LỤC SỐ 1
PHẠM VI CÔNG VIỆC DỰ ÁN ĐIỆN GIÓ KOSY BẠC LIÊU 40MW
Rate 23,300
No Description Unit Q'ty Price (VND) Total Price (VND)
1. Wind farm civil works 325,999,933,859
Foundations pcs 9 19,694,191,203 177,247,720,823
Crane Pads pcs 9 4,997,683,488 44,979,151,392
Road Total ‐
Access road (width 5m) m 1772 9,598,593 17,008,705,936
Internal road (width 5m) m 3726 9,598,593 35,764,355,709
Bridge pcs 6 6,000,000,000 36,000,000,000
Miscellaneous ‐
Jetty supply and construction pcs 1 15,000,000,000 15,000,000,000
Site preparation ls 15,000,000,000 ‐
‐
2 MV Networks ‐
MV ‐ OVHL m 5.80 2,145,466,170 12,443,703,788
‐
3 HV Substation ‐ 50MVA ‐ 220KV ‐
Electrical part set 1 71,428,217,238 71,428,217,238
Civil part set 1 16,679,080,057 16,679,080,057
Expansion for Hoabinh 220KV switch yard set 1 9,000,000,000 9,000,000,000
Fire fighting system (PCCC) set 1 5,000,000,000 5,000,000,000
‐
4 HV Transmission line ‐
HV ‐ OVHL 220KV‐ singe line ACSR 185 m 1650 5,115,010 8,439,765,804
‐
5 Inland transportation ‐
Custome clearance set 1 ‐
Transportation for Tuabin Tuabin 9 2,796,000,000 25,164,000,000
Transportation Tower Tower 9 1,398,000,000 12,582,000,000
‐
6 Installation of Tower + Tuabin ‐
Installation of Tower + Tuabin (Mechanical) Tuabin 9 4,660,000,000 41,940,000,000
Electrical install Tuabin 9 300,000,000 2,700,000,000
‐
7 Grid connection + COD service set 1 5,000,000,000 5,000,000,000
‐
‐
8.1 Technical design + approved set 1 10,000,000,000 10,000,000,000
8.2 Supervising set 1 12,000,000,000
‐
9 Project Management set 1 28,000,000,000 28,000,000,000
TOTAL BUDGET 601,789,060,077
USD $ 25,827,856.66
Ghi chú
‐ Bảng giá trên chưa bao gồm các chi phí bảo lãnh
Giá trên là giá tạm tính và sẽ được làm rõ trong quá trình đàm phán hợp đồng EPC chi tiết và đàm phán với các nhà
‐ thầu phụ