DD-101 Rotary Calciner Kiln

Material of 316-stainless
construction steel

S,volume (m3) 27.52

Weight of Reactor
170,548.50
(lbm)

Diameter (ft) 6.56

Orientation Horizontal
Table 1: Design data used for equipment cost calculation.

A. Correlation Method [1]

C e =a+b Sn
Where;
Ce=purchased equipment cost on a U.S. Gulf Coast basis, Jan. 2010
a,b=cost constant
S=size parameter
n=exponent for type of equipment

Figure 1: Data taken for equipment cost evaluation for DD-101 (HIGHLIGHTED IN YELLOW).
Figure 2: Data for material cost factor,Fm.

Since the material cost factor for stainless steel 304 and stainless steel 306 are same (1.3), thus the material factor will
not be included in our calculation.

C e =a+b Sn

C e =61,500+32,500 ∗27.520.8

C e =522,446.03USD

C e =522,446.03USD

The cost of equipment obtained were based on CEPCI, January 2010 (CEPCI=532.90). Cost index was used to evaluate
cost of equipment at 2020 (CEPCI=596.20).

C p=Base Cost (II )


base

C p=522,446.03 ( 596.20
532.90 )

C p=584,504.26 USD

C p=2,419,847.64 MYR
B. Graphical/Equation Method [2]

The equipment cost calculation using equation method was evaluated using equation below:

C p=F M CV +C PL
Where;
FM= material cost factor
CV=empty vessel factor
CPL=cost of platforms and ladders

Figure 3: Data for material cost factor,Fm.

Since the reactor in horizontally orientated, thus the formula below was used to evaluate the C V;

Horizontal Vessels for 1,000<W < 920,000lb :


2
{ 8.717 −0.2330 [ ln(W ) ] +0.04333 [ ln(W )] }
C V =e
2
{ 8.717 −0.2330 [ ln(170,548.50)] +0.04333 [ ln(170,548.50)] }
C V =e
C V =198,463.10 USD

The cost of platform and ladders were evaluated using equation below;

Horizontal Vessels for 3< D i <12 ft :

C PL =1,580 ( D i )0.20294

C PL =1,580 ( 6.56 )0.20294

C PL =2,314.53USD

C p=F M CV +C PL
C p=( 2.1)(198,463.10)+2,314.53

C P =419,087.04 USD

The cost of equipment obtained were based on CEPCI, January 2000 (CEPCI=394.00). Cost index was used to evaluate
cost of equipment at 2020 (CEPCI=596.20).

C p=Base Cost (II )


base

C P =419,087.04 ( 596.20
394.00 )

C P =634,161.66USD

C P =2,625,429.26 MYR

C. Aspen Plus Simulation

Figure 4: Figure above shows flowsheet for DD-101 simulation in Aspen Plus.

Figure 5: Figure above shows the equipment cost evaluation from Aspen Plus.

C P =401,500 USD

C P =1,662,210.00 MYR
(CALCINER-DD 101)
Method Correlation Graphical Aspen
2,419,847.6
Cost(MYR)
4 2,625,429.26 1,662,210.00

Table 2: Comparison for equipment cost evaluation using correlation, graphical and aspen plus.
References

1. Sinnott, P. T. G. R. K. (2021). Chemical Engineering Design, Second Edition: Principles, Practice and Economics of

Plant and Process Design by Gavin Towler Ph.D. R K Sinnott(2012–01-27). Butterworth-Heinemann.

2. Seider, W. D. (2021). Product And Process Design Principles: Synthesis, Analysis And Evaluation, 2Nd Ed (2nd ed.).

WSE.