You are on page 1of 83

PROGRAM PERCEPATAN

PENYELENGGARAAN KERETA API DOC. NO.


:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

CHAPTER I
I. GENERAL
I.1 Project Data
Integrated Light Rail Transit Project Jabodetabek (LRT Project) is a
rapid transportation system using light rail train (LRT) developed in Jakarta,
Indonesia.
LRT will connect Jakarta and the suburb area such as Bekasi and
Bogor. LRT is developed by Local Government of DKI Jakarta that build and
develop LRT around the city and PT Adhi Karya appointed by Government
qq Ministry of Transportation as the Main Contractor which responsible for
planning and developing LRT for connecting the Suburb areas under the
name LRT JABODEBEK.
For this purpose, PT Adhi Karya cooperated with their Sub Contractor
to achieve and optimize the project smoothly i.e. PT. Adhi Persada Gedung
(APG) and PT Smart-modular Building Indonesia (SBI) as one of the the Sub
Contractors of APG.
SBI is appointed as a Sub Contractor for the architectural works
especially for fasade and roof of the LRT stations. Here below is the Project
Chart :

Kemenhub (Owner)

OCG (Consultan)

PT. Adhi Karya (Contractor)

PT. Adhi Persada Gedung (Contractor)

PT. Smart-modular Building Indonesia


(Fabrication)

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


1
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

PT. Smart-modular Building Indonesia got the assignment at 2 line


services, that is services line 1:
a. Taman Mini
b. Kp. Rambutan
c. Ciracas
d. Harjamukti

Services line 3:
a. Jatibening (Jaticempaka)
b. Cikunir 1
c. Bekasi Barat
d. Jatimulya (Bekasi Timur)
e. Cikunir 2

Picture 1.1 LRT Station

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


2
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

I.2 Scope of works


1. Pay Item
7.3.2 = Façade
7.3.2.1 = Dinding Façade Panel Ringan (Sandwich Panel)
7.3.2.2 = Dinding Façade Panel Precast Ringan pada station
corner (beton precast)
7.3.2.3 = Terali Louvre Alumunium pada Tangga Darurat
7.3.2.4 = Terali Louvre Alumunium
VO-7.3.2.1 = Dinding Façade Panel Ringan (Sandwich Panel)
75mm
VO-7.3.2.2 = Expansion Solid Joint Sandwich Panel
VO-7.3.2.3 = Insulated Gutter
VO-7.3.2.4 = Alumunium Composite Panel
VO-7.3.2.5 = Manhole
VO-7.3.2.6 = Safety Track
VO-7.3.2.7 = Safety Line
VO-7.3.2.8 = Curtainwall pada sisi atas louvre t:6mm

2. Scope of works
a. Workshop
Scope of work in the workshop:
- Lamination Sandwich Panel
- Instalation of solartuff on to Sandwich Panel (RAL 5007 / Brilliant
blue)
- Gutter production

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


3
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

Picture 1.2.0 Unloading SWP from Container

Picture 1.2.1 SWP stock at SBI workshop Picture 1.2.2 Moving SWP Using Forklift
on workshop

Picture 1.2.2 SWP stockyard at SBI workshop

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


4
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

- Fabrication Skylight

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


5
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

- Fabrication Gutter

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


6
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

b. Materials Distribution
document provided for materials distribution consist of:
- Delivery Order

Gambar 1.3 Form Delivery Record Material Sandwich

- Delivery materials procedure


SWP are delivered to site using by Truck to the project location. All
materials arrived should be checked against conformity of document
as well as the quantity, dimensions, color, defect, etc.

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


7
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

Picture 1.4 SWP stacking

Load to
truck

Ready
to
deliver

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


8
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

c. Instalation of Material

Gambar 1.5 Instalation zone

Picture 1.6 scope of work


1. Panel curve T.75mm Ral 1013, ( bahan PIR (Fire Retertdan), Alm.
Ekstude, Sealent, Self screw).
2. Ekpansion Joint (bahan Alm. Ekstrude curving, Coil 0,5mm
Flashing, Rubber gasket, Bithutane, No more no seal).
3. Fix Joint (bahan Alm. Ekstrude curving, Coil 0,5mm Flashing, Self
screw, Rivet).
4. Capping ending curve (bahan panel, ACP, coil 0,5mm flashing,
Sealent).
5. Panel roof Ral 5007/6018 + Skylight, (bahan panel curve T.75mm,
Polycarbonat T.4mm, Alm. Mullion, Alm. Ekstrude).
6. Safety rail.

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


9
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

SWP installation shall start based on zone area. Start from zone 1
to zone 4 or reverse, before installing SWP, installing gutter is
mandatory. This is important as the start point for installing panel under
gutter or above gutter to minimize short length of SWP.
SWP installation shall use supporting equipment such as heavy
equipment, fixing equipment as the followings:

1. Total Station 2. Safety Face

3. Self Baricade 4. Shackle

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


10
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

5. Welding Tools 6. Webbing Sling

7. Chaing Block 8. Drill Tool

9. Jig Saw 10. Gerinda

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


11
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

11. Sigmat 12. Portable Winch

13. Scafolding

16. Safety Block


15. Full Body Harness

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


12
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

17. Safety Net For Tool 18. Safety Line

19. Safety Helm 20. Safety Shoes

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


13
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

d. Working area

Picture 1.7 Working Area

Working area is on the existing steel structure provided by others.


SWP is the LRT stations roof and the steel structures is the steel
frame where the SWP shall be installed on it. Supporting equipment
such as manlift is located at the platform for installing gutter and
SWP above gutter. White working area for installing SWP under
gutter is in the councorse.

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


14
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

CHAPTER II

II. STANDARD OF WORK


II.1 Guidlines Standard of work

Picture 2.1.1 Table SOP NC

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


15
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

Gambar 2.1.2 Table SOP NC

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


16
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

Gambar 2.1.3 Table SOP NC

Gambar 2.2 Table SOP Corrective Action Report

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


17
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

II.2 Materials Technical Requirement


a. Spesification of Sandwich Panel

Picture 2.3 Specificaion Sandwich Panel

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


18
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

- Conclusions

On the table spesification there is sandwich panel burning on temperature


100 c – 118 c, while on test laboratorium sandwich panel burning on
temperature 305 c – 415,8 c. it meant SWP meet the spesification.

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


19
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

b. Spesification of Gutter

Picture 2.4 Specification Gutter Sandwich

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


20
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

c. Solid Polycarbonat

Picture 2.5 Specification Polycarbonat For Skylight

d. Acsesoris
- Flashing (0,5mmT), from coil (skin panel)

Gambar 2.6 Specification Skin Sandwich Panel


- Folded, from Galvanis

Gambar 2.7 Material Closing Joint between Sandwic Panel

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


21
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

Picture 2.8 Mill Certificat For Galvanize Iron Sheet

- Alm. Ekstrusion

Picture 2.9 Material Alumunium Extrution

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


22
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

Picture 2.10 Mill Certificat For Extrution

e. Fixing
- Self Screw for Despach & Ekstrusion

Picture 2.11 Specification of Self Screw For Joint Sandwich Panel & Steel

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


23
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

Picture 2.12.1 Specification of Self Screw Performance Data

Gambar 2.12.2 Specification of Self Screw Performance Data

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


24
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

- Self screw for SWP to Steel

Picture 2.13 Self Screw For SWP To Steel

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


25
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

- Rivet for Hidden Despatch and Ekstrusion

Picture 2.14 Specification Rivet

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


26
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

- Sealent

Picture 2.15.1 Sealent

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


27
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

Picture 2.15.2 Sealent

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


28
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

Picture 2.5 Specification Sealent

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


29
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

f. Safety Track
- Specification of Safety Track

Gambar 2.6 Specification of Safety Track

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


30
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

- Detail Junction

Picture 2.7 Detail Junction

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


31
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

- Nut for Fixing on Bracket

Picture 2.8 Nut for Fixing on Bracket

- Tilting End Stop

Picture 2.9 Tilting End Stop

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


32
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

- End Stop

Picture 2.10 End Stop

- Trolley

Picture 2.11 Trolley

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


33
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

- Methode Install Safety Track

Picture 2.12 install Safety Track

Picture 2.13 Picture Safety Track

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


34
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


35
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

g. Safety Lifeline

Picture 2.13 install Safety Line

- Life line

Picture 2.14 Safety Life Line

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


36
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

Picture 2.15 Install Safety Life Line

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


37
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

- Specification Stainless Steel Cable

Picture 2.13 Specification Stainless Steel Cable

- Horizontal Lifeline on Ground

Picture 2.14 Horizontal Lifeline on Ground

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


38
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

- Components of Akrobat Lifeline

Picture 2.15 Components of Akrobat Lifeline

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


39
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

- Configurasi Components of Akrobat Lifeline

Picture 2.16 Configurasi Components of Akrobat Lifeline

- The Energy Absorber LVD032

Picture 2.17 The Energy Absorber LVD032

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


40
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

- Crimping ring on end anchor

Picture 2.18 Crimping ring on end anchor

- Crimping ring with threaded tip M10.

Picture 2.19 Crimping ring with threaded tip M10.

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


41
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

- Crimping ring – turnbuckle ligne

Picture 2.20 Crimping ring – turnbuckle ligne


- Crimping ring junction

Picture 2.21 Crimping ring junction


- Crimping rings for curve section

Picture 2.22 crimping rings for curve section

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


42
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

- Checking the crimping

Picture 2.23 checking the crimping

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


43
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

- Warning Plate

Picture 2.24 Warning Plate

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


44
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

- Tensionning toll

Picture 2.25 tensionning toll

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


45
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

- Schematic plan of installation

Picture 2.26 Schematic plan of installation

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


46
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

- Indentification of Akrobat Lifeline

Picture 2.27 Indentification of Akrobat Lifeline

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


47
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

- Recommendations relating of periodic review procedure

Picture 2.28 Recommendations relating of periodic review procedure

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


48
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

CHAPTER III

III.1 Implementation Flow

Picture 3.1.1 Flow Chart Deliver Material

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


49
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

Picture 3.1.2 Flow Chart Deliver Material

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


50
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

Picture 3.2.1 Flow Chart Inspection

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


51
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

Picture 3.2.2 Flow Chart Inspection

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


52
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

III.2 Work Preparation


1. Work Preparation Step
a. Individu Handling Sandwich Panel
Man power should use safety K3. When moving sandwich panel sheet
by sheet, moving sandwich panel should not with flat position because can
over stretch on the sandwich panel. Exposure from the sun to the sandwich
panel can make arch on SWP, then placed of sandwich panel on shade
area.

Picture 3.3 Individu Handling SWP

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


53
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

b. Handling SWP using Forklift

Picture 3.4 Handling SWP busing Forklift

Loading and unloading SWP using forklift shall be the following:


- SWP with length < 9,14 meter use single forklift with wide distance
fork. Fork placement shall realy in the center of stacking as show in
picture 3.4 above.
- SWP with length > 9,14 meter, shall use two forklift with the same
distance points. As show in picture 3.4 bottom.

Picture 3.4 Handling SWP using Double Forklift

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


54
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

c. Delivery Sandwich Panel

Picture 3.5 Delivery SWP

Delivery SWP by truck with protector sheet.

d. Storage

Picture 3.6 Storage Panels

Storage sandwich panel are placed in shade area and supported by


sterofoam, and given protector sheet.

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


55
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

e. Bolt Calculation

Picture 3.15 Bolt Calculation Picture 3.16 Gutter

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


56
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

Picture 3.17 Design Dimensions of Screw Threards, bolt, and according

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


57
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

f. Screw Calculation

Picture 3.18.1 Bolt Calculation Picture 3.18.2 Calculation Bolt

Quality Tapping Screw :


Tapping Screw Ø 5.5 mm
Tension Strength = 2.71 kN

Shear Strength = 1.2 kN ( See Attachment spesification )

Quality for design :


Tension Strength = 2.71 kN x 0.75 = 2.03 kN
= 207.19 kg
Shear Strength = 1.2 kN x 0.75 = 0.90 kN
= 91.74 kg

Due to loading, force that occurs on the top and bottom of the pedestal.
Force recive every support = 1/2 Fy dan 1/2 Fz
Fy = 609.7 kg 1/2 Fy = 304.85 kg
Fz = 75 kg 1/2 Fz = 37.5 kg

1m

Panel @ 1m

Loading area tapping screw


Picture 3.18.3 Bolt Calculation

Instalation Tapping screw every 500mm

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


58
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

Receive force every tapping screw :


(1/2) x (1/2 Fy) = 152.4 kg
= 153 kg
= 1.50 kN Tension < 2.03 kN (OK)

(1/2) x (1/2 Fz) = 18.75 kg


= 19 kg
= 0.19 kN Shear < 0.90 kN (OK)

2. Clearing Area
a. Ilustration area of Halim station

TO JAKARTA

TO CIKAMPEK

ST. HALIM

Picture 3.19.1 Ilustration Location of Halim station

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


59
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

b. Traffic Temporary Plans

Picture 3.20.1 Traffic Temporary Plans

III.3 Work Implementation


1. Implementation Instalation

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


60
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

a. Marking Position
Marking position should adjusted with cutting list panel from engineer.

Picture 3.22 Marking Position

Picture 3.23 Marking Position Bottom gutter

Marking Elevation Gutter


Verticality, Horizontal Length and Gutter Support Position check by surveyor
(Joint Survey) AK, APG, Steel Subcont, and SBI ( Measure With Total
Stations ).

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


61
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

- Steel structure checking (Joint Survey)

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


62
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

b. Zone Grouping

Picture 3.23 Zone Division

Picture 3.24 Zone Plan for Installation

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


63
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

Function of zone grouping for installing sandwich panel, if start installing


SWP from zone 1 then finished at zone 4.

c. Installing SWP
Before installing Sandwich Panel, need to be survey level plat jengger
using total station. After survey and got it level data, the highest plat jengger
become a refrence, while plat jengger shorter need propped up using
tefflon.
Slope conditioning gutter with do survey using total station, after got it
data and fix, then when will installing gutter need pulled thread for ensure
the same level gutter.
Installing SWP begining with installing gutter use U-Boxs, like under the
picture:

Picture 3.24.1 Installing gutter & SWP

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


64
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

Picture 3.24.3 Handling SWP & Gutter

Picture 3.25 Position Gutter

Picture 3.26 Gutter

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


65
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

46

5.111
5.119

6. 0
60
°

75 mm
1/5 L 2/3 L 1/5 L
1.000

10.000

Picture 3.28 Lifting Panel

Safety for Erection Panel


Type = GRAY 4 T
Quantity = 2 Unit
Actual Height = 8 m
Rated Capacity = 3200 KG
Weight Panel = 120 kg
Safety Factor = Cap/ W = 6400/ 120
= 53.3 SAFE

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


66
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

Picture 3.29 Support Manpower install under gutter

- Safety equipment temporary

TECHNICAL DATA
(CARMANTEL ROPE SEMI
STATIC ROPE)
•Length:50 meters
•Diameter:12.5 mm
•Static Strength:2500 kgs
•Weight per meter:68 gr
•Shrinkage:4%
•Dry Treatment:none

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


67
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

Picture 3.29 Installing Gutter

Picture 3.30 Position Gutter After Installed

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


68
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

Picture 3.30 Position Gutter After Installed


- Install SWP

A7Z1

A6Z1

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


69
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

Picture 3.31 SWP Above Gutter

ZONA 1A
ZONA 1B

Picture 3.32.1 Zone Grouping

ZONA 1A
ZONA 1B
ZONA 1C

Picture 3.32.2 Zone Grouping

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


70
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

- Install Endwall

End Wall Panel Installation


1. Marking Position
2. Cutting Panel
3. Lifting Panel (Hoist 5 Ton)
4. Lifting the second panel
5. Screw to Steel Frame
6. Finish

- Steel Structure & SWP

Picture 3.37 Steel Stucture & Panel

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


71
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

2. Moving mobilisation U-boxs


Mobilisation scafolding following installing SWP based on zone. Example
from zone 1 to zone 4.

Picture 3.38.1 Movement Scafolding

3. Fixing Material
Fixing material use U-boxs, for support fixing team, placed on U shape.

Picture 3.40 Boddy Harnes

Picture 3.41 Ninja Shoes

Picture 3.39 Suport Tim Fixing with U-boxs

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


72
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

Fixing screw male female to steel

Picture 3.42 Fixing Srew Male Female

Fixing screw male female with Alm. Area 45-90

Alm. Male-female

Picture 3.4.3 Alumunium

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


73
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

Picture 3.4.4 keyplan Alm. Male female


Installing alm. Male female from panel number 5 above gutter. For sealent
installing at alm. Male female.

- Install Acesoris

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


74
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

- Install Safety Track

- Install Safety Line

Safety Track and Safety Line Installation


1. Installation Man power Using scafolding
2. Safety life line bracket installation

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


75
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

4. Install ACP

End Cape Installation scafolding Method


1. Marking Position and install the Structural frame
2. Install Alumunium Composite Panel
3. Removing The Protected Lamination

5. Repair Gap SWP & Jengger

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


76
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

Accesories Installation
1. GAP Between Sandwich panel and Steel Plate (Jengger)
2. Marking Position for the Flashing, Make Hole for csk Rivet attachment ,
Fixing the csk Rivet
3. Sealent the Flasing
4. Mockup Sample

6. Install eksterior Acsesoris with Jaring Methode

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


77
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

Picture 3.4.5 support jaring

CHAPTER IV
IV.1 Inspection

Picture 4.1.1 Form Inspection Instalation

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


78
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

Picture 4.1.2 Form Inspection Instalation

2. Check Curve on the Sandwich Panel


Check curve (radius) on the Sandwich Panel using mold from stainless
stell, like the picture.

Picture 4.2.1 Mold SWP R 11

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


79
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

Picture 4.2.2 Mold SWP R 9

Picture 4.2.2 Mold SWP R 8

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


80
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

LAMPIRAN
FORM CEKLIST

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


81
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

CHAPTER V

V.1 Job Safety Analisys

Picture 5.1 Flowchart Job Safety Analisys

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


82
PROGRAM PERCEPATAN
PENYELENGGARAAN KERETA API DOC. NO.
:
RINGAN/LIGHT RAIL TRANSIT TERINTEGRASI
DI WILAYAH JAKARTA, BOGOR, DEPOK DAN DATE REV
BEKASI

1. EMERGENCY PREVENTION
PT. SBI will coordination with the customer in case of emergency condition.
In case of emergency situation, Stop the works immediately and do the
related prevention.
In case of accident, immediately report to HSE and do emergency
prevention if the victims become worsth, go to the nearest hospital.
In case of fire, try to extingwish using fire extingwisher. Otherwise, call fire
brigade.
In case of disaster (flooding, earth quake), immediately find a safe place
and contact management for next action.
Base of chaos or striking happened, immediately report to the authority.

2. LIST OF MOBILE PHONE NUMBER FOR EMERGENCY SITUATION


No Name Position No. Telpon

1 I Putu Kusuma S. Project Manager 081347427700


2 Amar Site Manager 081347380484
3 Dewa Supervisor 082220112821
4 Bian Surveyor 081387810008
5 Anang HSE 082134407571
Picture 5.2 Table of Emergency Call Number

3. SAFETY EQUIPMENT
During erection, PT. SBI will provide first and box (P3K) for first and purpose
in case of accident in accordance with Permenaker No. 15/ 2018.

METHODE STATEMEN SANDWICH PANEL STATION JATIMULYA


83