Professional Documents
Culture Documents
Innovative Tower Crane Foundation Designs by K A T L Kodikara
Innovative Tower Crane Foundation Designs by K A T L Kodikara
net/publication/307562928
CITATIONS READS
0 5,100
1 author:
Tharindu Kodikara
Queensland University of Technology
8 PUBLICATIONS 16 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
Model updating of real structures with ambient vibration data View project
All content following this page was uploaded by Tharindu Kodikara on 02 September 2016.
Abstract
In large scale construction projects, especially in high rise structures, tower cranes need to be installed for material
handling purposes. To withstand the loads transferred from the tower crane to ground it requires a good sub-
structure/foundation. A tower crane is of temporary use during the construction stage. The amount that should be spent
on the tower crane foundation is a direct cost of the project. So challenges for the design engineers in the construction
sector are that the foundations should be economical and, require quick designs; they also need to adapt to several
space restrictions and should convince consultants and/or clients to give approval prior to commencement of work.
Depending on the soil conditions present at site the foundations can be either shallow or deep. There is an opportunity
for innovative economical designs with the use of the building structure since it will reduce the cost of the project. This
paper is intended to cover the structural design aspects of some innovative tower crane foundations. General loadings
for the tower crane foundations are operational loads derived from respective tower crane manuals and the wind loads
derived from relevant codes of practice. Because of the complexity of the loading arrangements and analysis cases
finite element (FE) software packages are used for the structural analysis of tower crane foundations. Several analysis
cases to be considered during FE modeling depending on the height of operation, tie levels to the structure and wind
force directions. During the structural design stage the results obtained for the critical loading combinations are used
to design the structures according to relevant codes of practice. Structural detailing is very important, especially the tie
connections to the structure, because the detailing will govern the types and magnitude of forces transferred to the
building structure.
travelling over adjacent premises and that should also be
considered during design stage.
2. Design Methodology
The design cycle of tower crane foundation can be
divided into three main categories namely inputs,
activities and output. The following table illustrates the
description of the categories.
Table 1: Typical design cycle of tower crane foundations
Inputs Activities Output
Site plans, Load Structural
Architectural/Structural evaluation design reports
Drawings
Soil investigation Structural
report analysis
Supplier’s catalogues Design Validation
calculations from
consultant/
Previous design Review with
client Figure 2: Tower crane foundation using building piles
calculations design &
const. teams connected through ground beams
2.2 Load evaluation
2.1 Considering alternatives
The tower crane foundation can be either shallow or There are two main loading patterns that should be
deep depending on the soil condition at site. taken into consideration when designing tower crane
foundations. Namely operational loads derived from
Normally when the soil condition at site is healthy,
shallow foundations are used and normally it will be a raft tower crane manuals and wind loads derived from codes
foundation. When the bearing capacity of the soil is high, of practices.
Operational load will vary with the tower crane height,
in order to make the foundations more economical, the
volume of the raft is reduced by sizing the foundation. tie level to the building(s), jib position, maximum lifting
weight etc. It is important to remember that when the
Length and breadth will be provided only to satisfy
operational loads are derived from respective operational
bearing capacity of soil and to connect the four tower
crane legs. The depth of the foundation is provided only manuals, the forces are given to free standing height.
Whenever the tower crane is tied to building the free
to satisfy bending moment and shear (vertical line shear,
punching shear). Additional weight required to satisfy the standing height is the height above the top most tie level.
uplifting force generated by operational bending moment For wind loads the general practice in Sri Lanka is to use
wind codes CP3 Chapter V: Part 2: 1972 [1], BS 6399
of tower crane and wind force are provided by precast re
usable concrete blocks placed on top of the raft Part 2 [2] and the manual on Design of buildings for high
foundation, in order to make the concrete volume and winds in Sri Lanka [3].
steel tonnage in the foundations as low as possible. 2.3 Structural analysis of the tower crane
When the soil condition is poor, initially the possibility Structural idealization is very important in the design of
of soil improvement should be considered. But if the soil tower crane foundations. In order to obtain the correct
condition is very poor then it is essential to go for deep loading to the tower crane it is essential to idealize the
foundations. Since the construction cost of tower crane structure accurately. Due to complexity of the structural
foundation cannot be claimed, if new piles and a separate analysis it is normal practice to use finite element
structure is resorted to, it will be a huge cost overrun to software packages for 3 dimensional analysis - e.g.
the contractor. SAP2000 [4].
So it is the designer’s responsibility to design the There are number of cases to be modeled depending on
foundation with the use of building piles as much as the tower crane height of operation and the number of
possible and get the approval from consultant/client prior levels the tower crane is tied to the building. For the
to commencing the work. When building piles are used, foundation design, normally the critical condition is the
the piles are connected through ground tie beams and free standing operation of the tower crane, since all the
tower crane legs are fixed on to those ground tie beams. bending and torsional moments are directly transferred to
Also it is very important to consider the loading of the the foundation. When the tower crane is tied to the
building piles during construction stage when building building, the loads transferred to bracing are more critical
piles are used for the tower crane foundation. The than loads transferred to foundation.
combined load transferred from tower crane and building A number of cases need to be modeled in order to find
during construction stage should be less than the design out the most efficient tie levels to the building so that the
capacity of the pile. loads transferred to the building are kept to a minimum.
Normally this procedure is carried out on a trial and error 2.4 Load combinations used in the structural analysis
basis.
Load combinations are chosen as per the relevant codes
of practice. As per BS 8110: Part 1:1997 [5] the following
load combinations are considered as usually practice in
Sri Lanka.
Com. 1 : 1.0 Dead + 1.0 Sdead + 1.0 Live
Com. 2 : 1.4 Dead + 1.4 Sdead + 1.6 Live
Com. 3 : 1.2 Dead + 1.2 Sdead + 1.2 Live + 1.2 Wind X
Com. 4 : 1.2 Dead + 1.2 Sdead + 1.2 Live + 1.2 Wind Y
Com. 5 : 1.0 Dead + + 1.0 Sdead + 1.4 Wind X
Com. 6 : 1.0 Dead + + 1.0 Sdead + 1.4 Wind Y
Envelope : Envelope of all Combinations
Figure 3: An example of analysis cases with different tie The dead weight of the Tower Crane (Dead) includes the
levels to the building self weight of the tower crane (with jib). Super imposed
Ties to the building are modeled as pinned connections dead weight (Sdead) includes the counter balance weight
because it is unfavorable to transfer the bending and plus maximum lifting weight. Operational live bending
torsional moments to the building. Also, in general moment (Live) includes the bending moment on tower
practice the consultant/client will not allow the use of crane (obtained from the manual). Wind load - (Wind X)
fixed/ moment connections to the building. includes the wind force perpendicular to the jib and Wind
load - (Wind Y) includes the wind force acting parallel to
the jib.
In order to get at the most critical load combination, the
envelope of the all possible load combinations is
considered and structural design is carried out for the
worst case scenario.
2.5 Structural design
Structural design is carried out based on the resultant
forces obtained from the 3 dimensional finite element
model analysis.
For the design of substructure in Sri Lanka BS 8110:
Part 1:1997 [5] is used. The tower crane bracing to the
building is with steel universal beams and/or L angles.
Therefore for the steel design BS 5950: Part 1: 2000 [6] is
Figure 4: Typical 3 D model (SAP2000) with pinned used.
connections to the building It is very important to check the connection of tower
crane leg to the substructure for the possible up-lifting
When loads assigning to the tower crane model should due to wind load and operational bending moments
be carefully consider all the possible arrangements of jib generated through tower crane operation and to provide
positions (parallel to the building, perpendicular to the adequate anchorage length for tower crane leg into the
building, diagonal to building) and for each and every jib foundation.
position there are two wind loading conditions namely
wind parallel to the jib and wind perpendicular to the jib. 2.6 Typical connection details
There are two critical connections associated with
tower cranes. Namely connection of tower crane legs to
the foundation and tower crane ties to the building.
Connection of tower crane legs to the foundation is
normally done by embedding the tower crane leg into the
foundation by providing adequate anchorage lengths for
compression and tension. In order to enhance the
connection, tor steel bars are welded to tower crane legs
(fish tails).
The tower crane tie to the building is normally detailed
as pin connected, to ensure that no moment is transferred
to the building. Also, it is essential to allow the tower
crane to rotate freely through its own vertical axis in high
wind situations to ensure the safety of the tower crane.
The main objective of all the innovative designs for 4. Concluding Discussion
tower crane foundations will be to provide structurally
feasible solutions with a saving in monetary terms As there is no end for the innovations in any field, there
compared to conventional solutions. Two examples of is always space for further developments in the innovative
such innovative designs are briefly outlined below. designs of tower crane foundations. One aspect we have
already looked into is pre-cast foundations that can be
3.1 Examples for savings in innovative tower crane dismantled after the completion of the project and re-used
foundation designs in future projects. This idea is already implemented at
The Secretariat for Personnel Identification (SPI) at design stage but not yet implemented in a project.
Battaramulla is a 22 storied building and requires two It is very important to research for innovative methods
tower cranes with a maximum height of operation of of tower crane foundation designs and to keep the
100m. According to the soil investigation reports the soil discussion open, so that everyone is benefited in the
condition at the site is very poor and clearly not industry by saving money and sharing knowledge.
recommended for a shallow foundation design. Since the
weak soil layers are present at even 20m below existing
ground level, soil improvement is also not possible. So
there is no other option other than deep foundations. For References
the stability of a tower crane, a minimum of three piles is [1] CP3 Chapter V: Part 2: 1972. Code of practice for wind loading,
required. Rather than employing three new piles, two British Standards Institution, London.
building piles were used and only one new pile was cast [2] BS 6399 Part 2. Loading for buildings: Code of practice for wind
and connected through ground beams. loads, British Standards Institution, London.
[3] Design of buildings for high winds in Sri Lanka, Ministry of Local
Government, Housing and Construction, Colombo, 1980.
[4] SAP 2000 – Integrated finite element analysis and design of
structures, Computers and Structures, Inc, Berekeley, 1998.
[5] BS 8110: Part 1: 1997. Structural use of concrete, British Standards
Institution, London.
[6] BS 5950: Part 1: 2000. The structural use of steelwork in buildings,
British Standards Institution, London.