RECTIFICATION OF TILES BALCONY AT 10TH FLO
103 TILES SETTER ARAÑA CRISTHOPER TILES INSTALLATION ELEVATOR LOBBY AT 14T
106 TILES SETTER TALES FRANSISCO LEO ABSENT

PLUMBING WORKS
PLUMBER GONZALVO JONMAL PIPE INST. BALCONY DRAIN 10 - 11 FLOO
PLUMBER TROXON ROBERT
PLUMBER VALDEZ MARK ANTHONY PIPE INST. BALCONY / AIRCON DRAIN SWIMMING
PLUMBER LAURITO QUIJANO
PLUMBER REFORSADO REGIE
CHIPPING PREPARATION FOR INST. PIPING OF LATERAL SANITAR
PLUMBER REFORSADO RAY FLOOR.
PLUMBER ASDUCO RECARDO
PLUMBER CAMA RENALDO INST. OF STAB OUT FOR LAVATORY AT 17TH
PLUMBER BUMDALIAN EDZEL
INST. OF WATER LINE LOOPING AND SUPPLY FOR T&B
PLUMBER FLORES PAUL
PLUMBER ALDUNEZA ALDRINO
PLUMBER HURANCIA ARVIN INST. OF HUNGER FOR SANITARY AND WATER LINE A
PLUMBER RYAN
FOREMAN NEAR CARLO SITE SUPERVISION

HOUSE KEEPING WORKS


HOUSEKEEPER TALAY APPLE
CLEANING OF UNIT, BALCONY AND T&B AT UNIT 1
CLEANING OF UNIT, BALCONY AND T&B AT UNIT 1
HOUSEKEEPER ABULAG JANELLE
HOUSEKEEPER LAURENTE FLOREBELLE
CLEANING OF UNIT, BALCONY AND T&B AT UNIT 10
HOUSEKEEPER ALVIAR CLAUDINE
HOUSEKEEPER TUTOR ANALYN CLEANING OF UNIT, BALCONY AND T&B AT UN
HOUSEKEEPER TANNAS EMILY
HOUSEKEEPER LAMBOL MARICHO CLEANING OF UNIT, BALCONY AND T&B AT UNIT 923,
HOUSEKEEPER VILLANUEVA ARLYN
HOUSEKEEPER CARINO AILEEN
CLEANING OF UNIT, BALCONY AND T&B AT UNIT 11
HOUSEKEEPER PAZARDOZA ABIGAIL
HOUSEKEEPER DELA CRUZ LIZA MARIE
CLEANING OF UNIT, BALCONY AND T&B AT UNIT 1120
HOUSEKEEPER ESTAPIA MARIA SALNE
HOUSEKEEPER VALLE SNOOKY
CLEANING OF UNIT, BALCONY AND T&B AT HALLWAY, U
HOUSEKEEPER BUNAO LORNA
(PFCO)
ING WORKS

PAINTING OF PUNCHLIST WALL AT 9TH FLOOR UNIT 923

ARATION FOR PAINTING OF CEILING AT 9TH FLOOR HALLWAY


PARATION FOR PAINTING OF WALL AT 9TH FLOOR HALLWAY
LANT APPLICATION FOR KITCHEN CABINET AT 10TH FLOOR
ARATION FOR PAINTING OF WALL AT 10TH FLOOR UNIT 1016
ARATION FOR PAINTING OF WALL AT 10TH FLOOR UNIT 1023
ANING AND PAINTING OF PVC DOOR JAMB AT 10TH FLOOR
TERMINATION PAINTING WORKS OF UNIT AND T&B AT 11TH FLOOR UNIT
1102
ND TERMINATION PAINTING WORKS OF T&B AT 11TH FLOOR UNIT 1103
TERMINATION PAINTING WORKS OF UNIT AND T&B AT 11TH FLOOR UNIT
1106
ND TERMINATION PAINTING WORKS OF T&B AT 11TH FLOOR UNIT 1110
ND TERMINATION PAINTING WORKS OF T&B AT 11TH FLOOR UNIT 1117
TERMINATION PAINTING WORKS OF UNIT AND T&B AT 12TH FLOOR UNIT
1202
TERMINATION PAINTING WORKS OF UNIT AND T&B AT 12TH FLOOR UNIT
1205

TERMINATION PAINTING WORKS OF UNIT AND T&B AT 12TH FLOOR UNIT


1206

TERMINATION PAINTING WORKS OF UNIT AND T&B AT 12TH FLOOR UNIT


1209
TERMINATION PAINTING WORKS OF UNIT AND T&B AT 12TH FLOOR UNIT
1210
TERMINATION PAINTING WORKS OF UNIT AND T&B AT 12TH FLOOR UNIT
1212
TERMINATION PAINTING WORKS OF UNIT AND T&B AT 12TH FLOOR UNIT
1215
ARATION FOR PAINTING OF WALL AT 12TH FLOOR UNIT 1219
ND TERMINATION PAINTING WORKS OF UNIT AT 12TH FLOOR UNIT 1226

WORKS

STALLATION OF PVC DOOR 10TH TO 11TH FLOOR ALL UNIT

ABSENT
ALLATION OF BOARD UP AT 12TH FLOOR UNIT 5, 6, 17 TO 24

NSTALLATION OF BOARD UP AT 11TH FLOOR HALLWAY

ORKS
PREPARATION FLOORING AT 12TH FLOOR UNIT 21
UT APPLICATION BALCONY AND T&B AT 10TH FLOOR UNIT 22

PREPARATION FLOORING AT 11TH FLOOR UNIT 8 & 10

PREPARATION FLOORING AT 12TH FLOOR UNIT 29


PREPARATION FLOORING AT 12TH FLOOR UNIT 20
PREPARATION FLOORING AT 12TH FLOOR UNIT 17
ABSENT

RKS
RECTIFICATION OF TILES T&B AT 9TH FLOOR UNIT 22
ECTIFICATION OF TILES BALCONY AT 10TH FLOOR UNIT 16
ECTIFICATION OF TILES BALCONY AT 11TH FLOOR UNIT 27
RECTIFICATION OF TILES T&B AT 10TH FLOOR UNIT 25
ECTIFICATION OF TILES BALCONY AT 10TH FLOOR UNIT 6
TILES INSTALLATION ELEVATOR LOBBY AT 14TH FLOOR
ABSENT

WORKS
PIPE INST. BALCONY DRAIN 10 - 11 FLOOR

E INST. BALCONY / AIRCON DRAIN SWIMMING POOL SIDE

ATION FOR INST. PIPING OF LATERAL SANITARY AND LAVATORY AT 17TH


FLOOR.

INST. OF STAB OUT FOR LAVATORY AT 17TH FLOOR

F WATER LINE LOOPING AND SUPPLY FOR T&B AT 16TH FLOOR

OF HUNGER FOR SANITARY AND WATER LINE AT 16TH FLOOR

SITE SUPERVISION

G WORKS

ANING OF UNIT, BALCONY AND T&B AT UNIT 1026 AND 714


ANING OF UNIT, BALCONY AND T&B AT UNIT 1026 AND 714

NING OF UNIT, BALCONY AND T&B AT UNIT 1027 AND 1028

CLEANING OF UNIT, BALCONY AND T&B AT UNIT 1029

NG OF UNIT, BALCONY AND T&B AT UNIT 923, 1126 AND 1103

NING OF UNIT, BALCONY AND T&B AT UNIT 1121 AND 1020

NG OF UNIT, BALCONY AND T&B AT UNIT 1120, 1108 AND 825

OF UNIT, BALCONY AND T&B AT HALLWAY, UNIT 1112 AND 1109