Contractor

LONGJIAN– KEC JV
PHASE IV DC-02 PROJECT

METHOD STATEMENT FOR


BORED CAST IN SITU PILING
Document Name: Method Statement for Bored Cast in Situ Piling
Document Code:LONGJIAN-KEC/DMRC-DC02/MS/04/REV-02

Revision No Date PREPARED BY CHECKED BY APPROVED BY


REVIEWED BY

Harish Rajkishor
R2 03.03.2020 Ravi Raghav Pandey Arvind Tingloo
Chauhan

(Chief Safety Project


( Engineer QC) ( Manager QC )
Manager) Co-Ordinator
LONGJIAN-KEC (JV)
DELHI METRO RAIL PROJECT, PHASE - 4, PROJECT :
Contract DC-02: Part Design and Construction of Elevated
Viaduct from Maujpur (excluding) to Majlis Park
(excluding) including Bridge across river Yamuna,
Integrated Elevated Viaduct with PWD flyover at lower LONGJIAN – KEC JV
deck & metro line at upper deck from Yamuna Vihar to
Bhajanpura and 08 Elevated Stations of Majlis Park –
Maujpur Corridor of Delhi MRTSPhase-IV project))
Document Name Method Statement for Bored Cast in Situ Piling
Document Code LONGJIAN-KEC/DMRC-DC02/MS/04 Revision No: 02 Date: 03/03/2020

Project Title:DMRC CONTRACT: DC-02: Part Design and Construction of Elevated Viaduct
from Maujpur (excluding) to Majlis Park (excluding) including Bridge across river Yamuna,
Integrated Elevated Viaduct with PWD flyover at lower deck & metro line at upper deck from
Yamuna Vihar to Bhajanpura and 08 Elevated Stations viz. Yamuna Vihar, Bhajanpura,
KhajuriKhas, Sonia Vihar, Soorghat, Jagatpur Village, JharodaMajraa and Burari (including Entry
& Exit structures at stations but excluding Architectural finishing, Pre-engineered steel roof
structure and roof sheeting of stations) from Chainage 0.0 M to 12098.520 M of Majlis Park –
Maujpur Corridor of Delhi MRTSPhase-IV project.

METHOD STATEMENT FOR


BORED CAST INSITU PILING

DISCIPLINE Civil Mechanical Electrical General


Contact Document control

LONGJIAN-
NAME: M.S for Bored Cast in situ Piling KEC/DMRC-
DC02/MS/04/REV-02

Tel: Action Required

For information For Approval ✓

Page 2 of 30
LONGJIAN-KEC (JV)
DELHI METRO RAIL PROJECT, PHASE - 4, PROJECT :
Contract DC-02: Part Design and Construction of Elevated
Viaduct from Maujpur (excluding) to Majlis Park
(excluding) including Bridge across river Yamuna,
Integrated Elevated Viaduct with PWD flyover at lower LONGJIAN – KEC JV
deck & metro line at upper deck from Yamuna Vihar to
Bhajanpura and 08 Elevated Stations of Majlis Park –
Maujpur Corridor of Delhi MRTSPhase-IV project))
Document Name Method Statement for Bored Cast in Situ Piling
Document Code LONGJIAN-KEC/DMRC-DC02/MS/04 Revision No: 02 Date: 03/03/2020

Date of Section Details


Amendment No.

R0 22/01/2020 All R0 - Revision submission to Client for Approval

R1 08.02.2020 All
Clause 4.1Reference code & Standards :
Provision of Quality Assurance Manual & Safety Health
Environment included.

Clause 5.0Responsibility:
Provision of Jointly survey point of pile included.

Clause 7.1Equipment for rotary rig piling:


Type of crane mentioned.

Clause 7.2 Material :


Specifications of Polymer added.

Clause 9.2 Flushing Operation


Provision of Flushing operation included.

Clause 9.3.7 Slurry Specification for pile


Specification of slurry included in the table as per
technical specification

Clause 9.7 Sonic Tube Fixing methodology

Clause 9.2.7 Special arrangement for Yamuna bridge


crossing and irrigation Nallah
As per employers requirement volume 3
clause no 2.14 special arrangement Included.

Page 3 of 30
LONGJIAN-KEC (JV)
DELHI METRO RAIL PROJECT, PHASE - 4, PROJECT :
Contract DC-02: Part Design and Construction of Elevated
Viaduct from Maujpur (excluding) to Majlis Park
(excluding) including Bridge across river Yamuna,
Integrated Elevated Viaduct with PWD flyover at lower LONGJIAN – KEC JV
deck & metro line at upper deck from Yamuna Vihar to
Bhajanpura and 08 Elevated Stations of Majlis Park –
Maujpur Corridor of Delhi MRTSPhase-IV project))
Document Name Method Statement for Bored Cast in Situ Piling
Document Code LONGJIAN-KEC/DMRC-DC02/MS/04 Revision No: 02 Date: 03/03/2020

Clause 5.1Responsibility & Designation included.

Clause 9.2 Diameter of Yamuna River pile included.


R2 22.02.2020 All
Clause 9.5 Size of cutting tool included.

Clause 9.10 Vaccum Distance


Vaccum Distance between bottom tip of pile and
founding level of pile included.

Clause 9.12 Muck Disposal plan included

Appendix A: Bore Log Checklist included.

• Lift Plan For the proposed activity attached in


Appendix C

Edge protection near the deep excavated included


refer to section 12 , point 4 , page No. 25

• Rebar cage shall be lowered by both rig and crane


refer section 9.4 to page no: 19
• Safety measures for pilling across river Yamuna
included refer to page no: section 12 page no 25 also
included in Hazard and risk assessment
Appendix B
• Safety measures while working near the
sedimentation tank included refer to page no: section
12 page no 25 also included in Hazard and risk
assessment Appendix B.

• Safety measures while assembly and tying of part


wise part reinforcement cage included refer to page
no: section 12 page no 25 also included in Hazard and
risk assessment Appendix B.

Page 4 of 30
LONGJIAN-KEC (JV)
DELHI METRO RAIL PROJECT, PHASE - 4, PROJECT :
Contract DC-02: Part Design and Construction of Elevated
Viaduct from Maujpur (excluding) to Majlis Park
(excluding) including Bridge across river Yamuna,
Integrated Elevated Viaduct with PWD flyover at lower LONGJIAN – KEC JV
deck & metro line at upper deck from Yamuna Vihar to
Bhajanpura and 08 Elevated Stations of Majlis Park –
Maujpur Corridor of Delhi MRTSPhase-IV project))
Document Name Method Statement for Bored Cast in Situ Piling
Document Code LONGJIAN-KEC/DMRC-DC02/MS/04 Revision No: 02 Date: 03/03/2020

INDEX

Sr. PAGE
ITEM DESCRIPTION
No. No.
1 PREAMBLE 6
2 SCOPE OF WORK 6
3 FIELD OF APPLICATION 6
4 REFERENCE DOCUMENTS 6
5 RESPONSIBILITY 7
6 WORKMANSHIP 10
7 EQUIPMENTS & MATERIALS 10
8 PRELIMINARY ACTIVITIES 11
9 PILE INSTALLATION 12
10 ENVIRONMENTAL IMPACT 24
11 TOLERANCES 24
12 SAFETY 25
• APPENDIX A- ITP &CHECK LIST
• APPENDIX B- HAZARD IDENTIFICATION & RISKASSESSMENT

Page 5 of 30
LONGJIAN-KEC (JV)
DELHI METRO RAIL PROJECT, PHASE - 4, PROJECT :
Contract DC-02: Part Design and Construction of Elevated
Viaduct from Maujpur (excluding) to Majlis Park
(excluding) including Bridge across river Yamuna,
Integrated Elevated Viaduct with PWD flyover at lower LONGJIAN – KEC JV
deck & metro line at upper deck from Yamuna Vihar to
Bhajanpura and 08 Elevated Stations of Majlis Park –
Maujpur Corridor of Delhi MRTSPhase-IV project))
Document Name Method Statement for Bored Cast in Situ Piling
Document Code LONGJIAN-KEC/DMRC-DC02/MS/04 Revision No: 02 Date: 03/03/2020

1.0 Preamble
The object of this method statement is to lay down a procedure for the installation of
bored cast in-situ piles with hydraulic rigs using partial depth casing with polymer and
oscillator arrangement, for the DC02, package of DMRC.
2.0 Scope of Work
This work method statement covers the technical requirements for the manufacture and
installation of bored cast in-situ piles. This WMS also covers the furnishing of all
materials, plant, labor etc. for complete and proper installation of vertical concrete piles
including surveying and setting out correct location of piles, cut-off level of piles etc.
Concreting of bored cast in-situ pile as per approved drawings of DMRC including
reinforcement complete.
3.0 Field of Application
Valid up to installation of 1000/1200/1800mm dia. Piles for the alignment section for
DC02 package of DMRC inclusive of pile foundations across Yamuna.
4.0 Reference Documents
Relevant GFC drawings as received from client shall be applicable for carrying out all
the Piling activities.
4.1 Reference Codes & Standards
1. IRC:78 Standard specifications and code of practice for roads and bridges,
Foundation & Substructure
2. IS:2911 Part I/Sec-2
3. Technical Specification Volume 4, Section 8 Pile Foundations.
4. BBS (Bar Bending Schedule) as prepared by LONGJIAN-KEC JV and approved by
DMRC.
5. IS 1786 for High strength deformed steel bars and wires for concrete
reinforcement as per DMRC approved vendor.
6. IS 456
Page 6 of 30
LONGJIAN-KEC (JV)
DELHI METRO RAIL PROJECT, PHASE - 4, PROJECT :
Contract DC-02: Part Design and Construction of Elevated
Viaduct from Maujpur (excluding) to Majlis Park
(excluding) including Bridge across river Yamuna,
Integrated Elevated Viaduct with PWD flyover at lower LONGJIAN – KEC JV
deck & metro line at upper deck from Yamuna Vihar to
Bhajanpura and 08 Elevated Stations of Majlis Park –
Maujpur Corridor of Delhi MRTSPhase-IV project))
Document Name Method Statement for Bored Cast in Situ Piling
Document Code LONGJIAN-KEC/DMRC-DC02/MS/04 Revision No: 02 Date: 03/03/2020

7. API-13 B for polymer


8. ITP
9. Safety, Health & Environment Plan

5.0 Responsibility:
Reporting structure of personnel involved in installation of bored cast-in-situ pile/s
shall be as below:
Project Coordinator - Shall be responsible for the overall execution of piling activity.

Dy. Project Manager - Shall report to the Project Co-ordinator


(Viaduct& Sations) - Shall be responsible for control, supervision & direction for
implementation & execution of construction plans
- Shall also be responsible for supervision of construction
Records.
- Develop construction schedules, construction method
statements &prepare progress & accomplishment reports
- Shall communicate to client representative day to day
Activities
Piling-in-Charge/Engineers - Shall report to Dy. Project Manager
- Shall be responsible for day to day planning at site
- Piling activities and preparation of construction records as
per approved Method Statement and sub-contractor’s QC
activities compliance.
- Shall assist to evaluate the sub-contractor’s performance
- Monitoring of safety requirement and its compliances
from time to time.

- Physical inspection of machines and site condition.


- Shall communicate to client representative day to day

Page 7 of 30
LONGJIAN-KEC (JV)
DELHI METRO RAIL PROJECT, PHASE - 4, PROJECT :
Contract DC-02: Part Design and Construction of Elevated
Viaduct from Maujpur (excluding) to Majlis Park
(excluding) including Bridge across river Yamuna,
Integrated Elevated Viaduct with PWD flyover at lower LONGJIAN – KEC JV
deck & metro line at upper deck from Yamuna Vihar to
Bhajanpura and 08 Elevated Stations of Majlis Park –
Maujpur Corridor of Delhi MRTSPhase-IV project))
Document Name Method Statement for Bored Cast in Situ Piling
Document Code LONGJIAN-KEC/DMRC-DC02/MS/04 Revision No: 02 Date: 03/03/2020

Activities
Survey Engineer/Surveyor - Shall report to the Project Coordinator.
- Shall give location of pile/s at site as per approved scheme
- Pile & Pile Point shall get jointly checked by DMRC
Surveyor.
QA/QC Manager - Shall report to the Project Coordinator
- Shall ensure overall control of QC activities
- Implementation of Project Quality Plan.
- Shall be responsible for implementation of Inspection and
Testing Plan as per Specification.
- Custodian of approved construction methodology

P&M in Charge - Ensure continuous availability of P&M at the site.


- Ensure periodic preventive maintenance & timely
breakdown repairs of all machinery & electrical equipment
as per their inspection manuals.
- Responsible for making lifting plan and commencement of
all safety measures required before lifting of cage.

- Ensure operation of P&M as per company norms


Chief Safety Manager - Shall report to Project co-ordinator.
- Shall be responsible for overall control of SHE Activity as
per approved Safety Methodology.
- Responsible to provide Risk Assessment with the
involvement of R.A Team.

- Monitoring of safety requirement and its compliances


from time to time.

Page 8 of 30
LONGJIAN-KEC (JV)
DELHI METRO RAIL PROJECT, PHASE - 4, PROJECT :
Contract DC-02: Part Design and Construction of Elevated
Viaduct from Maujpur (excluding) to Majlis Park
(excluding) including Bridge across river Yamuna,
Integrated Elevated Viaduct with PWD flyover at lower LONGJIAN – KEC JV
deck & metro line at upper deck from Yamuna Vihar to
Bhajanpura and 08 Elevated Stations of Majlis Park –
Maujpur Corridor of Delhi MRTSPhase-IV project))
Document Name Method Statement for Bored Cast in Situ Piling
Document Code LONGJIAN-KEC/DMRC-DC02/MS/04 Revision No: 02 Date: 03/03/2020

Sr. Safety Manager - Responsible for check SHE documents needed for piling
activity.
- Responsible for provision of risk assessment.
- Responsible for ensuring crane/rig documents.

Jr. Safety Manager - Shall report to Sr. Safety Manager.


- Shall ensure accident prevention
- Shall ensure daily HSE activities fully complied.

Safety supervisor - Monitor Safety practices, persuade to minimize non


compliance
- Reports incidents beyond control and unsafe occurrences to
Chief Safety Manager.

5.1 OrganizationChart:

Project
Coordinator
(Arvind Tingloo)

DPM Stations QA/QC P&M in Cheif Safety Manager


DPM Viaduct Survey Manager
( Tarkeshwar Charge (Rajkishor pandey)
(Arijit Datta) Engineer (Ravi
Singh ) (Abhay
(Jaswinder) Raghav) Sr. Safety Manager
Kumar)
(Vishal Dixit)

Piling-in- Jr. Safety Manager


Charge/Engineers (Abhishek)

Safety
Supervisor
(Amit)

Page 9 of 30
LONGJIAN-KEC (JV)
DELHI METRO RAIL PROJECT, PHASE - 4, PROJECT :
Contract DC-02: Part Design and Construction of Elevated
Viaduct from Maujpur (excluding) to Majlis Park
(excluding) including Bridge across river Yamuna,
Integrated Elevated Viaduct with PWD flyover at lower LONGJIAN – KEC JV
deck & metro line at upper deck from Yamuna Vihar to
Bhajanpura and 08 Elevated Stations of Majlis Park –
Maujpur Corridor of Delhi MRTSPhase-IV project))
Document Name Method Statement for Bored Cast in Situ Piling
Document Code LONGJIAN-KEC/DMRC-DC02/MS/04 Revision No: 02 Date: 03/03/2020

6.0 Workmanship
6.1 General
Bored cast in-situ concrete piles of circular cross section of 1000/1200/1800mm diameter
shall be formed by boring to the termination level as indicated on GFC drawings or as
directed by Engineer/Consultant at site.
Concrete shall be of grade designation as specified in GFC drawings for the bored cast in-
situ piles.
Concrete for piles shall be produced only by weigh batching the ingredients.
6.2 Continuity of Construction
Work shall be carried out round the clock viz. in day & night shifts. Piles taken up for
execution from boring to final concreting shall be carried out un-interrupted. Stoppage of
work if unavoidable shall be permitted during boring only.
6.3 Temporary Casing
MS liners of 12mm thick (4m to 6m depth from EGL and as required for the nallah
section/As per Approved Drawing) with ID 1000/1200/1800mm shall be installed
during boring and shall be retrieved during concreting immediately or before Initial
setting time of concrete by using crane/ Piling rig. Care shall be taken while extracting
the casing by ensuring enough quantity of concrete within the bore to avoid necking of
the pile.

7.0 Equipment & Materials


7.1 Equipment for Rotary rig Piling
▪ Hydraulic rotary drilling Rig
▪ Batching plant of Min. 60 cum/hr. capacity
▪ Transit mixers 6 cum capacity (nos. as required)
▪ Tippers for Muck Disposal
▪ Water tank/water supply
Page 10 of 30
LONGJIAN-KEC (JV)
DELHI METRO RAIL PROJECT, PHASE - 4, PROJECT :
Contract DC-02: Part Design and Construction of Elevated
Viaduct from Maujpur (excluding) to Majlis Park
(excluding) including Bridge across river Yamuna,
Integrated Elevated Viaduct with PWD flyover at lower LONGJIAN – KEC JV
deck & metro line at upper deck from Yamuna Vihar to
Bhajanpura and 08 Elevated Stations of Majlis Park –
Maujpur Corridor of Delhi MRTSPhase-IV project))
Document Name Method Statement for Bored Cast in Situ Piling
Document Code LONGJIAN-KEC/DMRC-DC02/MS/04 Revision No: 02 Date: 03/03/2020

▪ Tremmie pipes of 200mm to 250mmØ and steel hopper/funnel for concreting.


▪ Crane 15T crawler or as required
▪ Rebar cutting & bending m/c (Casting yard)
▪ Trailer/truck
▪ Excavator
▪ Welding Machine
▪ Power generator of suitable capacity
All necessary equipment shall be provided as per site condition and before start of
activity.

7.2 Materials
▪ Concrete shall be of M35 grade or as per approved construction drawing, the maximum
size of coarse aggregate shall be as per approved concrete mix design.
▪ Watershall be provided as from specified source as per IS 456.
▪ Reinforcement Fe500 D shall be used as per IS 1786
▪ Polymer shall be used as per API13B.

8.0 Preliminary Activities


8.1 Traffic Management
The traffic diversion & management shall be as specified in the approved traffic
management plan.
8.2 Utilities
The area covered by the pile cap shall be examined for the presence of any utilities.
Identified utilities shall be mapped and those which are likely to cause hindrances to the
foundations shall be brought to the attention of the utility provider and Engineer.

Page 11 of 30
LONGJIAN-KEC (JV)
DELHI METRO RAIL PROJECT, PHASE - 4, PROJECT :
Contract DC-02: Part Design and Construction of Elevated
Viaduct from Maujpur (excluding) to Majlis Park
(excluding) including Bridge across river Yamuna,
Integrated Elevated Viaduct with PWD flyover at lower LONGJIAN – KEC JV
deck & metro line at upper deck from Yamuna Vihar to
Bhajanpura and 08 Elevated Stations of Majlis Park –
Maujpur Corridor of Delhi MRTSPhase-IV project))
Document Name Method Statement for Bored Cast in Situ Piling
Document Code LONGJIAN-KEC/DMRC-DC02/MS/04 Revision No: 02 Date: 03/03/2020

On approval from the Engineer the identified utility shall be relocated or


diverted/shifted through authorized sub-contractor of the utility providers before taking
up the piling/foundation work.
8.3 Structures & Other Encumbrances
Identified structures and encroachments along the alignment shall be removed by the
contractor under instructions from the Engineer In-charge.
9.0 Pile Installation
9.1 Formation of Pile bores
Pile bores up to the specified depth shall be executed by rotary drilling method. The pile
location shall be marked on the ground using wooden peg, 15-20 cm long. The
impression of the boring tool is made on around the point and the rig is correctly aligned
to the impression. On aligning the rig, boring shall be carried out to the required depth
and then MS liner of suitable length shall be placed in the pit concentric to the pile point.
The liner is then pressed inside with the arrangements available in the rotary rig. Material
inside the casing liner shall be removed progressively by the rig with the auger or bucket
tool. Thereafter the rotary drilling rig shall continue by continues supply prepared
Polymer slurry of desired pH and specific gravity into the bore hole with the help of
pump which is connected to the Polymer tank. Polymer slurry added to ensure the
stability of bore hole. The drilling operation will continue till the desired founding level.
The muck removed from the bore shall be disposed away from the site at approved
dumping location identified jointly with DMRC.
9.2 PILLING ACROSS RIVER YAMUNA
As per Employers requirement VOLUME 3 clause no 2.1.4
Provision of suitably designed pile foundations for piers in accordance with actual soil
parameters as obtained from detailed sub surface exploration as required or as directed.
All foundation shall be on piles of minimum 1800 mm dia. with minimum 8mm thick
permanent MS liners as per requirements, for complete pile length above hard/ rocky
Page 12 of 30
LONGJIAN-KEC (JV)
DELHI METRO RAIL PROJECT, PHASE - 4, PROJECT :
Contract DC-02: Part Design and Construction of Elevated
Viaduct from Maujpur (excluding) to Majlis Park
(excluding) including Bridge across river Yamuna,
Integrated Elevated Viaduct with PWD flyover at lower LONGJIAN – KEC JV
deck & metro line at upper deck from Yamuna Vihar to
Bhajanpura and 08 Elevated Stations of Majlis Park –
Maujpur Corridor of Delhi MRTSPhase-IV project))
Document Name Method Statement for Bored Cast in Situ Piling
Document Code LONGJIAN-KEC/DMRC-DC02/MS/04 Revision No: 02 Date: 03/03/2020

strata duly anchored as per Codal provisions. All piles shall be cast-in-situ piles bored
by hydraulic rotary rig only.
9.3 Stabilizing the bore hole:
9.3.1Water supply
An appropriate supply of water/or water tank must always be available.
9.3.2Positive Head Pressure
A minimum of 3 meters of polymer slurry pressure head should always be maintained
above the water table.
9.3.3The mixing tank
The mixing tank shall be installed taking into consideration the slurry needs for constant
agitation. This can be achieved by dedicating a pump and compressed air system to the
mixing tank. It is recommended to use piston pumps in place of centrifugal pumps for
best results.
In order to allow faster hydration of the polymer, a metallic splash plate should be
welded directly underneath the flow of water directed into the tank and inclined
approximately 45 degrees.
If the water flow of the slurry’s agitation is insufficient versus the rate of addition of the
dry polymer granulate, the formation of inert agglomerates will occur, thus resulting in a
higher consumption than initially expected.
The capacity of the storage should be taken into consideration the excavation’s volume
and pretended production rates preferably exceeding it 1.5 times.
9.3.4Storage, Sedimentation tanks and slurry plant schematic
Storage of slurry can be made in tanks having adequate capacity.
It is recommended that sedimentation tank shall be open on top to allow an easy cleaning
and removal of sediments. The inclusion of two deflective plates will assure the
continuous flow of the slurry in a “cascade” like mode, increasing the speed of
sedimentation occurring between different compartments or sections. This design causes
Page 13 of 30
LONGJIAN-KEC (JV)
DELHI METRO RAIL PROJECT, PHASE - 4, PROJECT :
Contract DC-02: Part Design and Construction of Elevated
Viaduct from Maujpur (excluding) to Majlis Park
(excluding) including Bridge across river Yamuna,
Integrated Elevated Viaduct with PWD flyover at lower LONGJIAN – KEC JV
deck & metro line at upper deck from Yamuna Vihar to
Bhajanpura and 08 Elevated Stations of Majlis Park –
Maujpur Corridor of Delhi MRTSPhase-IV project))
Document Name Method Statement for Bored Cast in Situ Piling
Document Code LONGJIAN-KEC/DMRC-DC02/MS/04 Revision No: 02 Date: 03/03/2020

a significant increase of the sedimentation process. The inlet valve shall be directed to the
top of the first deflective plate. Both valves should be placed at the same height from the
top of the deflective plates.
The installation of slurry plant must allow all operations to be carried out at the same
time Mixing, sending and receiving slurry without interfering with production rate.
The sedimentation tanks are extremely important in the returning slurry’s self – cleaning
process by sedimentation and must be incorporated in a slurry plant.
9.3.5Description and usage of polymer
• Synthetic dry granular biodegradable polymer should be mixed with water at an
initial rate of 1 kg per cubic meter, which may be increased or decreased as per
requirements at site to aid proper stabilization of bore.
• Before adding polymer, the water pH should be adjusted to 8 to 11. For a correct
adjustment of the water’s pH, it is advisable that the usage of Sodium Hydroxide or
Potassium Hydroxide in a concentration of 45 to 50% in a rate of 1 liter per M 3 of water. If
purchased in dry flakes the correct amount is 0.5 Kg per M3.
• With the initial recommended dosage and after previous treatment of the water’s
pH the viscosity will be between 60 to 70 seconds per liter (API Marsh Funnel). Based on
site experience , the slurry’s viscosity should always be maintained greater than 55
seconds for best results which may be identified and changed as per requirements at site.
Polymer maintains its properties through time provided that is not exposed to high
concentrations of chemical contaminants, such as calcium carbonates, magnesium,
calcium and chlorine amongst others.
• The values above were calculated considering the usage of an adequate mixing tank.
Whenever the usage of tanks is not possible, with direct mixing at the excavation, the
required dosage may be higher with no harm whatsoever to product’s best performance.

Page 14 of 30
LONGJIAN-KEC (JV)
DELHI METRO RAIL PROJECT, PHASE - 4, PROJECT :
Contract DC-02: Part Design and Construction of Elevated
Viaduct from Maujpur (excluding) to Majlis Park
(excluding) including Bridge across river Yamuna,
Integrated Elevated Viaduct with PWD flyover at lower LONGJIAN – KEC JV
deck & metro line at upper deck from Yamuna Vihar to
Bhajanpura and 08 Elevated Stations of Majlis Park –
Maujpur Corridor of Delhi MRTSPhase-IV project))
Document Name Method Statement for Bored Cast in Situ Piling
Document Code LONGJIAN-KEC/DMRC-DC02/MS/04 Revision No: 02 Date: 03/03/2020

• It is recommended that whenever possible the mixing should be preferably done in


a proper mixing tank. However, depending on general circumstances such as lack of
space or soil conditions, it may be necessary to add polymer directly at the excavation.
The application this method has several advantages like increased slurry viscosity and an
overall stabilization of the formation helping to prevent fluid loss and improving the
slurry’s performance.
9.3.6Technical specification and key slurry properties to be monitored

Viscosity
The viscosity of polymer should be maintained 34-143 seconds per liter as per Outline
Construction specification clause 8.1.4. It is also recommended that the slurry’s viscosity
should always be maintained greater than 55 seconds for best results which may be
adjusted suitably for site conditions in order to stabilize the bore.
pH.
For best performance, pH should always be kept between 8 and 11. Under no
circumstances should the pH of the slurry be lower than 8 and higher than 11. If it exceeds
above 11 pH it may damage the molecular structure of polymer leading to harm
performance of polymer. Continuous monitoring of pH is extremely important since it is
slurry’s only protection against chemical or contaminants in general.
Specific weight or Density
The specific density in a slurry mix is 1.025 g/cc max.
Sand Content
Specification in sampling from the excavation is usually equal or inferior to 1.0%.
Sand content should be checked prior to placing the reinforcement cage or whenever
specified by project.

Page 15 of 30
LONGJIAN-KEC (JV)
DELHI METRO RAIL PROJECT, PHASE - 4, PROJECT :
Contract DC-02: Part Design and Construction of Elevated
Viaduct from Maujpur (excluding) to Majlis Park
(excluding) including Bridge across river Yamuna,
Integrated Elevated Viaduct with PWD flyover at lower LONGJIAN – KEC JV
deck & metro line at upper deck from Yamuna Vihar to
Bhajanpura and 08 Elevated Stations of Majlis Park –
Maujpur Corridor of Delhi MRTSPhase-IV project))
Document Name Method Statement for Bored Cast in Situ Piling
Document Code LONGJIAN-KEC/DMRC-DC02/MS/04 Revision No: 02 Date: 03/03/2020

Sampling Procedure
The sampler must be able to retrieve the samples. The samples shall be collected from
bottom , middle & end point of pile and tested for viscosity, density, pH and sand
content. A sample shall be collected after rebar cage setting.

9.3.7 Slurry specification for pile


Quality parameters for slurry are recommended in following table as Outline
Construction Specification
Property In Hole at Time Method
of Test
Concreting

Viscosity Marsh Funnel


seconds per quart 32-135 AP 13B-1
(seconds per liter) (34-143) Section 2.2
Density Density Balance
Ponds per Cubic foot 64 max API 12B-1 Section 1
(kilogram per cubic meter) (1025max)
Sand Content % 1.0 max. API 13 B -1, Section 5
pH 8-11 pH paper/pH meter

If the Sp. Gravity of Drilling mud at the base of Bore exceeds 1.20gm/cc the placing of
Concrete shall not be proceeded

9.3.8 Preparation of Polymer Slurry.


Polymer slurry will be produced using a synthetic dry granular/ powder biodegradable
polymer which when mixed with water an initial rate of 1 kg per Cum forms a slurry

Page 16 of 30
LONGJIAN-KEC (JV)
DELHI METRO RAIL PROJECT, PHASE - 4, PROJECT :
Contract DC-02: Part Design and Construction of Elevated
Viaduct from Maujpur (excluding) to Majlis Park
(excluding) including Bridge across river Yamuna,
Integrated Elevated Viaduct with PWD flyover at lower LONGJIAN – KEC JV
deck & metro line at upper deck from Yamuna Vihar to
Bhajanpura and 08 Elevated Stations of Majlis Park –
Maujpur Corridor of Delhi MRTSPhase-IV project))
Document Name Method Statement for Bored Cast in Situ Piling
Document Code LONGJIAN-KEC/DMRC-DC02/MS/04 Revision No: 02 Date: 03/03/2020

suitable for soil stabilization in cohesive and non-cohesive soils. The dosage may change as
per site requirements.
If the water of the soil has chemical contaminants it may be required add Sodium
Hydroxide or Potassium Hydroxide to precipitate salts in solution. Additional polymer
may also be required to add directly at the excavation assures soil stabilization.
The values above are calculated considering the usage of an adequate mixing tank and
positive displacement pumps. Direct mixing at the excavation is recommended for
viscosity adjustment in the slurry column while drilling. The mixing should preferably be
done in mixing tank. The polymer slurry is than pumped using a diaphragm/piston pump
to the excavated bored pile location.
• Pump out the water from top to the mixing tank, leaving the last 50 cm. Last 50 cm
water shall be disposed off.
• The sediments deposited in bottom shall be disposed off.
• If the water with the referred concentration is used without pre-treatment, polymer
consumption will be high.
• Upon concrete pouring to an excavation the slurry shall be retrieved passing
through a sedimentation tank. This prevents particles carrying to the storage tanks
or mixing tanks. Further it prevents the slurry cycle from contamination.
The polymer slurry circulation arrangement as shown at attached Figure-1.

Page 17 of 30
LONGJIAN-KEC (JV)
DELHI METRO RAIL PROJECT, PHASE - 4, PROJECT :
Contract DC-02: Part Design and Construction of Elevated
Viaduct from Maujpur (excluding) to Majlis Park
(excluding) including Bridge across river Yamuna,
Integrated Elevated Viaduct with PWD flyover at lower LONGJIAN – KEC JV
deck & metro line at upper deck from Yamuna Vihar to
Bhajanpura and 08 Elevated Stations of Majlis Park –
Maujpur Corridor of Delhi MRTSPhase-IV project))
Document Name Method Statement for Bored Cast in Situ Piling
Document Code LONGJIAN-KEC/DMRC-DC02/MS/04 Revision No: 02 Date: 03/03/2020

Schematic flow chart:


1. From Mixing tank to Pile bore (1st Dosage)
2. From Pile bore to working/sedimentation polymer tank
3. From working/sedimentation polymer tank to Mixing tank
4. From Mixing tank to Pile bore.
The arrangement may change as per site conditions but properties of polymer required for
piling will be as per contract specifications.

9.4 Control of Alignment/Liner Punching

The piling rig itself has in-built provisions to check and maintain the verticality of the
bore. In case, if required, verticality can also be checked using by spirit level. The tool is
attached to a telescopic Kelly guided by guide frame. Piles shall be installed within
permissible limits according to the approved drawings/Outline Construction
Specification.

Page 18 of 30
LONGJIAN-KEC (JV)
DELHI METRO RAIL PROJECT, PHASE - 4, PROJECT :
Contract DC-02: Part Design and Construction of Elevated
Viaduct from Maujpur (excluding) to Majlis Park
(excluding) including Bridge across river Yamuna,
Integrated Elevated Viaduct with PWD flyover at lower LONGJIAN – KEC JV
deck & metro line at upper deck from Yamuna Vihar to
Bhajanpura and 08 Elevated Stations of Majlis Park –
Maujpur Corridor of Delhi MRTSPhase-IV project))
Document Name Method Statement for Bored Cast in Situ Piling
Document Code LONGJIAN-KEC/DMRC-DC02/MS/04 Revision No: 02 Date: 03/03/2020

9.4 Reinforcement
All reinforcement shall be as per the approved drawings. The reinforcement shall be
assembled and tied together and made up into cages sufficiently rigid to withstand
handling without any damage and distortion.
Where the number and diameters of the reinforcement bars change as per the drawing,
laps of the reinforcement bars shall be as indicated on the drawing/as approved. Joints in
longitudinal bars shall be made by lapping by stitch welding, as per code provisions or
by couplers, to prevent distortion of the reinforcing cage. Joints in the reinforcement shall
be such that the full strength of each bar is effective across the joint and shall be made
such that there is no detrimental displacement of the reinforcement during construction
of the pile.
The projecting lengths of the longitudinal bars beyond the pile cut-off level shall be as
indicated in the drawing.
The lateral links or helical reinforcement shall fit closely around the main longitudinal
bars and be fixed to them by 18-gauge GI binding wires.
The reinforcement cages shall be joined together at site by lifting it from one end with the
help of pilling rig kelly and parallelly support shall be given with the help of hydra so as
to protect the cage from touching the ground and there by protecting it from damage and
distortion .
Concrete cover to all the reinforcement, including lateral links or helical, shall be 75mm
or as per Approved Drawing. Circular concrete (M35 OR to be Specified) cover block of
150mm diameter threaded on to the helix shall be used for ensuring the cover of 75mm.
The cover blocks shall be placed at 1.5 meter spacing along the helix. Cover blocks of
required shape and size, M.S. Chairs and spacer bars(16mm) shall be used to ensure
accurate positioning of reinforcement. Cover blocks shall be cast well in advance and
shall consist of approved proprietary pre-packaged free flowing mortars (Conbextra HF
Page 19 of 30
LONGJIAN-KEC (JV)
DELHI METRO RAIL PROJECT, PHASE - 4, PROJECT :
Contract DC-02: Part Design and Construction of Elevated
Viaduct from Maujpur (excluding) to Majlis Park
(excluding) including Bridge across river Yamuna,
Integrated Elevated Viaduct with PWD flyover at lower LONGJIAN – KEC JV
deck & metro line at upper deck from Yamuna Vihar to
Bhajanpura and 08 Elevated Stations of Majlis Park –
Maujpur Corridor of Delhi MRTSPhase-IV project))
Document Name Method Statement for Bored Cast in Situ Piling
Document Code LONGJIAN-KEC/DMRC-DC02/MS/04 Revision No: 02 Date: 03/03/2020

of Fosroc or equivalent). They shall be circular in shape for side cover and square for
bottom cover. The strength of cover block shall be same or higher than the strength of
concrete used.
Stacking of pile cages shall be done carefully to avoid distortion and damage and shall be
shifted to boring locations with the help of multi axle vehicle and lowered with the help
of pilling rig and cranes.
For cross hole sonic integrity test 4 number of vertical 50mm ID and 1mm thick exactly
parallel steel pipes shall be inserted and fastened to the inside of the reinforcement cage
before concreting. It shall be supported and braced securely in order to maintain their
position during subsequent operation. To form single tube the pipe to be connected
within Enlarged end Bel mouth – Push arrangement proved with Rubber gasket only
Cross Hole sonic test will be performed on 25% of piles and Pile Integrity test will be
performed on 75% of piles of Pile group.

9.5 Rotary Drilling Method


The mechanism involved in the machine is rotary drilling using hydraulic feed. Boring is
carried out to the required depth using suitable auger attached to the telescopic Kelly bar.
A bucket tool attached to the Kelly is used for mucking operation and a rock auger and
barrel is used for boring into rocky strata/ Hard Strata.
As a general guideline, size of cutting tool shall in no case be less than the diameter of the
pile minus 75mm. However the size of cutting tool shall be chosen by contractor
depending on the type of substrata and equipment employed by contractor so that
executable pile shall not have diameter less than nominal diameter of pile as specified in
drawing.

Page 20 of 30
LONGJIAN-KEC (JV)
DELHI METRO RAIL PROJECT, PHASE - 4, PROJECT :
Contract DC-02: Part Design and Construction of Elevated
Viaduct from Maujpur (excluding) to Majlis Park
(excluding) including Bridge across river Yamuna,
Integrated Elevated Viaduct with PWD flyover at lower LONGJIAN – KEC JV
deck & metro line at upper deck from Yamuna Vihar to
Bhajanpura and 08 Elevated Stations of Majlis Park –
Maujpur Corridor of Delhi MRTSPhase-IV project))
Document Name Method Statement for Bored Cast in Situ Piling
Document Code LONGJIAN-KEC/DMRC-DC02/MS/04 Revision No: 02 Date: 03/03/2020

9.6 Final post bore cleaning


The bottom of pile bore shall be cleaned of all loose materials with a cleaning bucket. The
final depth shall be checked with a sounding chain.

9.7 Sonic tube installation


• Install a bottom cap onto the first sonic tube.
• Fix the sonic tube to the rebar cage by trying the steel wire around the fixing
ears and tube.
• Fix the next tube to the rebar cage as the step 2.
• Push the two tubes together. (Push –fit mark to ensure full engagement).
• Ensure both ears are aligned. Then connect tightly the ears of both tubes with a
steel wire.
• Repeat the process above till all tubes is installed.

9.8 Placement of reinforcement cage


After ensuring the depth of the bore, pre-fabricated reinforcement cage as per the
approved drawing shall be lowered. The rebar cage shall be lowered into the bore by
gravity only, either with the rig or by crane. The lifting plan and other related documents
will be submitted prior to any lifting activity with help of crane. For piles requiring
multiple length of rebar cages, the first length of cage shall be lowered into the bore by
gravity only, either with the rig or by crane and is placed in position, lapped/joined in
place and then cage is lowered. The laps shall be welded (at location/in-situ) or joined

Page 21 of 30
LONGJIAN-KEC (JV)
DELHI METRO RAIL PROJECT, PHASE - 4, PROJECT :
Contract DC-02: Part Design and Construction of Elevated
Viaduct from Maujpur (excluding) to Majlis Park
(excluding) including Bridge across river Yamuna,
Integrated Elevated Viaduct with PWD flyover at lower LONGJIAN – KEC JV
deck & metro line at upper deck from Yamuna Vihar to
Bhajanpura and 08 Elevated Stations of Majlis Park –
Maujpur Corridor of Delhi MRTSPhase-IV project))
Document Name Method Statement for Bored Cast in Situ Piling
Document Code LONGJIAN-KEC/DMRC-DC02/MS/04 Revision No: 02 Date: 03/03/2020

with couplers before lowering. After lowering of the cage, tremie pipe shall be lowered
and it should be water tight with minimum diameter of 200mm.
9.9 Flushing Operation
Before the concreting starts the bore shall be flushed with fresh polymer suspension and
bore shall be covered with proper covering arrangement Immediately .Lowering of the
cage, tremie pipes of minimum 200/250 mm dia of suitable length are jointed together
and lowered into the the bore and the polymer shall be pumped through the tremie pipe.
Fresh polymer is pumped into pile bore through the tremie pipe & returned
contaminated polymer is collected at ground level and same is recycled through polymer
tank kept at ground level. Flushing shall be continued density of return mud is less than
1.2gm/cc. The polymer slurry collected during the flushing operation shall be collected in
the compartments of the vat.
9.10 Pile Concreting
Pile concreting shall be done using tremmie pipe method. Generally, each tremmie pipe
length is 1 to 2 meters & The vacuum distance between the bottom tip of pile and
foundation level of pile is 300mm. Only fresh batched concrete shall be used, and the
concreting has to be done continuously without interruption.
Tremmie pipe concreting shall be done as per IS: 456 and IS: 2911 (Part-I/Sec-2) using a
pipe of minimum 200mm diameter. The steel hopper at the top shall have a volume
greater that the tremmie pipe volume. A suitable steel stopper at the neck of the hopper
which can be withdrawn with least resistance or a sliding plug can be used. The hopper
and pipe shall be clean of encrusted concrete, dust, debris etc., and shall be watertight.
Concrete placing into the hopper shall be facilitated using suitable ramps for direct pour
from the transit mixers. In case of inaccessible locations, concrete can alternatively be
placed into the hopper by concrete pump. The hopper shall be filled with concrete
completely and then the stopper plate is removed to allow the concrete to flow into the
pipe. Subsequent charges of concrete shall be maintained continuous as required till the
Page 22 of 30
LONGJIAN-KEC (JV)
DELHI METRO RAIL PROJECT, PHASE - 4, PROJECT :
Contract DC-02: Part Design and Construction of Elevated
Viaduct from Maujpur (excluding) to Majlis Park
(excluding) including Bridge across river Yamuna,
Integrated Elevated Viaduct with PWD flyover at lower LONGJIAN – KEC JV
deck & metro line at upper deck from Yamuna Vihar to
Bhajanpura and 08 Elevated Stations of Majlis Park –
Maujpur Corridor of Delhi MRTSPhase-IV project))
Document Name Method Statement for Bored Cast in Situ Piling
Document Code LONGJIAN-KEC/DMRC-DC02/MS/04 Revision No: 02 Date: 03/03/2020

pile bore is cast to the specified height. The bottom of tremmie pipe shall always be inside
concrete forming watertight system. The tip shall be minimum 1.5metres inside concrete
depending upon rate of pouring concrete. The tremmie pipe shall be withdrawn in stages
as and when concrete builds up in the bore. Care shall be taken when vertical movement
is imparted on tremmie pipe to force concrete down into the pipe and when tremmie pipe
is raised so that the rebar cage is not disturbed from its position.
In Case of concrete being placed by tremmie method and pile cut off level less than
1.0 meter below the found level, concrete shall be cast to the piling platform level
to the permit over flow of the concrete for visual inspection. In case COL of pile Is
more than 1.0 meter below working level then concrete shall be casted to a
minimum of one meter above COL/COL to be mentioned in approved drawing.
Entire concrete pouring process should be completed within two hours.
Concrete slump should be maintained 150 to 180 (as per clause no 7.3.2 of IS 2911
Part 1/sec 1:2010) at time of concrete pouring.
The time interval between the completion of boring and placing of concrete shall
not exceed 6 Hours.
9.11 Installation Records
Detailed pile installation records in duplicate for each pile installed shall be maintained.
The details of the record shall include among others, pile number, coordinates, pile size,
pile elevation, pile cut-off, ground level, pile bore data (such as length of liner, boring
duration, bored length, pile length etc.), concreting record (grade of concrete, as mixed
slump, volume of concrete, timing, pile cage details, etc.)
9.12 Clean-up
Upon completion of piling, casings, equipment, construction tools, debris, scrap, muck , if
any, shall be removed from the place of work. Generally after replacement of use of
Bentonite , for soil stabilization , with polymer , there is usually negligible or no muck
produced which inturn shall be loaded with backhoe loader into tipper & shall be
Page 23 of 30
LONGJIAN-KEC (JV)
DELHI METRO RAIL PROJECT, PHASE - 4, PROJECT :
Contract DC-02: Part Design and Construction of Elevated
Viaduct from Maujpur (excluding) to Majlis Park
(excluding) including Bridge across river Yamuna,
Integrated Elevated Viaduct with PWD flyover at lower LONGJIAN – KEC JV
deck & metro line at upper deck from Yamuna Vihar to
Bhajanpura and 08 Elevated Stations of Majlis Park –
Maujpur Corridor of Delhi MRTSPhase-IV project))
Document Name Method Statement for Bored Cast in Situ Piling
Document Code LONGJIAN-KEC/DMRC-DC02/MS/04 Revision No: 02 Date: 03/03/2020

dumped in designated dumping yard location identified by DMRC. Exposed and


finished concrete and dowel surface shall be left in a clean condition.

10. Environmental Impact


Synthetic polymer is biodegradable and non-pollutant or harmful to the environment.
There are several methods for treatment of polymer slurries after usage. The most
common is perhaps the treatment with Calcium Hypochlorite and Muriatic acid. The
treatment neutralizes the pH levels, eliminating the system, turning the slurry into
residual water. This procedure is applied only once at the end of the project, unless
otherwise users decides to re-use the slurry in another project or location.
The acid is used to neutralize alkaline ph.. Quantities to be applied vary from 3 to 5 liters
per M3 of slurry. The tanks must be agitated when this product is added.
The Calcium Hypochlorite is available in the market in granular form and different
concentrations. The ideal concentration for this process ranges 60-70 %. The quantities to
be used vary from 0.1-0.5 kg per M3 of slurry by adding the product directly to the slurry
after neutralizing the ph. The result is the transformation of the slurry in “residue water”.
The term “residue water” is used to best describe the sediment fines and soil particles
previously in suspension.
The product resultant from this treatment can be directly discharged without any danger
of contamination, to the environment of sewerage systems accordingly to local laws.

11.0 Tolerances
(a) Angular Deviation from vertical : 1.5% of vertical pile
(b) Piles should not deviate more than 75mm or D/6 whichever is less (75mm or D/10
which ever is more in Case of piles having diameter more than 600mm) from their
designed positions at the working level. In case of single pile under a column the
positional deviation should not be more than 50mm or D/6 whichever is less (100mm in
Page 24 of 30
LONGJIAN-KEC (JV)
DELHI METRO RAIL PROJECT, PHASE - 4, PROJECT :
Contract DC-02: Part Design and Construction of Elevated
Viaduct from Maujpur (excluding) to Majlis Park
(excluding) including Bridge across river Yamuna,
Integrated Elevated Viaduct with PWD flyover at lower LONGJIAN – KEC JV
deck & metro line at upper deck from Yamuna Vihar to
Bhajanpura and 08 Elevated Stations of Majlis Park –
Maujpur Corridor of Delhi MRTSPhase-IV project))
Document Name Method Statement for Bored Cast in Situ Piling
Document Code LONGJIAN-KEC/DMRC-DC02/MS/04 Revision No: 02 Date: 03/03/2020

case of piles having diameter more than 600mm) Greater tolerances may be prescribed for
piles cast over water .

12. Safety
1) All safety norms and precautions to be taken care as per the site safety plan
(SHE plan) for each activity and safety clearance to be taken before commencing
the activity.
2) All staff and workmen shall wear safety gear such as helmet, fluorescent vest
safety shoes, Hand gloves, noise mask etc. Safety harness with shock observer
while working at height and face shield with suitable dark glass for welding work
shall be used.
3) The work area shall be properly barricaded as laid down in the traffic management
plan.
4) The edge of the boring hole shall be guarded with the help of fabricated TMT cage
to cover the complete bore and barricading shall be ensured to cordon off the area .
The cage shall be equipped with lifting arrangement so as to provide ease in lifting
operations.
5) First aid box shall be kept at site.
6) Rig-operator, Riggers and Foreman shall have adequate knowledge and
experience.
7) Lifting tools and tackles shall have load test certificates of Competent Person.
8) Persons shall not be under the suspended load while lifting load.
9) Loose materials/tools shall not be left at height in the mast.
10) Piling area shall be restricted to unauthorized persons.
11) While the rig is in operation, nobody including the concerned workmen shall be
allowed in the operation area.
12) Earth slush shall be removed, and passage shall be kept clear
Page 25 of 30
LONGJIAN-KEC (JV)
DELHI METRO RAIL PROJECT, PHASE - 4, PROJECT :
Contract DC-02: Part Design and Construction of Elevated
Viaduct from Maujpur (excluding) to Majlis Park
(excluding) including Bridge across river Yamuna,
Integrated Elevated Viaduct with PWD flyover at lower LONGJIAN – KEC JV
deck & metro line at upper deck from Yamuna Vihar to
Bhajanpura and 08 Elevated Stations of Majlis Park –
Maujpur Corridor of Delhi MRTSPhase-IV project))
Document Name Method Statement for Bored Cast in Situ Piling
Document Code LONGJIAN-KEC/DMRC-DC02/MS/04 Revision No: 02 Date: 03/03/2020

13) Exposed reinforcement heads shall be properly covered, and the area barricaded.
14) For storage of any chemical MSDS shall be displayed and to prevent any leakage
dip tray Shall be used.
15) The polymer tank and sedimentation tank area shall be barricaded for restricted
entry and access to only authorized personals shall be ensured. The top of the tank
shall be provided with working platform for inspection and testing and guarded
by hand rails to prevent any injury due to falling. The area shall be given access to
authorized personals only for the duration of testing and immediately shall be
closed after that.
16) Special precautions as mentioned in point no. 11 of Hazard & risk assessment shall
be taken while working in river Yamuna.
Specific preventive measures like a life guard , life jackets and boat shall be kept
ready to prevent the workmen from drowning in flash flood situations and constant
co-ordination shall be made with meteorological departments for flood alerts.
Parallelly all the construction activities shall be monitored carefully in order to avoid
water pollution in river.

Page 26 of 30
LONGJIAN-KEC (JV)
DELHI METRO RAIL PROJECT, PHASE - 4, PROJECT :
Contract DC-02: Part Design and Construction of Elevated
Viaduct from Maujpur (excluding) to Majlis Park
(excluding) including Bridge across river Yamuna,
Integrated Elevated Viaduct with PWD flyover at lower LONGJIAN – KEC JV
deck & metro line at upper deck from Yamuna Vihar to
Bhajanpura and 08 Elevated Stations of Majlis Park –
Maujpur Corridor of Delhi MRTSPhase-IV project))
Document Name Method Statement for Bored Cast in Situ Piling
Document Code LONGJIAN-KEC/DMRC-DC02/MS/04 Revision No: 02 Date: 03/03/2020

APPENDIX A
ITP &CHECKLIST

Page 27 of 30
LONGJIAN-KEC (JV)
DELHI METRO RAIL PROJECT, PHASE - 4, PROJECT :
Contract DC-02: Part Design and Construction of Elevated
Viaduct from Maujpur (excluding) to Majlis Park
(excluding) including Bridge across river Yamuna,
Integrated Elevated Viaduct with PWD flyover at lower LONGJIAN – KEC JV
deck & metro line at upper deck from Yamuna Vihar to
Bhajanpura and 08 Elevated Stations of Majlis Park –
Maujpur Corridor of Delhi MRTSPhase-IV project))
Document Name Method Statement for Bored Cast in Situ Piling
Document Code LONGJIAN-KEC/DMRC-DC02/MS/04 Revision No: 02 Date: 03/03/2020

APPENDIX B
HAZARD IDENTIFICATION AND RISK
ASSESSMENT

Page 28 of 30
LONGJIAN-KEC (JV)
DELHI METRO RAIL PROJECT, PHASE - 4, PROJECT :
Contract DC-02: Part Design and Construction of Elevated
Viaduct from Maujpur (excluding) to Majlis Park
(excluding) including Bridge across river Yamuna,
Integrated Elevated Viaduct with PWD flyover at lower LONGJIAN – KEC JV
deck & metro line at upper deck from Yamuna Vihar to
Bhajanpura and 08 Elevated Stations of Majlis Park –
Maujpur Corridor of Delhi MRTSPhase-IV project))
Document Name Method Statement for Bored Cast in Situ Piling
Document Code LONGJIAN-KEC/DMRC-DC02/MS/04 Revision No: 02 Date: 03/03/2020

APPENDIX C

LIFT PLAN
FOR
REINFORCEMENT CAGE

Page 29 of 30
LONGJIAN-KEC (JV)
DELHI METRO RAIL PROJECT, PHASE - 4, PROJECT :
Contract DC-02: Part Design and Construction of Elevated
Viaduct from Maujpur (excluding) to Majlis Park
(excluding) including Bridge across river Yamuna,
Integrated Elevated Viaduct with PWD flyover at lower LONGJIAN – KEC JV
deck & metro line at upper deck from Yamuna Vihar to
Bhajanpura and 08 Elevated Stations of Majlis Park –
Maujpur Corridor of Delhi MRTSPhase-IV project))
Document Name Method Statement for Bored Cast in Situ Piling
Document Code LONGJIAN-KEC/DMRC-DC02/MS/04 Revision No: 02 Date: 03/03/2020

Page 30 of 30