You are on page 1of 25

School of Engineering

Design of Beam – Column Moment


Connections

Prof Dennis Lam


University of Bradford, UK
School of Engineering

Types of Beam – Column Moment Connections

• Bolted connections
• Welded connections
– Site welding
School of Engineering

Factors Influencing the Use of Site Welding


Disadvantages:
• Access and welding position may be restricted owing to lack of
manipulation and hoisting facilities on site. Manual manipulation of
small sub-assemblies may still be possible alongside the main
structure but this work can be done in the works, in any case.
• With thick walled sections the cooling rate of welds will be high. This
can be offset by using preheat but with particularly heavy sections
the cost of heating can be excessive. Thin sections (e.g. as in hollow
section structures) present no difficulty in this respect and are more
readily welded on site.
• In adverse climates e.g. frost or high wind, localized shelter and
preheat are essential and yet may be difficult to provide.
School of Engineering

Factors Influencing the Use of Site Welding


Disadvantages (cont’d):
• Misalignment or bad fit-up may waste considerable time. Temporary
devices and attachments are sometimes used to pull components into
correct alignment. Welding distortion may further aggravate the problem.
Normal site facilities are inadequate for dealing with major distortion
problems.
• Subsequent adjustment or dismantling is difficult with wholly-welded
construction.
• Inspection and testing is often inconvenient on site and remedial work
comes at an inopportune time, possibly affecting general progress.
School of Engineering

Factors Influencing the Use of Site Welding


Advantages:
• Occasionally, it is physically impossible to develop the required
strength in a bolted joint.
• Bolted joints reduce the effective cross-sectional areas in tie
members, tension flanges, etc.
• Numbers of bolt require for the joints may not be possible due to
access and clearance.

• Site welding may prove economical where there is a sufficient


quantity of repetitive work to justify a transfer of special plant and
equipment to site.
School of Engineering
School of Engineering
School of Engineering

b b

c tw b−c
m= − − 0 .8 r emin = n = emin , ≤ 1.25m
2 2 2
School of Engineering
School of Engineering
School of Engineering
School of Engineering

Equivalent T-stubs, Leff for Bolt Row


School of Engineering

Moment Capacity, Mp

Leff × t
2 fy
Mp = ×
4 γ M0
School of Engineering

Web Tension in Beam or Column


Ft = Lt × tw × fy / γM0
School of Engineering

Design Assumptions
• Beam end plate is at least as strong as the
column flange
• For extended end plate connection, the
two top rows can be taken as acting
together as a group with the combined
potential resistance shared equally
between rows 1 & 2.
• Each lower row is then based on a T-stub
length of vertical pitch ‘p’
School of Engineering

Design Assumptions (cont’d)


• They are checked to ensure to be within
the triangular limit.
• For flash end plate connection, the top
row is taken to act in isolation (pattern i or
ii).
• Each lower row is then based on a T-stub
length of vertical pitch ‘p’
School of Engineering

Extended end plate connection

Leff = 4m +1.25e+ p
School of Engineering

Flash end plate connection

Leff = 4m +1.25e
School of Engineering

Design Example

You might also like