Professional Documents
Culture Documents
☐
PROJECT NAME:
Construction of Link Roads Adjacent to Al
CONSTRUCTION MANAGER 0 MECHANIC 2 SEPARATION UNIT 2 Hard Rock (100 -
Khor Expressway 250 Mpa)
LOCATION: Al Khor HR MANAGER 0 NDM HKN TECHNICIAN 0 GENERATOR 2
☐
Medium Rock (50 -
CLIENT: ASHGHAL ADMINSTRATION OFFICER 0 HSEQ OFFICER 4 PUMP 4 100 Mpa)
CONTRACTOR: Tekfen SITE SUPERVISOR/ENGINEER 1 WATCHMAN 4 TANK 4
☐
Soft Rock ( < 50
PROJECT IN CHARGE: Berly Thomas TBM OPERATOR 4 DRIVER 2 CONTAINER 4 Mpa)
CRANE OPERATOR 4 TON DRIVER 2 CABIN 2
SIGNED: Clay Conditions ☐
SURVEYOR 1
D/SHIFT
PIPE NUMBER
N/SHIFT
PIPE TYPE
JACKING PRESSURE (ton)
INSTALLED LENGTH
MAXIMUM HOR + 0
DAILY TOTAL MAXIMUM JACKING OTHER
0 0 - BENTONITE USE (Liters)
PRODUCTION (m) PRESSURE (ton) DRIFTING (mm) VER + 0 CHEMICALS
-
GROUTING FROM SHAFT TO SHAFT LENGTH (m) DAY SHIFT QTY. (m3) NIGHT SHIFT QTY (m3) TOTAL (m3)
INSERTION FROM SHAFT TO SHAFT LENGTH(m) DAY SHIFT QTY. (m) NIGHT SHIFT QTY (m) TOTAL (m)
FABRICATION WORKS MOBILIZATION PULL BACK SERVICES X X EQUIPMENT BREAKDOWNS SHAFT NOT READY SLURRY/SPOIL REMOVAL
SHUTTERING B/WALL SET JACKING FRAME ENTRANCE RING DETAILS DEWATERING ISSUES PIPES ON SITE
LOWER MACHINE / POURING CONCRETE WALL
SLURRY TANK SET UP LAUNCH MACHINE MAINTENANCE OTHER
CONNECT SERVICES
TUNNELLING COMPLETED DRIVE TAKE OUT MACHINE Proposed work for next day and comments (include other delay explanation)
TURN AROUND BREAKING B/ WALL DE-MOBILIZATION Day: Drive completed
PIPE RE-JACKING CASTING F/WALL SHUTTERING F/WALL Night: Drive completed
☐
PROJECT NAME:
Construction of Link Roads Adjacent to Al
CONSTRUCTION MANAGER 0 MECHANIC 0 SEPARATION UNIT 2 Hard Rock (100 -
Khor Expressway 250 Mpa)
LOCATION: Al Khor HR MANAGER 0 NDM HKN TECHNICIAN 0 GENERATOR 2
☐
Medium Rock (50 -
CLIENT: ASHGHAL ADMINSTRATION OFFICER 0 HSEQ OFFICER 0 PUMP 4 100 Mpa)
CONTRACTOR: Tekfen SITE SUPERVISOR/ENGINEER 0 WATCHMAN 4 TANK 4
☐
Soft Rock ( < 50
PROJECT IN CHARGE: Berly Thomas TBM OPERATOR 0 DRIVER 0 CONTAINER 4 Mpa)
CRANE OPERATOR 0 TON DRIVER 0 CABIN 2
SIGNED: Clay Conditions ☐
SURVEYOR 0
D/SHIFT
PIPE NUMBER
N/SHIFT
PIPE TYPE
JACKING PRESSURE (ton)
INSTALLED LENGTH
MAXIMUM HOR + 0
DAILY TOTAL MAXIMUM JACKING OTHER
0 0 - BENTONITE USE (Liters)
PRODUCTION (m) PRESSURE (ton) DRIFTING (mm) VER + 0 CHEMICALS
-
GROUTING FROM SHAFT TO SHAFT LENGTH (m) DAY SHIFT QTY. (m3) NIGHT SHIFT QTY (m3) TOTAL (m3)
INSERTION FROM SHAFT TO SHAFT LENGTH(m) DAY SHIFT QTY. (m) NIGHT SHIFT QTY (m) TOTAL (m)
FABRICATION WORKS MOBILIZATION PULL BACK SERVICES EQUIPMENT BREAKDOWNS SHAFT NOT READY SLURRY/SPOIL REMOVAL
SHUTTERING B/WALL SET JACKING FRAME ENTRANCE RING DETAILS DEWATERING ISSUES PIPES ON SITE
LOWER MACHINE / POURING CONCRETE WALL
SLURRY TANK SET UP LAUNCH MACHINE MAINTENANCE OTHER
CONNECT SERVICES
TUNNELLING COMPLETED DRIVE TAKE OUT MACHINE Proposed work for next day and comments (include other delay explanation)
TURN AROUND BREAKING B/ WALL DE-MOBILIZATION Day: Day off
PIPE RE-JACKING CASTING F/WALL SHUTTERING F/WALL Night: Day off
☐
PROJECT NAME:
Construction of Link Roads Adjacent to Al
CONSTRUCTION MANAGER 0 MECHANIC 2 SEPARATION UNIT 2 Hard Rock (100 -
Khor Expressway 250 Mpa)
LOCATION: Al Khor HR MANAGER 0 NDM HKN TECHNICIAN 0 GENERATOR 2
☐
Medium Rock (50 -
CLIENT: ASHGHAL ADMINSTRATION OFFICER 0 HSEQ OFFICER 4 PUMP 4 100 Mpa)
CONTRACTOR: Tekfen SITE SUPERVISOR/ENGINEER 1 WATCHMAN 4 TANK 4
☐
Soft Rock ( < 50
PROJECT IN CHARGE: Berly Thomas TBM OPERATOR 4 DRIVER 2 CONTAINER 4 Mpa)
CRANE OPERATOR 4 TON DRIVER 2 CABIN 2
SIGNED: Clay Conditions ☐
SURVEYOR 1
D/SHIFT 3 4 5
PIPE NUMBER
N/SHIFT 6 7 8
PIPE TYPE Concrete Concrete Concrete Concrete Concrete Concrete
JACKING PRESSURE (ton) 40 40 40 40 40 40
INSTALLED LENGTH 3 3 3 3 3 3
GROUTING FROM SHAFT TO SHAFT LENGTH (m) DAY SHIFT QTY. (m3) NIGHT SHIFT QTY (m3) TOTAL (m3)
INSERTION FROM SHAFT TO SHAFT LENGTH(m) DAY SHIFT QTY. (m) NIGHT SHIFT QTY (m) TOTAL (m)
FABRICATION WORKS MOBILIZATION PULL BACK SERVICES EQUIPMENT BREAKDOWNS SHAFT NOT READY SLURRY/SPOIL REMOVAL
SHUTTERING B/WALL SET JACKING FRAME ENTRANCE RING DETAILS DEWATERING ISSUES PIPES ON SITE
LOWER MACHINE / POURING CONCRETE WALL
SLURRY TANK SET UP LAUNCH MACHINE MAINTENANCE OTHER
CONNECT SERVICES
TUNNELLING X X COMPLETED DRIVE TAKE OUT MACHINE X Proposed work for next day and comments (include other delay explanation)
TURN AROUND BREAKING B/ WALL DE-MOBILIZATION Day: Remove equipment inside tunnel
PIPE RE-JACKING CASTING F/WALL SHUTTERING F/WALL Night: Remove equipment inside tunnel