You are on page 1of 5

Nama : Michael Ari Sulistia P

Nim : B11.2019.05626
Matkul : Pratikum Manajemen Operasional ( B11.4.5 )

SOAL

Jawaban :
• TABEL
Optimistic Most Pessimistic Predecessor Predecessor Predecessor Predecessor Predecessor Predecessor Predecessor
Activity
time Likely time 1 2 3 4 5 6 7
A 3 6 15
B 2 4 14
C 6 12 30 A
D 2 5 8 A
E 5 11 17 C
F 3 6 15 D
G 3 9 27 B
H 1 4 7 E F
I 4 19 28 G H
• Tabel Project Management ( PERT/CPM ) Result

Activity Activity Early Standard


Early Finish Late Start Late Finish Slack
time Start Deviation

Project 54 6.4
A 7 0 7 0 7 0 2
B 5.33 0 5.33 19.67 25 19.67 2
C 14 7 21 7 21 0 4
D 5 7 12 20 25 13 1
E 11 21 32 21 32 0 2
F 7 12 19 25 32 13 2
G 11 5.33 16.33 25 36 19.67 4
H 4 32 36 32 36 0 1
I 18 36 54 36 54 0 4

• Tabel Activity Time Computations

Most
Optimistic Pessimistic Activity Standard
Likely Variance
time time time Deviation
time
A 3 6 15 7 2 4
B 2 4 14 5.33 2 4
C 6 12 30 14 4 16
D 2 5 8 5 1 1
E 5 11 17 11 2 4
F 3 6 15 7 2 4
G 3 9 27 11 4 16
H 1 4 7 4 1 1
I 4 19 28 18 4 16
Project results
Sum of crit act var 41
Square root of total 6.4
CHARTS

You might also like