RIGGING PLAN “CHRANE”

Subject : Lifting 20 ft -500 KVA Genset Containerized-


Equipment Used : Crane 55 T
Efficiency Condition : 100%
Length of Boom : 22.7 m
Height of Lifting :6m
Angle boom : 54◦
Working Radius : 12 m
Safe Work Load : 9.7 ton
Weight of Load : 6000 kg
Weight of Main Hook : 450 kg
Weight of Lifting gear : 40 kg
Safety Factor : (3490/17300) x 100% = 66.90 % < 80% (safe)
Lifting Gears : four leg sling 18 T, 4 ea – 10 T webbing sling
Lifting Gears No. :
Rigging Type : Vertical
Safety Equipment : 4 ea Tag Line 5 m
Safety Device : Anti Two Block, Main Host, Aux Hoist, Hook Block, Level Indicator, Load Indicator
Personnel In charges : 1 FOREMAN 
1 Crane Operator (SIO MIGAS) 
1 Signal Man (Certificate MIGAS) 
1 Rigger 
1 HSE 

REMARKS
DESCRIPTION BY SIGNATURE

PREPARED BY

RESPONSIBLE
PERSON

CHECK
/REVIEWED BY

APPROVED BY

Notes : - Pastikan no hand on load


- Pastikan ikuti Lifting Plan
- Pastikan hanya crew Lifting yang bekerja saat proses pengangkatan
- Pastikan semua crew Lifting mengerti apa yang di kerjakan
- Jaga komunikasi dengan baik antar setiap crew saat melakukan pengangkatan
- Stop pekerjaan bila melihat ada indikasi hal yg berbahaya,lakukan evaluasi kembali
sebelum melanjutkan pekerjaan tersebut.
-Jaga posisi tubuh di area yg aman (Line of hire) di saat pengangkatan.