Project Title : Modification New Pipe for Sprinkle

Project Location : PT. AKR Corporation Tbk


Work Location : Semarang - Jawa Timur
Author Org. :
Period of Work : 10 April 2021
SEISO
HSSE KPI's

Input Prev Today Cum Input Prev Today

PTW 30 1 31 Incident / Accident 0 0


Toolbox Talk 30 1 31
Safety Induction 2 0 2 Man Hours Record 1680 56

Current Status
A BUNDWALL CHEMICAL

1 Repainting new pipe Repainting new pipe 3 inch (posisi support Type 7)

Pasang pondasi support Type 5, dengan komposisi pasir,


2 Instal pondasi support
semen, dan coral

Hydrotest dengan perlengkapan pompa dan barton,


3 Hydrotest dengan pressure awal 7 - 8 bar

HSSE

Overall Progress Gas Freeing


Plan (%) Actual (%) Variance (%)
8.00% 8.00% 0.00%

Form No.: Issue: A Rev.: 0 Dated: 10 April 2021


Photo

DOKUMENT AK
Document Title : DAILY PROGRESS REPORT
Document No : 211503-SEISO-PRJ-RPT-001
Prepared by : Naufar Wildan Gresika
Reviewed by : Fahrizal Ricky
SEISO INDONESIA Page : 1 of 1
PERSONNEL ON BOARD WEATHER

Cum No Company Name POB Man Hours

0 1 SEISO 7 56 ✘

1736
TOTAL 7 56

Forward Plan (Tomorrow Activity) 13-Mar-21


A BUNDWALL CHEMICAL

1 Repainting new pipe Repainting new pipe 3 inch dan support Type 5

Pasang pondasi support Type 7, dengan komposisi pasir,


2 Instal pondasi support
semen, dan coral
Hydrotest dengan perlengkapan pompa dan barton,
3 Hydrotest dengan pressure awal 7 - 8 bar

Area of concern