DAILY REPORT - MICROTUNELLING WORKS

COUNTRY QATAR ☒ KUWAIT☐ OMAN ☐ UAE☐ PROJECT CODE QA-1064


DATE: 09/01/2021 CLASSIFICATION QTY CLASSIFICATION QTY CLASSIFICATION QTY Tunnel Face
REPORT NO.: 005 OPERATION MANAGER 1 PIPE FITTER 12 RENTAL CTA 0

Very Hard Rock >

MANPOWER & EQUIPMENT


PROJECT NO.: QA-1064 TECHNICAL ADVISOR 0 FOREMAN 4 TBM EQUIPMENT 2 250 Mpa


PROJECT NAME:
Construction of Link Roads Adjacent to Al
CONSTRUCTION MANAGER 0 MECHANIC 2 SEPARATION UNIT 2 Hard Rock (100 -
Khor Expressway 250 Mpa)
LOCATION: Al Khor HR MANAGER 0 NDM HKN TECHNICIAN 0 GENERATOR 2

Medium Rock (50 -
CLIENT: ASHGHAL ADMINSTRATION OFFICER 0 HSEQ OFFICER 4 PUMP 4 100 Mpa)
CONTRACTOR: Tekfen SITE SUPERVISOR/ENGINEER 1 WATCHMAN 4 TANK 4

Soft Rock ( < 50
PROJECT IN CHARGE: Berly Thomas TBM OPERATOR 4 DRIVER 2 CONTAINER 4 Mpa)
CRANE OPERATOR 4 TON DRIVER 2 CABIN 2
SIGNED: Clay Conditions ☐
SURVEYOR 1

MT WORKS FROM 1000 LENGTH PIPE ID N SHIFT Accumulative


DONE PIT
MH-26 TO PIT MH-25 AVN
(m)
34.333 (mm)
1000 D SHIFT (m) 0 (m)
0 (m)
30
M-1538

D/SHIFT
PIPE NUMBER
N/SHIFT
PIPE TYPE
JACKING PRESSURE (ton)
INSTALLED LENGTH

MAXIMUM HOR + 0
DAILY TOTAL MAXIMUM JACKING OTHER
0 0 - BENTONITE USE (Liters)
PRODUCTION (m) PRESSURE (ton) DRIFTING (mm) VER + 0 CHEMICALS
-

GROUTING FROM SHAFT TO SHAFT LENGTH (m) DAY SHIFT QTY. (m3) NIGHT SHIFT QTY (m3) TOTAL (m3)

INSERTION FROM SHAFT TO SHAFT LENGTH(m) DAY SHIFT QTY. (m) NIGHT SHIFT QTY (m) TOTAL (m)

Activity D N Activity D N Activity D N Delay D N Delay D N Delay D N

FABRICATION WORKS MOBILIZATION PULL BACK SERVICES X X EQUIPMENT BREAKDOWNS SHAFT NOT READY SLURRY/SPOIL REMOVAL

SHUTTERING B/WALL SET JACKING FRAME ENTRANCE RING DETAILS DEWATERING ISSUES PIPES ON SITE
LOWER MACHINE / POURING CONCRETE WALL
SLURRY TANK SET UP LAUNCH MACHINE MAINTENANCE OTHER
CONNECT SERVICES
TUNNELLING COMPLETED DRIVE TAKE OUT MACHINE Proposed work for next day and comments (include other delay explanation)
TURN AROUND BREAKING B/ WALL DE-MOBILIZATION Day: Drive completed
PIPE RE-JACKING CASTING F/WALL SHUTTERING F/WALL Night: Drive completed

Document Name: Daily Report - Microtunelling Works R04 Page No: 1 of 1


Document Number: BQPE 002 Revised on: 05-11-2019
DAILY REPORT - MICROTUNELLING WORKS
COUNTRY QATAR ☒ KUWAIT☐ OMAN ☐ UAE☐ PROJECT CODE QA-1064
DATE: 08/01/2021 CLASSIFICATION QTY CLASSIFICATION QTY CLASSIFICATION QTY Tunnel Face
REPORT NO.: 004 OPERATION MANAGER 0 PIPE FITTER 0 RENTAL CTA 0

Very Hard Rock >

MANPOWER & EQUIPMENT


PROJECT NO.: QA-1064 TECHNICAL ADVISOR 0 FOREMAN 0 TBM EQUIPMENT 2 250 Mpa


PROJECT NAME:
Construction of Link Roads Adjacent to Al
CONSTRUCTION MANAGER 0 MECHANIC 0 SEPARATION UNIT 2 Hard Rock (100 -
Khor Expressway 250 Mpa)
LOCATION: Al Khor HR MANAGER 0 NDM HKN TECHNICIAN 0 GENERATOR 2

Medium Rock (50 -
CLIENT: ASHGHAL ADMINSTRATION OFFICER 0 HSEQ OFFICER 0 PUMP 4 100 Mpa)
CONTRACTOR: Tekfen SITE SUPERVISOR/ENGINEER 0 WATCHMAN 4 TANK 4

Soft Rock ( < 50
PROJECT IN CHARGE: Berly Thomas TBM OPERATOR 0 DRIVER 0 CONTAINER 4 Mpa)
CRANE OPERATOR 0 TON DRIVER 0 CABIN 2
SIGNED: Clay Conditions ☐
SURVEYOR 0

MT WORKS FROM 1000 LENGTH PIPE ID N SHIFT Accumulative


DONE PIT
MH-26 TO PIT MH-25 AVN
(m)
34.333 (mm)
1000 D SHIFT (m) 0 (m)
0 (m)
30
M-1538

D/SHIFT
PIPE NUMBER
N/SHIFT
PIPE TYPE
JACKING PRESSURE (ton)
INSTALLED LENGTH

MAXIMUM HOR + 0
DAILY TOTAL MAXIMUM JACKING OTHER
0 0 - BENTONITE USE (Liters)
PRODUCTION (m) PRESSURE (ton) DRIFTING (mm) VER + 0 CHEMICALS
-

GROUTING FROM SHAFT TO SHAFT LENGTH (m) DAY SHIFT QTY. (m3) NIGHT SHIFT QTY (m3) TOTAL (m3)

INSERTION FROM SHAFT TO SHAFT LENGTH(m) DAY SHIFT QTY. (m) NIGHT SHIFT QTY (m) TOTAL (m)

Activity D N Activity D N Activity D N Delay D N Delay D N Delay D N

FABRICATION WORKS MOBILIZATION PULL BACK SERVICES EQUIPMENT BREAKDOWNS SHAFT NOT READY SLURRY/SPOIL REMOVAL

SHUTTERING B/WALL SET JACKING FRAME ENTRANCE RING DETAILS DEWATERING ISSUES PIPES ON SITE
LOWER MACHINE / POURING CONCRETE WALL
SLURRY TANK SET UP LAUNCH MACHINE MAINTENANCE OTHER
CONNECT SERVICES
TUNNELLING COMPLETED DRIVE TAKE OUT MACHINE Proposed work for next day and comments (include other delay explanation)
TURN AROUND BREAKING B/ WALL DE-MOBILIZATION Day: Day off
PIPE RE-JACKING CASTING F/WALL SHUTTERING F/WALL Night: Day off

Document Name: Daily Report - Microtunelling Works R04 Page No: 1 of 1


Document Number: BQPE 002 Revised on: 05-11-2019
DAILY REPORT - MICROTUNELLING WORKS
COUNTRY QATAR ☒ KUWAIT☐ OMAN ☐ UAE☐ PROJECT CODE QA-1064
DATE: 07/01/2021 CLASSIFICATION QTY CLASSIFICATION QTY CLASSIFICATION QTY Tunnel Face
REPORT NO.: 003 OPERATION MANAGER 1 PIPE FITTER 12 RENTAL CTA 0

Very Hard Rock >

MANPOWER & EQUIPMENT


PROJECT NO.: QA-1064 TECHNICAL ADVISOR 0 FOREMAN 4 TBM EQUIPMENT 2 250 Mpa


PROJECT NAME:
Construction of Link Roads Adjacent to Al
CONSTRUCTION MANAGER 0 MECHANIC 2 SEPARATION UNIT 2 Hard Rock (100 -
Khor Expressway 250 Mpa)
LOCATION: Al Khor HR MANAGER 0 NDM HKN TECHNICIAN 0 GENERATOR 2

Medium Rock (50 -
CLIENT: ASHGHAL ADMINSTRATION OFFICER 0 HSEQ OFFICER 4 PUMP 4 100 Mpa)
CONTRACTOR: Tekfen SITE SUPERVISOR/ENGINEER 1 WATCHMAN 4 TANK 4

Soft Rock ( < 50
PROJECT IN CHARGE: Berly Thomas TBM OPERATOR 4 DRIVER 2 CONTAINER 4 Mpa)
CRANE OPERATOR 4 TON DRIVER 2 CABIN 2
SIGNED: Clay Conditions ☐
SURVEYOR 1

MT WORKS FROM 1000 LENGTH PIPE ID N SHIFT Accumulative


DONE PIT
MH-26 TO PIT MH-25 AVN
(m)
34.333 (mm)
1000 D SHIFT (m) 9 (m)
9 (m)
30
M-1538

D/SHIFT 3 4 5
PIPE NUMBER
N/SHIFT 6 7 8
PIPE TYPE Concrete Concrete Concrete Concrete Concrete Concrete
JACKING PRESSURE (ton) 40 40 40 40 40 40
INSTALLED LENGTH 3 3 3 3 3 3

MAXIMUM HOR + -10


DAILY TOTAL MAXIMUM JACKING OTHER
18 40 - BENTONITE USE (Liters)
PRODUCTION (m) PRESSURE (ton) DRIFTING (mm) VER + +17 CHEMICALS
-

GROUTING FROM SHAFT TO SHAFT LENGTH (m) DAY SHIFT QTY. (m3) NIGHT SHIFT QTY (m3) TOTAL (m3)

INSERTION FROM SHAFT TO SHAFT LENGTH(m) DAY SHIFT QTY. (m) NIGHT SHIFT QTY (m) TOTAL (m)

Activity D N Activity D N Activity D N Delay D N Delay D N Delay D N

FABRICATION WORKS MOBILIZATION PULL BACK SERVICES EQUIPMENT BREAKDOWNS SHAFT NOT READY SLURRY/SPOIL REMOVAL

SHUTTERING B/WALL SET JACKING FRAME ENTRANCE RING DETAILS DEWATERING ISSUES PIPES ON SITE
LOWER MACHINE / POURING CONCRETE WALL
SLURRY TANK SET UP LAUNCH MACHINE MAINTENANCE OTHER
CONNECT SERVICES
TUNNELLING X X COMPLETED DRIVE TAKE OUT MACHINE X Proposed work for next day and comments (include other delay explanation)
TURN AROUND BREAKING B/ WALL DE-MOBILIZATION Day: Remove equipment inside tunnel
PIPE RE-JACKING CASTING F/WALL SHUTTERING F/WALL Night: Remove equipment inside tunnel

Document Name: Daily Report - Microtunelling Works R04 Page No: 1 of 1