Appendix I

Flowchart Showing the Application Procedures for a DG Licence

Applicant submits Application with plans

(14 working days)

Conducts on-site inspection to formulate


fire safety requirements

Reject the Submitted


No details/plans
Application
acceptable?
with Reasons

(14 working days)


Yes

Issue of Fire Safety Requirements and return


Forward the case to Ventilation
one set of endorsed plans to applicant
Division (VD) if Mechanical
Ventilation System/Electrical
Installation within hazardous zone is
provided

Report of Compliance to VD

Report of Compliance to DGD


(16 or 21 working days)
Conduct Compliance
Inspection
Rectify (7 working days) Rectify
Outstanding Item Outstanding Item

Conduct Compliance Inspection


Full No
Compliance?

No Yes
(6 working days)
Full
Compliance?
Issue of Letter of
Compliance

Yes
(6 working days)

Issue of Licence