CHAPTER I
I. GENERAL
I.1 Project Data
Integrated Light Rail Transit Project Jabodetabek (LRT Project) is a
rapid transportation system using light rail train (LRT) developed in Jakarta,
Indonesia.
LRT will connect Jakarta and the suburb area such as Bekasi and
Bogor. LRT is developed by Local Government of DKI Jakarta that build and
develop LRT around the city and PT Adhi Karya appointed by Government
qq Ministry of Transportation as the Main Contractor which responsible for
planning and developing LRT for connecting the Suburb areas under the
name LRT JABODEBEK.
For this purpose, PT Adhi Karya cooperated with their Sub Contractor
to achieve and optimize the project smoothly i.e. PT. Adhi Persada Gedung
(APG) and PT Smart-modular Building Indonesia (SBI) as one of the the Sub
Contractors of APG.
SBI is appointed as a Sub Contractor for the architectural works
especially for fasade and roof of the LRT stations. Here below is the Project
Chart :
Kemenhub (Owner)
OCG (Consultan)
Services line 3:
a. Jatibening (Jaticempaka)
b. Cikunir 1
c. Bekasi Barat
d. Jatimulya (Bekasi Timur)
e. Cikunir 2
2. Scope of works
a. Workshop
Scope of work in the workshop:
- Lamination Sandwich Panel
- Instalation of solartuff on to Sandwich Panel (RAL 5007 / Brilliant
blue)
- Gutter production
Picture 1.2.1 SWP stock at SBI workshop Picture 1.2.2 Moving SWP Using Forklift
on workshop
- Fabrication Skylight
- Fabrication Gutter
b. Materials Distribution
document provided for materials distribution consist of:
- Delivery Order
Load to
truck
Ready
to
deliver
c. Instalation of Material
SWP installation shall start based on zone area. Start from zone 1
to zone 4 or reverse, before installing SWP, installing gutter is
mandatory. This is important as the start point for installing panel under
gutter or above gutter to minimize short length of SWP.
SWP installation shall use supporting equipment such as heavy
equipment, fixing equipment as the followings:
13. Scafolding
d. Working area
CHAPTER II
- Conclusions
b. Spesification of Gutter
c. Solid Polycarbonat
d. Acsesoris
- Flashing (0,5mmT), from coil (skin panel)
- Alm. Ekstrusion
e. Fixing
- Self Screw for Despach & Ekstrusion
Picture 2.11 Specification of Self Screw For Joint Sandwich Panel & Steel
- Sealent
f. Safety Track
- Specification of Safety Track
- Detail Junction
- End Stop
- Trolley
g. Safety Lifeline
- Life line
- Warning Plate
- Tensionning toll
CHAPTER III
d. Storage
e. Bolt Calculation
f. Screw Calculation
Due to loading, force that occurs on the top and bottom of the pedestal.
Force recive every support = 1/2 Fy dan 1/2 Fz
Fy = 609.7 kg 1/2 Fy = 304.85 kg
Fz = 75 kg 1/2 Fz = 37.5 kg
1m
Panel @ 1m
2. Clearing Area
a. Ilustration area of Halim station
TO JAKARTA
TO CIKAMPEK
ST. HALIM
a. Marking Position
Marking position should adjusted with cutting list panel from engineer.
b. Zone Grouping
c. Installing SWP
Before installing Sandwich Panel, need to be survey level plat jengger
using total station. After survey and got it level data, the highest plat jengger
become a refrence, while plat jengger shorter need propped up using
tefflon.
Slope conditioning gutter with do survey using total station, after got it
data and fix, then when will installing gutter need pulled thread for ensure
the same level gutter.
Installing SWP begining with installing gutter use U-Boxs, like under the
picture:
46
5.111
5.119
6. 0
60
°
75 mm
1/5 L 2/3 L 1/5 L
1.000
10.000
TECHNICAL DATA
(CARMANTEL ROPE SEMI
STATIC ROPE)
•Length:50 meters
•Diameter:12.5 mm
•Static Strength:2500 kgs
•Weight per meter:68 gr
•Shrinkage:4%
•Dry Treatment:none
A7Z1
A6Z1
ZONA 1A
ZONA 1B
ZONA 1A
ZONA 1B
ZONA 1C
- Install Endwall
3. Fixing Material
Fixing material use U-boxs, for support fixing team, placed on U shape.
Alm. Male-female
- Install Acesoris
4. Install ACP
Accesories Installation
1. GAP Between Sandwich panel and Steel Plate (Jengger)
2. Marking Position for the Flashing, Make Hole for csk Rivet attachment ,
Fixing the csk Rivet
3. Sealent the Flasing
4. Mockup Sample
CHAPTER IV
IV.1 Inspection
LAMPIRAN
FORM CEKLIST
CHAPTER V
1. EMERGENCY PREVENTION
PT. SBI will coordination with the customer in case of emergency condition.
In case of emergency situation, Stop the works immediately and do the
related prevention.
In case of accident, immediately report to HSE and do emergency
prevention if the victims become worsth, go to the nearest hospital.
In case of fire, try to extingwish using fire extingwisher. Otherwise, call fire
brigade.
In case of disaster (flooding, earth quake), immediately find a safe place
and contact management for next action.
Base of chaos or striking happened, immediately report to the authority.
3. SAFETY EQUIPMENT
During erection, PT. SBI will provide first and box (P3K) for first and purpose
in case of accident in accordance with Permenaker No. 15/ 2018.