General Rules:
1 Operation flow is as per serial no. of operations. That is operation 1 feeds Operation 2, operation 2 feeds operation 3 and so on.
2 Enough hours must be worked on each operation to give the target output in this case 1000pcs/Day.
3 Any operator should work for minimum ½ hour at any allocated operation, i.e. in a two-hour slot any operator can work for maximum 4 different operations.
4 You may allocate floaters to cover for absenteeism and/or WIP/production balancing. (i.e. allocate floater as and when required)
5 Machine/attachment used in different operations is different.
6 All production and WIP should be written in round figure (no decimal)
7 Maximum three machines are available for each operation
8 Opening WIP between operations are 100. Negative WIP figure to be avoided, any negative WIP figure will disqualify the team
9 Try to maintain maximum WIP of total 400-600 pieces in line.
10 When any operator is unavailable, his/her machine can be utilised by other operator. During any m/c breakdown operator can move to other operation or m/c to work.
11 Use operators or floaters on operations they can do best, i.e. try to get maximise time on standard (by using operators/floaters on operations where they work on incenti
12 Any operator can work for maximum 2 hours in any two hours slot. If your allocation exceeds 2 hours, red colour alert will be shown against that operator. Please avoid
This module was developed as a part of APPC subject for B.F.Tech and GMP subject for M.F.Tech students of NIFT. This remains a intellectual property of NIFT,
Department of Fashion Technology and any unauthorized copy is strictly prohibited.
to teacher.
e the exercise.
This module was developed as a part of APPC subject for B.F.Tech and GMP subject for M.F.Tech students of NIFT. This remains a intellectual property
of NIFT, Department of Fashion Technology and any unauthorized copy is strictly prohibited.
This module was developed as a part of APPC subject for B.F.Tech and GMP subject for M.F.Tech students of NIFT. This remains a intellectual property of NIFT, Departmen
unauthorized copy is strictly prohibited.
14:30 - 16:30
Operator Hrs Prod WIP
Devi 1.5
### 72
Gita 1.5
### 72
Ramar ###
0 0 118
Gita 0.5
### 56
Sangita ###
1 150
### 0 124
Ramesh ###
1 186
### 0
### 0 60
Sangita ###
1 61
Kalindi ###
2 163
### 0 13
Sunil ###
2 112
Ramar ###
2 84
Ramesh ###
1 31 12
Urvashi ###
2 240
### 0
### 0
Line Efficiency Operator Utilisation
92% 88%
re
Garment Manufacturing Process / Apparel Production Planning and Control
This module was developed as a part of APPC subject for B.F.Tech and GMP subject for M.F.Tech students of NIFT. This remains a intellectual property of NIFT, Department
unauthorized copy is strictly prohibited.
14:30 - 16:30
Operator Hrs Prod WIP
Gita ###
2 95
Ramar ###
2 117
Devi ###
2 95 134
---N/A--- ###
0 0
Sangita ###
2 300
---N/A--- ### 0 121
Ramesh ###
1 186
Floater 0.5
### 62
### 0 126
Kalindi 0.5
### 41
---N/A--- ###
0 0
Bhanu ###
2 204 139
Sunil ###
2 112
Kalindi 1.5
### 105
Ramesh ###
1 31 79
Urvashi ###
1 120
Floater ###
1 135
### 0
Line Efficiency Operator Utilisation
82% 92%
Student's Name:
_________________________________
This module was developed as a part of APPC subject for B.F.Tech and GMP subject for M.F.Tech students of NIFT. This remains a intellectual property of NIFT, D
Fashion Technology and any unauthorized copy is strictly prohibited.
New Delhi Kolkata Hyderabad Chennai Mumbai Gandhinagar Bangalore