Professional Documents
Culture Documents
Catchment Area:
Catchment area is calculated using Google earth pro. So total area found to be as
Net Head:
From the Google map pro, we found the Gross head = 90m
=90 – (0.5*90)
= 85.5
❖ Mean monthly flow using Medium Hydropower Study Project (NEA 1997) Method have been
tabulated as follows along with MHSP prediction equation constants for mean flow.
Sample calculation:
For November,
=0.00792*(635)0.8804*(2594)0.2707
=19.51 m3/s
Where, C, A1, A2 are Medium Hydropower Study Project (NEA 1997) prediction equation
constants for mean flow.
C A1 A2
Month
January 0.03117 0.8644 0 8.47
February 0.02417 0.8752 0 7.04
March 0.02053 0.8902 0 6.5979
April 0.01783 0.9558 0 8.7683
May 0.01193 0.9657 0 6.256
June 0.01135 0.9466 0.2402 34.75
July 0.01641 0.9216 0.3534 104.02
August 0.02592 0.9095 0.3242 120.75
September 0.02206 0.8963 0.3217 92.48
October 0.01504 0.8772 0.2848 41.69
November 0.00792 0.8804 0.2707 20.06
December 0.00538 0.889 0.258 13.04
❖ The mean monthly flows in m3/s if plotted versus their respective months in hierarchical order
give a curve known as hydrograph. From the graph, one can have an idea about during which
month maximum and minimum discharge is available.
Hydrograph Plot
140
120.75
120 104.02
100 92.48
Disharge(Q)
80
60
41.69
34.75
40
20.06
13.04
20 8.47 7.04 6.5979 8.7683 6.256
Months of a year
Flow Duration Curve tells us for what percentage of time (year) ‘Q’ discharge is available. For
FDC, following tabulated data have been used: -
Dependent
b a c
variable Discharge(m3/s)
QMax(Q0) 0.812 0.537 0.061411 789.143
= 0.00891460*6350.9239*25940.2018
=16.92m3/s
800
700
600
500
400
300
200
100
0
Qmax Q25% Q45% Q65% Q85% Q95% Qmin
Discharge
Or, RR =0.6256m3/s
MONTHLY ENERGY GENERATION:
3
Month MMF(m /s) MMF-RR Discharge(m3/S) KW generated MWh Gen / M
jan 8.47 7.8444 7.8444 5629.050858 4052.916618
feb 7.04 6.4144 6.4144 4602.899371 3314.087547
mar 6.5979 5.9723 5.9723 4285.653516 3085.670532
apr 8.7683 8.1427 8.1427 5843.107494 4207.037396
may 6.256 5.6304 5.6304 4040.310024 2909.023217
jun 34.75 34.1244 16.92 12141.59662 8741.949566
jul 104.02 103.3944 16.92 12141.59662 8741.949566
aug 120.75 120.1244 16.92 12141.59662 8741.949566
sep 92.48 91.8544 16.92 12141.59662 8741.949566
oct 41.69 41.0644 16.92 12141.59662 8741.949566
nov 20.06 19.4344 16.92 12141.59662 8741.949566
dec 13.04 12.4144 12.4144 8908.430087 6414.069663
Annual Energy Generated(MWH) 76434.50237
= 90-0.05*90
= 85.5 m.
Head KW.
= 16.92*9.81*85.5
Power input to the turbine = 14191.73 KW.
Assuming turbine, generator and transformer efficiency to be 90%, 97% and 98% respectively,
Electrical Power Output = 0.9*0.97*0.98*32469.138 KW
=12141.5 KW
The sample calculation for monthly energy generation for May is:
= 76434.5 MWh
=0.9*0.97*0.98*16.92*9.81*85.5*12*30*24/1000
=104903.39 MWh
Annual Plant Factor = (annual energy generation)/ (max. annual energy generation possible)
=76434.5/104903.39
=0.7286
Turbine Selection:
=14.28 MVA
= 6.07/0.85 MVA
=7.14 MVA
16.92
Design discharge/ unit = = 8.46 m3/s
2
The following points must be considered during selection of number and size of units: -
1) Hydrology: - Generally for design discharge of Q45%, two units are selected. So, two units
have been selected for our hydropower plant.
2) System size: - The size of a unit must be less than 10% of the system size. The total system size
of Nepal is about 800 MW and capacity of a unit of our power plant is 6.07 MW, which is only
0.76% of the whole system capacity.
3) Maintenance: - The design discharge is available for 6 months and during dry season one of
the units can be maintained.
1. Net head: The net head of the site provided to us is 85.5m. From the table given below,
we have four choices namely, Francis, Pelton, Michell-Banki and Turgo. So, we go for
next criterion for the selection of turbine that is discharge.
2. Discharge: We have design discharge per unit as 8.46 m3/s which is low and discharge
available during the driest month that is during May is 6.256 m3/s allowing the riparian
release of 10% which is more than 65% of design discharge. So, during the driest month
we can put a unit under operation and maintain the other.
3.
85.5
6.256
From this chart we can select Francis turbine.
4. Specific speed: - It is defined as the speed through which the model runner turns with a
head of 1m and a discharge Q such that the generator power is 1KW and is given by: -
Ns= (nP0.5)/h1.25
Where, Ns= specific speed
n= generator synchronizing speed
P= power
h= net head
Following graph was used to determine specific speed for Francis turbine: -
P=6071 KW
= 550.56 rpm
No of poles Sync. Speed (at 60Hz) Sync. Speed (50 Hz)
2 3600 3000
4 1800 1500
6 1200 1000
8 900 750
10 120 600
12 600 500
Synchronizing Speed(n)=600rpm
Lab-2
Calculation & design of rating & number of Generator and bus bar.
Generators:
= (12.14 * 0.97)/0.85
= 13.85 MVA
Frequency = 50Hz
Number of Poles = 10
Duty: The duty is continuous. Because for operations 24 hours 9day, 7 days a week, under full
load conditions.
LOW VOLTAGE BUS BAR:
A 400V Low Voltage Distribution System is used in this particular installation which is shown in
the Single Line Diagram attached here. It includes a 400V bus bar which receives power from both
units and there is also a diesel generator for black start. This scheme consists of three full capacity
redundant power source. For example, if one unit is out the Low Voltage Bus Bar gets power from
unit two and vice versa. Furthermore, if both units are out the Diesel Generator (DG) come into
operation for black start.
A 11kV Medium Voltage Bus Bar is used in this particular installation as shown in the Single Line
Diagram attached here. The Medium Voltage Bus Bar supplies power to the low voltage bus bar
and local distribution using a 11: 0.4 kV isolation transformer.
A 66kV High Voltage Bus Bar is used in this particular installation as shown in the Single Line
Diagram attached here. It is used to supply power from the generating stations to various sub
stations. It consists of two separate bus bars viz. the Modified Main Bus and the Transfer Bus. The
main objective of using two bus bars is that continuous power can be supplied even during failure
of one of the buses or if one of the buses is to be disconnected for maintenance purpose.
GENERATOR GROUNDING RESISTANCE:
Earthing Resistance (Rn) < Reactance Developed Between Line and Ground (Xc).
CALCULATION OF Xc:
CALCULATION OF Rn:
The value of Rn is calculated by choosing the appropriate ratio of Xcg / Rn from the following plot.
The ratio should be selected in such a way that
Re - striking Voltage is always less than two times the system voltage.
Hence, the ratio Xcg/Rn = 1.5 is chosen considering the above-mentioned argument. This is
indicated in the plot below:
So,
→ 𝑹𝒏=𝟏𝟖𝟑𝟕.𝟐𝟖𝟕𝛀
Rn is not directly connected to the ground, as the heat dissipated in such a high resistance value
may be very high. So, a dry type transformer arrangement as shown below shall be used.
Taking the transformer ratio of the dry transformer to be [11/√3 : 0.24 kV ], then the transformer
ratio (n) = 26.461
𝑹 = 𝑹𝒏 /𝒏2
GENERATOR LEADS:
Generator lead means the circuit between the generator terminals and the unit transformer. The
equipment selected depends upon the distance between the generator and transformer, the capacity
of the generator, type of generator breaker employed and the economics of installation.
𝑃
We have, 𝐺𝑒𝑛𝑒𝑟𝑎𝑡𝑜𝑟 𝑂𝑢𝑡𝑝𝑢𝑡 𝐶𝑢𝑟𝑟𝑒𝑛𝑡 = √3VcosØ
6.07
=
√3∗11∗0.85
= 374.81𝐴
Since, this current is less than 4kA and in consideration to fault we choose regenerated generator
leads as it is less prone to line to line faults for this design.
Excitation System:.
The Excitation System used in the plant is Brushless DC Excitation system. It consists of dry type
transformer. A solid-state rectifier rotates with the shaft converting the AC output from the
generator into the DC which is then supplied to the rotating field coils of the main generator
without the need of brushes.
TRANSFORMER SELECTION:
In this design three phase delta – delta transformer is used. Each generating unit is then connected
to individual transformer i.e. for this case there are two transformers for the two generating units.
The rating of the transformer is chosen such that its capacity is higher than the maximum capacity
of the generating units. Since the generating capacity of each unit is 7.14 MVA for 0.85 p.f, the
transformer rating is chosen to be 7.2 MVA.
Lab-3
Calculation and design of transmission line, rating of circuit breakers & transformer selection.
For Nc =1
Lt P *1000
Economical Voltage (V eco) = 5.5 +
1.6 cos * Nc *150
= 63.94 KV
For Nc =2
Lt P *1000
Economical Voltage (V eco) = 5.5 +
1.6 cos * Nc *150
= 52.92 KV
𝑀𝑓 =𝑃𝑚𝑎𝑥/ 𝑆𝐼𝐿
Nc =1, Zc =400 Ω
𝑆𝐼𝐿 = 𝑉2/ 𝑍𝑐
= 662/ 400
= 10.89 MW
𝑀𝑓 = 𝑃𝑚𝑎𝑥/ 𝑆𝐼𝐿
= 12.14/10.89
=1.11<𝑀𝑓 limit
Nc =2 , Zc =200 Ω
𝑆𝐼𝐿 =𝑉2/Zc
𝑀𝑓 = 𝑃𝑚𝑎𝑥 /𝑆𝐼𝐿
= 12.14/ 21.78
= 0.55<𝑀𝑓 limit.
P / Nc
∴ Line current (I) =
3 * Vll * cos
12.14 / 1 * 1000
=
3 * 66 * 0.85
= 124.93 A
1) Rabbit
Current Carrying Capacity = 208 A > 124.93A
Resistance @ 200C = r = 0.5449 Ω/ km
Total Resistance @ 200C = R20 = r * Lt
= 0.5449 * 80
= 43.592 Ω
Resistance @ 650C = R65 = R20 (1+α Δ t) = 43.599*(1+ 0.004* (65-20))
= 51.43 Ω
∴ Total loss = p =3* IL2* R65
= 3*(124.93)2 * 51.43
= 2.408 MW
∴ Efficiency (ɳ) = 1 – PL /P = 1 – 2.4/12.14 = 80.1 %
2) WOLF
Since, the maximum current capacity of “WOLF” Conductor is 430 A (at 40⁰C ambient
temperature). hence, “WOLF” conductor is used for power transmission.
Let us assume that, transmission line is connected in an equilateral triangle configuration as shown
in the figure below:
D1 = 1.78m D2 = 1.78m
D3 = 1.78m
𝑉
Spacing (D) = √s + 150 , where V is in KV and s( sag ) is in meter.
= 3.4m
66
Therefore spacing (D) = √3.4 + 150 = 2.28 m
1
𝑡ℎ𝑒𝑛, D = (𝐷1 ∗ 𝐷2 ∗ 𝐷3)3
1
= (2.28 ∗ 2.28 ∗ 2.28)3
= 2.28𝑚
= 2288𝑚𝑚
𝑟′ = re−0.25
18.13
= 𝑥 𝑒−0.25
2
= 7.05𝑚𝑚
= 3.63Ω/𝑘𝑚
Now, the reactance per unit length of the transmission line for Wolf conductors is
3.63 Ω/km.
= 290Ω
GENERATOR SUB TRANSIENT REACTANCE SELECTION:
The generator sub transient reactance is calculated from the table as shown below:
From graph,
X(pu) RPM
0.26 150
X 165
0.28 100
Using interpolation method,
𝑋−0.26 165−150
=
0.28−0.25 100−150
Or, X = 0.254
TRANSFORMER REACTANCE SELECTION:
And for transformer capacity of rated 7.14 MVA and high voltage winding of 66KV we chose the
maximum of 0.0915 p. u reactance from above table.
Fault calculation:
= 377.9𝐴
11 x 103
𝐵𝑎𝑠𝑒 𝐼𝑚𝑝𝑒𝑑𝑎𝑛𝑐𝑒 =
√3x 377.9
= 16.8Ω
7.14
𝐹𝑜𝑟 generator, 𝑅𝑒𝑎𝑐𝑡𝑎𝑛𝑐𝑒 = 0.254 𝑥 7.2
= 0.25𝑝𝑢
66 x 103
𝐵𝑎𝑠𝑒 𝐼𝑚𝑝𝑒𝑑𝑎𝑛𝑐𝑒 =
√3x 62.98
= 605.03 Ω
= 0.479 𝑝𝑢
= 7.944 𝑝𝑢
𝐼𝑓𝑎𝑢𝑙𝑡 = 7.944∗377.9 =3 𝑘𝐴
𝐼𝑓 =1 /0.134 = 7.44 𝑝𝑢
HV breaker
• At fault point 3,
I𝑪𝑩𝟒=2.9284*377.9 = 1.1 KA
• At point 4,
= 0.12 pu
𝐼𝑓 = 1/ 0.12 = 5 𝑝𝑢
• At fault point 6
= 0.29
𝐼𝑓 = 1/ 0.29
= 3.438 𝑝𝑢
𝐼𝑓 = 3.438∗377.9 = 1.299𝐾𝐴
Fault at point 5,
𝐼𝑓 = 1/ 0.25
= 4 𝑝𝑢
𝐼𝑓 = 4∗377.9 = 1.511𝐾𝐴
• Fault at point 8,
𝐼𝑓 =1/ 0.479
= 2.08 𝑝𝑢
Similarly,
• fault at point 7,
= 0.17 pu
𝐼𝑓 =1/ 0.17
= 5.85 𝑝𝑢
Making current=2.55*367.78=937.83A
According to the table, we choose CB with normal rated current of 200A for the High Voltage side
and the Transmission Line. But the normal rated current is this design is 73.48 A which is very
less than 200A so a proper scheme using CTs and. Relays will be used to trip the CB.
Lab -4
Selection of station service Transformers and Diesel power plant
The hydro plant’s electric auxiliaries consist of unit and station auxiliaries. The unit auxiliaries are
the auxiliaries associated with each unit. The loss of a unit auxiliary immediately affects the
availability of the unit, causing a unit trip or reduced unit output.
The station auxiliaries are auxiliaries utilized for the entire powerhouse or station. The loss of a
station auxiliaries will not affect the unit operation immediately but after a period of time. Power
is furnished to the hydro plant’s electric auxiliaries by the station auxiliary transformer (SAT) for
station auxiliaries or by the unit auxiliary transformer (UAT) for unit auxiliaries
There are generally two schemes for supplying the power to the auxiliaries.
1. Using the power from the generator in this scheme, the power generated from the generator is
directly connected to the isolation transformer and supply is fed to the auxiliaries of the power
house.
2. Using the power from the HV side of the switchyard. In this scheme the step-down transformer
associated with the HV bus bar feeds the auxiliaries.
In our power plant design, we preferred scheme 1 considering economic and safety concerns.
Redundancy
Any hydropower plant needs regular maintenance for scheduled outage or forced outage in worst
condition. For that critical components need to be duplicated for backups are governor oil pump,
transformer, oil pump, transformer cooling water pumps, ACB air compressor etc. This kind of
duplication or spare parts of the critical components is called redundancy. Generally, in low
voltage distribution system there are three power sources, namely main generator, station
transformer and diesel generator. For redundant component or critical component supply is given
from any one of these in case of failure of any one of the units. Diesel generator comes in contact
when two of the units are out or when there is complete black out in power house, even when there
is no feedback from the grid.
Selection of station service transformer capacity Because of the redundancy described above the
total connected load of the power plant is always greater than the total consumed load. This kind
of duplication helps in making the power plant reliable. The maximum demand that is expected on
the station service system is the basis for developing station service transformer rating. The
minimum diversity factor must be 0.75. During high activity periods or plant emergencies, higher
than normal station service loads can be expected and if a small diversity factor has been used, the
system may not have adequate capacity to handle its loads.
In our power plant we chose minimum diversity factor of 75% of our demand kVA. Hence, we
chose station service transformer capacity 550 KVA for each.
“Black start” capability is desirable at hydro plants since the plants can assist in re-establishing
generation for the power system in an emergency. “Black start” capability is defined as the ability
of the plant, without an external source of power, to maintain itself internally, start generating
units, and bring them up to speed-no-load conditions, close the generator breakers, energize
transformers and transmission lines, perform line charging as required, and maintain units while
the remainder of the grid is re-established. The plant must then resynchronize to the grid.
Here in our design for black start capability we choose diesel generator and capacity is calculated
by using capacity of most important auxiliaries like governor oil pump, transformer water cooling
pump etc.
For future growth of load, we add 20% extra load in our demand KVA. Hence our capacity of
diesel plant is 1000KVA.
Lab: - 5
1. Selection of an appropriate Battery Bank and Battery Charger Scheme & Calculation of
the necessary battery capacity with reasons or assumptions.
Depending upon the types of equipment and their power requirements, different rated values of dc
voltage is selected. In the table below, rated dc voltage for auxiliaries are tabulated.
Among various battery viz lead acid, NiCd, NiMH, lithium ion type, lead acid type has highest
efficiency, high number of cycles neglecting its short comings like gassing pollution, higher
upfront cost, lower energy density, less depth of discharge. In order to control the problem of
gassing, we choose vent regulated lead acid.
The characteristics of lead acid battery.
From the duty cycle curve, it is clear the system draws 80A for 1.5 hours and 40 A for remaining
6.5 hours.
Hence Battery capacity: 80*1.5+ 40*6.5=380Ah
Allowing the 20% growth for future expansion the designed capacity is 350+0.2*350=420Ah.
For greater reliability and segregation of faults we use two battery banks 210Ah.
# Number of cells
Therefore, we require 66 numbers of cells voltage ranging from 2V at fully charged to 1.8V as end
of discharger voltage at maximum discharge.
# Battery room size
In order to safely put battery better to provide one separate room or as compromise can use area
enclosed with fence for protection against accident contact. Area should be well ventilated so that
exhaust air from the room does to enter any other room in the power plant. Rating of battery
decrease with temperature should be multiplied by correction factor below certain definite
temperature. So, adequate heat must be provided for full rated performance out of the cells. Battery
charging equipment’s, contactors and arc producing device and control are not in battery room.
Thermostat for heater should be sealed. The cells should be mounted in rows on racks permitting
viewing the edges of plates and the bottom of the cells from one side of the battery. The lighting
fixtures in the room should be of the vapor-proof type, with the local control switch mounted
outside by the entrance to the room. Referring to the catalogue of Battery Company.
For 110V battery system (i.e. Two battery banks of 210Ah capacity and 66 cells:)
Size of 110 V system having 960mm gap between the two banks=1661mm*(1020*2+960)
Length*Width=2m*3m
Total room area with 1m gap around the battery banks (length*width) =4m*5m
Battery Chargers
For backups there is battery chargers in the power plant. Battery chargers are used to convert ac to
dc to charge station batteries which helps in supplying power or dc loads during normal operation.
Two sets are generally preferred one for normal use while other for backup. The charger capacity
should be sufficient for supplying the continuous DC load normally carried while recharging the
station battery at the normal rate. The chargers should be of the “battery eliminator” type
(additional filtering) allowing them to carry station DC loads while the battery is disconnected for
service.
In our design, we selected constant current system as the Battery charging system.
In this system, the charging current is kept constant by varying the supply voltage to overcome the
increased back emf of cells. If charged on a dc supply, the current is controlled by varying the
rheostat connected to the circuit. Although it takes comparatively longer time but it is reliable and
efficient. The efficiency of constant voltage charging system is reduced by 10% or more than
constant current charging system. So, it is appropriate for our design.
Constant-Voltage Charging
Constant-voltage (often called constant-potential) chargers maintain nearly the same voltage input
to the battery throughout the charging process, regardless of the battery's state of charge. Constant-
voltage chargers provide a high initial current to the battery because of the greater potential
difference between the battery and charger. A constant voltage charger may return as much as
70% of the previous discharge in the first 30 minutes. This proves useful in many battery
applications involving multiple discharge scenarios. As the battery charges its voltage increases
quickly. This reduces the potential that has been driving the current, with a corresponding rapid
decrease in charge current as depicted in Figure. As a result, even though the battery reaches
partial charge quickly, obtaining a full charge requires prolonged charging. Constant current
system.
The charge algorithm for lead-acid batteries is similar to lithium-ion but differs from nickel based
chemistries in that voltage rather than current limiting is used. The charge time of a sealed lead-
acid battery is 12-16 hours (up to 36 hours for larger capacity batteries). With higher charge
currents and multi-stage charge methods, the charge time can be reduced to 10 hours or less. Lead-
acid cannot be fully charged as quickly as nickel or lithium-based systems. It takes about 5 times
as long to recharge a lead-acid battery to the same level as it does to discharge. On nickel based
batteries, this ratio is 1:1, and roughly 1:2 on lithium-ion.
A multi-stage charger first applies a constant current charge, raising the cell voltage to a preset
voltage (Stage 1 in Figure 1). Stage 1 takes about 5 hours and the battery is charged to 70%. During
the topping charge in Stage 2 that follows, the charge current is gradually reduced as the cell is
being saturated. The topping charge takes another 5 hours and is essential for the well being of the
battery. If omitted, the battery would eventually lose the ability to accept a full charge. Full charge
is attained after the voltage has reached the threshold and the current has dropped to 3% of the
rated current or has leveled off. The final Stage 3 is the float charge, which compensates for the
self-discharge.
Voltage Regulation
In order to regulate the battery voltage up to the end to confine variations within reasonable limits
some means to regulate the battery voltage is necessary. And in our design, we chose diode voltage
regulation control system. The dc consumers of the power plant must be supplied at some constant
voltage. But the voltage of the battery varies over a considerable range. So, this method is chosen
in order to regulate the output voltage of the battery.
Diode Voltage regulation (DVR) Control system
In our design of Battery Bank system, we chose Diode Voltage regulation control system to
regulate the dc voltage system What actually happens in this regulating control system is that the
charger is connect parallel to the battery bank which passes through the diodes to the dc bus. These
diodes can be bypassed or stay in the circuit by the help of the contactor. Talking about the normal
condition the output of the battery voltage is higher than the required dc auxiliary system voltage.
So we need the diode bank in our circuit in order to drop the amount of voltage in it and that
happens through opening of the contactor and the voltage regulation is acquired. In emergency
condition where we cannot expect the charger supply then obviously the battery voltage reduces
on supplying to the emergency loads. Here we bypass the battery banks one after another so that
the dc auxiliary system voltage remains within the permissible range.
In order to find the fault current at dc bus and feeder circuits the battery short circuit current value
is important. This calculated short circuit current is for dc battery bank at its end terminals.
For typical voltage per cell (VPC) of 2.0v let us assume the internal resistance is 0.00018 Ω. Short
circuit current per cell=2.0/0.00018 = 11.1 kA
In our design we have chosen 66 cells and let us assume the interconnection cables for the battery
is 0.010 Ω
The charger output current during charging of battery and supplying the normal load is 120A dc.
Hence, the maximum value of short circuit due the battery charger is limited by the current limiting
circuit of the charger to 1.5 times
=1.5*120A
=180A
The designer should always design for the worst condition. And the worst short circuit occurs in
the dc auxiliary system is when the sectionalized bus connected by the bus coupler when one of
the chargers become faulty. In this case maximum current flows from the charger and the batteries.
And this is called combined short circuit from battery and the charger at dc bus.
For a typical dc system, the short-circuit current from the charger has already peaked and decayed
before the short-circuit current from the battery reaches its peak. Due to this battery time constant,
the maximum coincident short-circuit current can be conservatively calculated as the sum of the
peak short-circuit current from the battery and the current-limit value from the charger.
In case of our power plant two battery banks of operate independent of one another during normal
condition. However, if a charger fails then both the dc bus is connected by the bus coupler breaker.
Hence, the maximum fault current flows during the interconnection of two buses.
The maximum combined fault current at the dc bus due to charger and two battery banks is (DC
Bus Fault):
(Healthy Charger)
= 12244 A
.
Lab-6
Protection Schemes
In modern power system to have a normal operation of the system without electrical failure and
damage to the equipment two alternatives are available with the designer, one is to design a system
so that faults cannot occur and the other is to accept the possibility of the faults and take steps to
guard against the ill effects of such faults. Although it is possible to eliminate faults to a large
extent by careful system design, careful insulation coordination, proper operation and
maintenance, it is obviously not possibility of faults must be accepted and the necessity of
protection scheme must be realized.
a. Generator protection
b. Transformer protection
c. Line protection
1. Generator protection:
Thermal overloading
Over voltage
Mechanical damage
Turbine protection
The protection scheme applied for generator in our design is differential protection scheme. The
differential protection scheme is the most commonly employed scheme. This protective scheme is
very effective for earth faults and faults between phases.
2. Transformer protection:
Power transformers are static devices, totally enclosed and usually oil immersed, and therefore,
chances of fault occurrence on them are very rare. But the consequences of even a rare fault may
be very serious unless transformer is quickly disconnected from the system. Hence automatic
protection of transformers against possible faults (usually dangerous overloads and excessive
temperature rise) is essential and of utmost importance.
The protection system employed for protection of transformer against internal fault is Buchholz
protection. Buchholz protection employing Buchholz relay is the simplest form of protection and
is most commonly used on all oil-immersed transformers provided with conservator.
For protection of transformer from external fault differential protection scheme is employed.
3. Transmission line protection:
The possibility of fault on the overhead transmission line is much more due to greater lengths and
exposure to the atmospheric conditions. Among several protection systems Time graded
overcurrent protection is employed in our design.
CONTROL AND SCADA SYSTEM
SCADA is a system developed to control and monitor power system collecting information from
various parts of the substation and transmitting them to a control operator where the received
information is displayed and corrective action scan be made automatically.