You are on page 1of 14

sign, and improved manufacturing tech- manyfold in its 70 years of existence.

existence. To- are as great as or greater than ever before,


niques have resulted in lower costs and day 80,000,000 kw, 500 watts per capita, and the rewards to the industry will fully
lower weight and volume of material per of capacity are installed. In the next 10 justify the risks.
kilovolt-ampere of rating. In turn, years, it is very likely that this figure will
higher-rated generators and power plants be doubled. Energy generated today References
have resulted in more economic produc- amounts to about 2,500 kilowatt-hours
tion of power. Water-wheel generators 1. ELECTRICAL TRANSMISSION AND DISTRIBUTION
per capita per year, and continues to grow REFERENCE BOOK (book), Westinghouse Electric
may be expected to deliver one-fourth to at a rate of doubling in 10 years. Corporation, East Pittsburgh, Pa., fourth edition,
September 1950.
one-half more kilowatts without increas- Certainly the art of power generation
2. THE ELECTRIC POWER INDUSTRY, PAST,
ing size or weight. Turbine generators has reached no ultimate peak, and the PRESENT AND FUTURE. Electrical World (New
will probably exceed 300,000 kw at 3,600 industry can look forward to advances not York, N. Y.), volume 131, May 21, 1949.
rpm. yet produced by the minds of men. The 3. MID-CENTURY REVIEW AND FORECAST OF
WESTINGHOUSE ENGINEERING. Westinghouse Engi-
The electric-power industry has grown money and effort for further development neer (Pittsburgh, Pa.), volume 10, January 1950.

Discussion of supplying the load, after providing for


necessary scheduled and routine mainte-
providing it. As a matter of fact, the instal-
lation of capacity should be planned and
nance and for reasonable protection against justified on the basis of a measured risk so
C. W. Watchorn (Pennsylvania Water and the contingencies of forced outages and that at rare occasions the load may be as
Power Company, Baltimore, Md.): The greater than expected loads. From the much or more than the then available
statement in the section entitled "Energy planning standpoint, reserve generally is generating capacity.
Requirements" that "The total installed expressed as the excess of the planned ca-
generating capacity as indicated in Figure 4 pacity over the expected load. Variations
is required to supply peak loads throughout in the actual loads as compared with those A. C. Monteith and A. A. Johnson: The
the country with some margin for reserve" expected (which are usually estimated 2 to matter of margin for reserve in generating
is undoubtedly correct in the sense intended 4 years in advance) result in variations of capacity is a question which must be de-
by the authors; however, unfortunately this considerable magnitude in the actual re- cided by each individual operating group,
simple expression frequently is misunder- serve as compared with that used as a basis and over-all by each group of organizations
stood. for planning. The reduced reserves that in a given area. The point concerning defi-
Too often it appears that the provision of may exist when the actual loads turn out to nition of margin or the meaning of excess
reserve, simply to provide a margin over be larger than those estimated serve as an capacity over peak load, as discussed by Mr.
load, is overstressed. As a matter of fact, illustration of the use of the planned reserve Watchorn, is well taken. It was not the
generating capacity is installed only to carry for the purposes for which it is provided. intention of this paper, however, in any
load; whether or not the reserve is there in Such condition is not per se an indication way, to determine or state what this margin
any specified a mount or percentage is imma- of insufficient capacity having been pro- should be or how it is determined. Certainly
terial so long as the load is supplied. vided since, if the planned reserve were not allowances must be made for routine main-
Capacity should be provided in such used, at least from time to time, there cer- tenance of equipment and for forced outages
amount as to result in reasonable assurance tainly would be very little justification in of equipment.

a 13-mile line was built, and transmission


Progress and Future Trends in Electric "recommended" above a kv. Two years
later 10 kv was considered "available,"
and 15 to 20 kv "possible." A notable oc-
Transmission currence at that time was the start of a
plant transmitting at 2.5 kv over a dis-
tance of 41/2 miles.
S. B. CRARY 1. W. GROSS C. F. WAGNER In 1896 the record shows the following:
FELLOW AIEE FELLOW AIEE FELLOW AIEE

Transmission
THE transmission lines are most im- high-voltage transmission above that Voltage D-C 1 Phase 2 Phase 3 Phase
portant links in the electric power range to 230 kv, and extra-high voltage
supply system. This was recognized from above this value. Going back some 60 Volts ........... 8,000...3,000... 5,500-...11,000
Distance, miles.. 12 ... 3... 8... 35
the early days of electric power, and has years it is found that voltages now in the Horsepower I, 000... 400... 200... 1 400
become increasingly important as the use distribution range were being spoken of as
of electricity has expanded until today it transmission. In 1892, 4 kv was just All these systems were reported to operate
is part and parcel of our everyday life. starting as a "transmission" voltage, and successfully.
This presentation deals largely with the Two years later one critical stumbling
progress and development in the electric Paper 52-255, recommended by the AIEE Power block to higher voltage transmission was
Generation Committee and approved by the AIEE
transmission field. It also includes a brief Technical Program Committee fpr presentation at reported to be the insulators.
the Centennial of Engineering-1952, Chicago, Ill.,
history of the art, and a discussion of the September 10 12, 1952. Manuscript submitted With the start of the century transmis-
present status and future trends. June 12, 1952; made available for printing July 23, sion-line voltages increased progressivelv
1952.
At present, "transmission" usually is from 22 kv through 40, 60, 80, 100, to 150
S. B. CRARY is with the General Electric Company,
thought of as lines of about 23 kv or Schenectady, N. Y., I. W. GROSS is with the Ameri- until around 1920 when 220 kv was con-
above, these comprising what might be can Gas and Electric Service Corporation, New
York, N. Y., and C. F. WAGNER is with the West-
sidered an engineering possibility and
called subtransmission up to about 69 kv, inghouse Electric Corporation, East Pittsburgh, Pa. lines of this voltage came into existence

OCTOBER 1 952 Crary, Gross, Wagner Progress in Electric Transmission 963


Figure 1. High- for lines and for equipment. Lines with
est transmission- their direct exposures, when no provisions
line voltages are taken to protect them, under average
I-0J
300
conditions can have flashovers of the in-
sulators of about 100 per 100 miles of line
0
-J per year. With adequate lightning pro-
200
tection, this can be reduced to a few per
- _ _ _ _ _ _

cent.
For transmission lines, this protection
usually takes the form of overhead con-
ductors that are grounded at each tower.
In the early days the ground wires were
85 90 1900 10 20 30 40 50 60 located to give optimum coupling on the
YEAR
theory that induced strokes was the phe-
nomenon to be guarded against. By 1930,1
shortly thereafter; see Figure 1. Today is shown in Table I. however, the direct stroke theorv was pro-
the highest voltage transmission in this From a recent survey1 it is seen that the posed. The data accumulated since then
country is 288 kv which has been in serv- circuit miles are increasing at a rate of have confirmed this theory. Ground
ice over 15 years. There is now being about 30,000 per year. About 50 per cent wires now are located above the conduc-
built in this country and Canada 330 to ofthe circuit miles are in the voltage classi- tors, preferably with a shielding angle of
345-kv, and in Europe 380 to 400-kv fication above 66 kv and the other half 11 about 30 degrees, although quite satisfac-
transmission. kv to 66 kv. Also, these same surveys in- tory service can be obtained at the sacri-
Initially small plants were built to sup- dicate that there is an increasing percent- fice of additional direct strokes to the con-
ply local requirements for lighting and age of higher voltage as compared with ductor if an angle as large as 45 degrees is
gradually were increased in size to supply lower voltage transmission. The growth used.
power. The increasing demand for power of transmission systems, as indicated by It is not sufficient that the stroke
in the early stages required larger amounts the percentage increase in circuit miles, merely be intercepted by the ground wire.
of power to be transmitted longer dis- is at greater rate than the percentage in- The footing resistance of the tower must
tances, and therefore higher voltage for crease in generating capacity. This in- be low. With a high tower footing re-
economical delivery and expansion. dicates a continuing trend to transmit sistance, the entire tower including the
The technical literature in the AIEE larger loads a greater distance. There ground wire is raised in potential above
abounds with engineering papers describ- is every indication that this will continue, ground by the passage of the stroke cur-
ing the thinking, analysis, theory, and ex- particularly with the building of larger rent through the footing resistance. Since
perience of those pioneers who laid the generator stations at a distance from the conductors are parallel to the ground
foundation for the transmission art and their loads. wire, voltage is induced in them by mutual
contributed greatly to rapid and extensive It is also of interest to note from Table coupling. The voltage across the insula-
growth at that time. I that about 93 per cent of the transmis- tor string is equal to the difference in
The practice of 1 kv per mile was stated sion circuit miles below 100 kv use wood- voltage of the ground wire and of the con-
early as a practical and economical rule- pole structures, whereas above 100 kv, 51 ductor. Thus the voltage that causes a
of-thumb figure. While this figure is not per cent use steel structures. Wood poles flashover of the insulator string is propor-
realistic today, transmission throughout are used up to and including 230 kv. tional to 1.0 minus the coupling factor and
the years has followed this general pat- By 1927 the transmission systems al- to the tower top potential. The latter
tern, although in certain cases it has gone ready had been developed quite fully as can be kept low only by means of a low
as high as 3 or four miles per kv. shown in Figure 2. This shows the cir- tower footing resistance.
It is interesting to note that even in the cuits of 60 kv and above in the United Other factors that determine the line
early days of electricity when the growth States at that time. performance are the magnitude and fre-
of the electric power system was first In the natural evolution of power sys- quency of occurrence probabilities of
started, it was recognized and emphasized tems higher circuit voltages are super-
that the economics and reliability of elec- imposed upon the lower voltage existing
tric service always must be kept in the system as the load density and size of Table I. Circuit Miles of Transmission, United
forefront. blocks of power to be transmitted in- States
crease. Figure 3 shows the present 230- 1950 Statistics, References 1 and 2
Physical Growth kv and higher circuits now in use or defi-
nitely projected. Although small in per- Circuit Miles
A-c transmission had its beginning in centage of total circuit miles, the higher Type of Structure
the late 1880's with the invention of the power carrying capability of the higher
voltage circuits make them important Kilovolts Steel Wood Total
transformer. During the past 65 years the
growth has continued until today there elements of the transmission systems.
15.3 to 26.4 299... 25,743 .... 26,042
are nearly 300,000 circuit miles of trans- .0... 41,240
26.5 to 36.5 ...... 1,174 ... 40066
mission in the United States. 36.6 to 47.5. -1,412... .24,953.... 26,365
Lightning Protection 47.6 to 79.9..... 7,975 ... 46,407 .... 54,382
In 19501,2 there were in existence in the 80 to 125 ...... 16,151... 21,777 .... 37,928
126 to 143 ......10,230.... 7,508 .... 17,738
United States nearly 220,000 circuit miles Lightning has been one of the most 144 to 188 2,651.. 3,689.... 6,340
of transmission. The distribution in cir- formidable enemies of power lines and 189 to 253 3,051.... 506 .... 5,557
254 and up 791.... 0.... 791
cuit miles according to voltage classifica- equipment. Protection against its ef-
tion and type of structure (wood or steel) fects has taken entirely different courses Total .. .. 43,734... 170,649 ... 216,383

964 Crary, Gross, Wagner Progress in Electric Transmission OCTOBER 1 952


Figure 2. Location oF transmission lines in
the United States operating at 60 kv and above
in 1927

lightning stroke currents, the span lengths the lightning arrester, but now it is a re- lower insulation is in progress. More and
and, of course, the number of insulators markably reliable and effective piece of more it is becoming the practice to lower
in the string. The over-all effect of these equipment.) Experience has shown light- the insulation level of transformers one
factors is shown in Figure 4 for typical ning arrester failures to be extremely rare level below that in use some 25 years ago.
steel tower lines5 from 69 to 230 kv in- when properly applied, on the order of These are the so-called "reduced level'
clusive, in which the flashovers are plotted one in every 10,000 lightning arrester- values.
as a function of the tower footing resist- years of service. The whole theory of in- The use of protective gaps as a primary
ance. WA'hile practice varies with regard sulation co-ordination and the detenrina- protection in substations is being aban-
to the number of insulators used for any tion of the basic impulse insulation levels doned rapidly. Only with full trans-
particular voltage, the full lines are drawn of equipment are based upon the perform- former insulation and with the gaps set to
'for the average number now in use in this ance of lightning arresters. In the high- such low values that switching surges
country. Similarly, the span lengths also voltage field, most lines are equipped with frequently produce flashovers can the gap
were taken for average conditions. These ground wires either for their entire length afford proper protection to the trans-
curves emphasize the need for low tower or for about 1 mile out from the substa- former. With the American practice of
footing resistance. While in some regions tion. In addition, ground wires fre- using lightning arresters, not only is
the normal tower footing resistances are quently are run over the substation it- better service obtained but, in addition, a
sufficiently low to provide satisfactory self. Thus, for substation protection, the less expensive combination of transformer
service, at others special steps must be lightning arrester is not subject to the full and lightning arrester is obtained. The
taken to lower the resistance. Ground rods magnitude of the lightning stroke current additional cost of the lightning arrester
or counterpoises sometimes are used. which might reach magnitudes of 150,000 is more than paid for by the reduced cost
Ground rods as long as 150 feet or more or 200,000 amperes as extreme limits. of the transformers and better protection
have been driven at some locations. Most of the current is diverted to ground is provided.
Counterpoises usually are buried about 18 by the ground-wire system so that, in con-
inches below the surface of the ground trast, the lightning arresters in stations Symmetrical Components
and may be of the crow foot or the con- rarely are called upon to discharge cur-
tinuous type. To obtain the maximum rents in excess of 5,000 amperes. Prior to 1918 practically all system cal-
benefit from the porcelain insulation, the Since the lightning arrester rating is de- culations were made for balanced 3-phase
clearances from the conductors to the termined by the maximum dynamic volt- conditions. There was no convenient
tower structure must be co-ordinated with age that can appear across its terminals, tool with which to handle unbalanced
the flashover characteristics of the in- solidly grounding the system permits a conditions. It was at this time that Dr.
sulator strings. sufficiently low-rated lightning arrester C. L. Fortescue developed and presented
Equipment protection centers around so that, with the limitation in discharge to the world symmetrical components.6
the lightning arrester. (In the beginning current just noted, a steady increase in the For years, however, it was felt that the
a number of problems were presented by proportion of substation transformers of principal application of symmetrical com-

OCTOBE-R 1 952 Crary, Gross, Wagner Progress in Electric Transmission 965


Figure 3. Location of transmission lines in the United States and Canada operating at 220 kv
N. \and above in 1952
Circuits now in operation
- - - - Circuits deFinitely planned or projected for operation at 220 kv and above

WLATITUDE_ -

C
OIQ~~~~~
TS t ;~ X ) 4>.

0~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

C)
H:\
20 EXAMPLE OF CALCULATED SWING CURVE

4 cn
w
w
i&
CD
w
a
-i
z
a2 1
0
2
w
w
0 (Li
0. 4
s -J

0
a-z
z
(0)
c,)
41
-j 41
U. -j
CD
4

0 20 40 60 80 100
TOWER FOOTING RESISTANCE IN OHMS
Figure 4. Performance of typical well-shielded steel-
tower transmission line from 69 to 230 kv inclu- Figure 5. Example of calculated angular displacement of generators
sive, as a function of tower footing resistance and on a faulted system, showing stable and unstable conditions for
number of 53/4-inch spaced insulators diKferent fault clearing times

ponents would be for the analysis of sequence reactance. Relays that respond In 1937 the Subcommittee on Inter-
machines under unbalanced conditions. to certain combinations of these compo- connection and Stability Factors of the
It was not until 1925 that the value of this nents of voltage or current have been de- AIEE Transmission and Distribution
tool was appreciated as applied to the veloped. The use of the a-c calculating Committee presented "The First Report
calculations of unbalanced faults7'8 on board for system studies is based on the of Power System Stability"9 which sum-
symmetrical systems and as applied to the concept of symmetrical components. marized the development and application
stability problem. Today these latter ap- of stability theory to power system de-
plications are the most important ones System Stability sign. This report includes a table of the
and account for the widespread accept- essential features of several of the major
ance of this method of analysis. Hunting of parallel generators driven high-voltage transmission systems exist-
The great usefulness of symmetrical by reciprocating prime movers was one of ing at that time, with an extensive bibliog-
components in the electric utility field the first types of instability evidenced in raphy. This bibliography has been ex-
arises from the simplification that results power system operation during the period tended to 1946 in reference 10.
when the system itself is balanced and the from 1890 to 1900. This problem of hunt- The step-by-step solution of the multi-
only unbalance is that arising from a fault. ing was overcome largely by the use of machine transient stability problem as
In this case, the actual system voltages damper windings for the salient-pole type originally described during the 1930's is
and currents can be resolved into three of engine-driven alternator and by the use still used as the basis for determining the
completely independent balanced systems of closed rotor slots for the turbine-driven system transient stability characteristics.
with their own associated impedances. alternators. As a result, in the period Figure 5 is typical of a calculated swing
Today the terms used in symmetrical 1900-1910, the hunting problem had been curve. This is an example of a 4-machine
components are the accepted parlance of fairly well solved so that during the next problem which shows the effect of quick
the industry. The terms positive, nega- decade, 1910-1920, attention could be de- fault clearing. Today, stability studies
tive, and zero sequence form a part of the voted to the transient stability problem. are considered a part of most system
working tools of the transmission engi- During the 1920's, the fundamental studies and the methods of analysis have
neer. The application of relays and cir- theory began to be evolved which became been highly developed and continually re-
cuit breakers are based upon, and ex- the basis for the present-day methods of fined. Verification of the theory has been
pressed in, terms of sequence impedances. analysis. Both steady-state and transient obtained in many cases by actual system
The degree of system grounding is ex- stability theory were developed to a con- oscillographic records and relay opera-
pressed as a ratio of the zero- to positive- siderable extent in the 1920's and 1930's. tions of system disturbances.

OCTOBER 1 952 Crary, Gross, Wagner Progress in Electric Transmission 967


Table 11. A-C Calculating Boards boards are used primarily for the deter-
mination of power system performance,
Year including load flow and stability, and for
Name Location Installed the accurate predetermination of the re-

Massachusetts Institute of Technology


quired line and terminal equipment. The
(in co-operation with General Electric Company) .... ......... Cambridge, Masa. 1929 stability problem also has been solved
Westinghouse Electric Corporation Number 1
(later transferred to Purdue University) ..................... East Pittsburgh, Pa. ... 1929 more recently by the use of the differential
Pennsylvania Railroad .................................... New York, N. Y. 1932 analyzer and miniature systems using
Commonwealth Edison Company
General Electric Company Number
.......................... Chicago,
.................. Schenectady, N. Y.
193 rotating machine analogues. These lat-
5. 1 .....
Public Service Company of New Jersey ..................... Newark, N. ... 1938 ter methods are more effective for study-
Valley
Tennessee Authority ................................ Chattanooga, Tenn.
Bonneville Power Authority ............................... Portland, Oreg. 1938 ing special effects and are limited to rela-
Sao Paulo Tramway Light and Power Company ............. Sao Paulo, Brazil.
Potomac Electric Power Company .......................... Washington, D. C.
*. 1940
1941
tively few machine groups. The a-c cal-
11. Hydro-Electric Power Commission of Ontario .............. Toronto, Ontario, Canada 1941 culating board is by far the most impor-
Public Service Company of Oklahoma ...................... Tulsa, Okla.
Westinghouse Electric Corporation Number 2.. East Pittsburgh, Pa.
.1941
tant means for solving the specific and de-
..
1942
Illinois Institute of Technology ............................ Chicago, 1945 tailed system problems involving many
15. Iowa State College ........................................ Iowa Ames,
16. Agricultural and Mechanical College of Texas College Station, Tex.
..............
.1946
.1947
machine groups.
City of Los Angeles Department of Water and Power Los Angeles, Calif.
......... 1947 The methods of analysis which have
University of Kansas ..................................... Lawrence, Kans.
Associated Electrical Industries, Ltd ................ Willesden, England.
... 1947 been developed, combined with the use of
20. Georgia School of Technology ........................ Atlanta, Ga ........... .1947 the a-c calculating board, have resulted in
Pacific Gas and Electric Company........ San Francisco, Calif. ... .1948
Consolidated Gas Electric Light and Power Company of a broad and basic understanding of system
Baltimore ............................................. Baltimore, Md.
United States Bureau of Reclamation ....................... Denver, Colo. 1948 performance under both steady-state and
24. Electricite de France ...................................... Paris, France. .. 1948 transient conditions. This has aided ma-
General Electric Company 2 ............................... Schenectady, N.
English Electric Company, Ltd ............................. Stafford, England.
1949 terially the rapid advancement of im-
26.

Jugoslavia ........................................................................ .1949 proved methods of operation and prac-


University of California .................................. Los Angeles, Calif.
India Institute of Science .................................. Bangalore, Hindustan. *1950 tical system design for improved economy,
Electricity Supply Commission of Johannesburgh ............. Union of South Africa. 1950 and has provided an effective engineering
Victoria State Electricity Commission ....................... Melbourne, Australia.
Commonwealth Edison Company .......................... Chicago, 1951 tool to cope with the rapid expansion and
Northwestern University
University of Illinois
..................................

......................................
Evanston, Ill.
Urbana, Ill.
1951
.1951
interconnection of systems.
35. Detroit Edison Company .................... Detroit, Mich. 1951 Another important calculating device
American Gas and Electric Service
Westinghouse Electric Corporation
Corporation ..............

.........................
New York, N. Y.
Lima, Ohio.
1951
1951
is the transient analogue computer which
Comision Federal De Electricidad .......................... Mexico City, Mexico .on order has provided a means for studying a wide
Tabelec ............................. Brussels,Belgium
Magrini, S. A.Bergamo, Italy .on order range of transient problems resulting
from faults, switching, and lightning
surges. By means of these devices it has
Improvement of stability characteris- metries. Later, the machine th been possible to include the nonlinear
tics is now realized by a relatively small extended to include the effect of aory was effects, for example, of saturation in trans-
increase in cost by proper co-ordination of seur windings, excitation response ~,satura- formers and lightning arresters, which
would have been far too difficult to solve
the design factors. The essential reason tion, and other characteristics s This
for this is that the trend in system and continually improved understai nding of by ordinary methods. This type of de-
vice has been most useful in investigating
equipment design, in order to obtain high the performance of synchronous machines
loadings and low investment costs, neces- provided a sound basis for evaluCating the the causes of overvoltages and what had
sarily has been steadily in the direction to different characteristics of the electric
been heretofore complex and not well-
improve the system stability character- equipment and their influence oi system n
understood phenomena.
istics. design.
Overvoltages Other than Lightning
Machine Analysis Calculating Devices
As the methods of analysis and ex-
It was realized early in the development The economic importance of power perience were applied successfully to re-
of the stability theory that an adequate system studies and the excelleint back- duce the frequency and severity of out-
theory for synchronous machine perform- ground for analysis which had been de- ages caused by lightning, increasing atten-
ance was also essential. Much of this veloped from the theory of syTrimetrical tion was given to all other sources of over-
fundamental work was developed by components, stability, and rotalting ma- voltages. A report in 1948 by the General
Doherty and Nickel" and Park'2 and from chinery resulted in the developu nent and Systems Subcommittee of the AIEE
this grew an understanding of the impor- application at an early date of sp)ecial cal- Transmission and Distribution Commit-
tant characteristics, particularly the re- culating devices for the solution cif system tee entitled "Power System Overvoltages
actances, which define the essential per- problems. One of the most outtstanding Produced by Faults and Switching Opera-
formance of machines under steady-state developments was that of the a-c calculat- tions"'13 gives the historical background
and transient conditions. This develop- ing board in 1929 which had E een pre- and analytical and experience record, as
ment of machine theory was paralleled ceded about 10 years by the wse of d-c well as a bibliography of this material.
with both system and generator tests, calculating boards for the determination Reference 14 further extends this bibliog-
verifying the correctness of the theory. of short-circuit currents. The uLse of the raphy. These studies, making use of the
The machine analysis, coupled with the a-c network calculating board has de- analogue computers and test experience,
method of symmetrical components, pro- veloped at an accelerated rate diuriig the resulted in a greatly improved under-
vided the basis for studies of the effect past decade. Table II, which . lists 40 standing of the cause of overvoltages and
of unbalanced faults and other dissym- boards, indicates their wide use . These the performance of protective equipment

968 Crary, Gross, Wagner-Progress in Electric Transmission OCTOBER 1 952


such as to provide a rational basis for the Table 111. Preferred System Voltages above 1,000 Volts
reduction of line and terminal insulation,
From EEI-NEMA Preferred Voltage Report, 1949
all in the direction of further system
economy.
Maximum Tolerable Voltage

Preferred System Voltages Preferred Primary Substations


Nominal Voltage Voltages at and
System Utilization Distribution Transformers
Voltage Point Transformers Systems
Standardization of voltages dates back
to the AIEE standardization rules of
1899. Since that time there have been 2,400 .... ....... 2,540 ... ...... 2,600 ..... ..... 2,750
2,400/4,160 Y ........... 2,540/4,400 ......... 2,600/4,500 . ......... 2,750/4,760
several revisions, the last of which took 4,800 .... ....... 5,080 ... ...... 5,200 .... ...... 5,500
6,900* .... 7,200 .................................
place in 1949 through the activity of the
...............

7,200. 7,800 .................... 8,250


Edison Electric Institute (EEI) and the 4,800/8,320 Y .......... 5,200/9,000 ........... 5,500/9,520
National Electric Manufacturers Associa- 12,000 .......... 13,000 .......... 13,200
7,200/12,470 Y .......... 7,200/12,470 .......... 7,920/13,700
tion (NEMA).'5 The latest revision be- Y7,620/13,8200 ...........8.............................. 8,250/14,300 .......... 8,320/14,500
came necessary because of (1) the upward 13,200 .................... 14,300 ................... 14,500
14,400 ... 15,000 .................... 15,500
trend of utilization voltages, (2) the in- 23,000 ......................................................................... 25,800
creasing use of high- and low-voltage net- 27,600 ..... 31,000
works, and (3) more complete studies of 34,500 ......................................................................... 38,000
46,000 ......................................................................... 48,300
voltage regulation problems. Table III 69,000 ......................................................................... 72,500
gives the results of the EEI and NEMA 115,000 ......................................................................... 121,000
138,000 ......................................................................... 145,000
recommendations. The first column in 161,000 .... 169,000
this table gives the preferred nominal 230,000 .... 242,000
system voltages. The maximum toler- * Since utilization at this level is confined principally to 6,600-volt motors in large steel mills, mines, and
so forth, a nominal designation of 6,900 volts is commonly used and is included herewith, even though it is
able voltage at which the system must not consistent with other nominal voltages in the utilization group. The voltage zones for this level like-
operate is of utmost importance to the wise are related to 6,900 volts rather than to 7,200 volts.
utility engineer in determining the volt-
age regulation conditions and to the
manufacturer in designing his equipment
to meet system operation conditions. It
perweld, or galvanized steel, and are giv- in which a line that has been de-ener-
was recognized that the maximum toler-
ing entirely satisfactory performance. gized for some time flashes over upon
able voltage must be a function of loca- being re-energized even under normal
tion in the system at which the equipment Line Insulation voltage. This phenomenon appears to be
is placed to provide for regulation. This associated with the condensation of dew,
has been taken care of by establishing While, as was shown under the section which would not have occurred had the
different maxima for (1) the voltage entitled "Lightning Protection," the line been energized continuously.
utilization point, (2) primary voltages at number of insulators has a profound effect As can be seen from Figure 4, the num-
distribution transformers, and (3) sub- upon the lightning performance of lines, ber of insulators that are used most fre-
station and transformer svstems. These the actual number of insulators usually quently in practice at any voltage in-
three maxima are listed in Table III also. are selected for other reasons. If light- crease progressively as the system volt-
In the higher voltages there is less need for ning were the only consideration, there age increases. The lines, as a result, also
a distinction between these conditions, wotuld not be much difference in insula- become progressively immune to light-
and only one maximum which at 46 kv tion between lines of different voltages. ning. At about the 230-kv level of in-
and above is 5 per cent above the nominal. Surveys indicate that, in general, the in- sulation, an increase in the number of in-
sulation increases with voltage. Table IV sulators does not appreciably improve the
gives the most common number5 and the lightning performance. Unless contami-
Ground Wires range of insulators that are used on wood- nation conditions dictate otherwise, it is
pole and steel tower lines. It is difficult to likely that beyond 230 kv a somewhat re-
As stated previously, the function of determine precisely the insulation for a duced increment of insulation can be
ground wires is to intercept the lightning given line. And, of course, this is borne used.
stroke and to prevent the stroke from out by the range in the number of insu-
striking the current-carrying conductors. lators that are in use at the present time. Conductors
Before the need for adequate grounding Contamination, whether from salt spray
and tower footing resistances was well or industrial depositions, plays an impor- The choice of conductor size in the
understood, the mechanical hazards, with tant part. Table IV gives the 60-cycle early days appeared to be influenced
the poor construction then in vogue, fre- flashover values of different numbers of largely by the dictates of Kelvin's law.
quently overshadowed the advantages ob- insulators under both wet and dry condi- Today, however, there are many other
tained. However, during the past 25 tions. These values are for clean insula- factors which influence the choice, such as
years, with the better understanding of tors. Dirt might well decrease the flash- providing for suitable transmission-line
its function and the improvement in over so that the insulators, which under capabilities, and emergency requirements
mechanical construction, the ground wire wet conditions and clean, have a flash- as well as service reliability under the
has developed from the accessory or over of five times normal, when wet and most severe operating conditions. Loads
nuisance stage to conductors having the contaminated might have a value of three on transmission systems are not fixed
same reliabilities as the current-carrying times normal. This approaches a condi- throughout their useful life. They vary
wires. Today they are usually made of tion under which switching surges could widely in some cases because of changing
steel, reinforced aluminum, copper, cop- produce flashover. Conditions also occur power flow between systems, possible

OCTOBER 1 952 Crary, Gross, Wagner-Progress in Electric Transmission 969


Table IV. 60-Cycle Characteristics of Modern Lines
Wood-Pole Lines Steel-Tower Lines
60-Cycle Flashover 60-Cycle Flashover
Nominal
Voltage Number* Dry Wet Number* Dry Wet
in of Times Times of Times Times
Kilovolts Insulators Kilovolts Nominal Kilovolts Nominal Insulators Kilovolts Nominal Kilovolts Nominal**

4 270 . 6.8 . 180 ... 4.5............ 4.......... 270 .......... 6.8 .. 180. 4.5
69 .......... .........330 . 8.3 ......230 . 5.8 ............ 380......... 9.5 .
... 260
. 6.5
6 ....... 380 .. 9.5 .......... 270 ......... 6.8 . . 8 500 . 12.5 8.5. 340
5 6 380 . 5.7 .......... 270 ......... 4.1 . 6. 380 . 5.7 . 3.9.
260
115 .......... 8 . 00. 7.5 . 340 . 5.1............ 8.......... 500 .......... 7.5 . 340 . 5.1
10 600 9.0 420 .......... 6.3
..........
. 10 . 600 . 9.0 . 6.2. 410
8. 500 . 6.3 .......... 340 .......... 4.3 . 8. 500 . 6.3 . 4.3. 340
138 . ..9......... .......... 6.9 . 370 . 4.7
. .........0 600
10 .......... 7.5. 4105. 1
11....... 660 .. 8.3 .......... 450 . ......... 5.7 12 . 710 . 8.9 . 6.0. 480
i9 550 . 5.9 .......... 370 .......... 4.0 . 9. 550 .
660
11 ..........
5.9 .
7.1.
4.0.370
450 4.8
161 . 10......... . 600 .. 6.5 . 420 . 4.5 . .
(12 . 710 .. 7.6 .......... 480 ...........5.2 . 14 . 820 . 8.8 . 6.0. 560
14 . 820 . 6.2 . 560 . 4.2
230 ..... .16 . 930. 7 .. 630. 4.7
20 . 1140 .......... 8.6 .. 780 . 5.9
516 .. 930 .......... 5.6 .. 630 . 3.8
287. . . . .18
. 1030 . 6.2..
......... 710 . 4.3
22 .. 1250 . 7
...... .. 8.55...1
* Middle number represents most common practice; other numbers the range.
** Times normal line-to-ground.

failure of equipment or paralleling lines, moved in the early 1920's with the de- kv lines. Limited trial installations also
staged or forced outages of equipment for velopment in the art of making insulators have been made on 220-kv lines. Many
maintenance, and system growth before with freedom from porosity and a better protector tubes are now in service on 110-,
additional generating facilities can be in- performance under the thermal expansion 66-, 33-, and 27-kv lines and are giving
stalled. These are features which must be characteristics of porcelain and hardware. good account of their ability to make the
considered in selecting the conductor This resulted in availability of porcelain lines lightning-resistant.
size. insulators not only of the suspension type On the high-voltage lines (132 kv) the
In the extra-high voltage field, factors but also of the pin type, where required, tubes were mounted directly on the in-
other than copper loss must be considered. which have given an excellent account of sulator string assemblies and at every
Corona was given careful study in the themselves since that time. Today there structure. On the lower voltage lines the
early 1930's prior to the building of 288- is practically no insulator problem as tubes were supported directly on the
kv lines. Radio influence is now another such. tower arms or from auxiliary arms or
factor which has received considerable at- The early design of high-voltage trans- bracing. To reduce cost on the lower
tention of late in the projected design of mission lines of 110 kv and above using voltage lines, the tubes were mounted at
extra-high voltage lines. The result of suspension insulators gave trouble in every third structure or so but usually on
this study shows the need to increase the some cases (in addition to faulty porcelain all three phases of the line. A later prac-
conductor diameter to limit radio in- and insulator assembly) due to insulator tice on lines not using ground wires was to
fluence; see Figure 6. On the other hand, damage by lightning flashover. This install the tubes on the top phase wire
an offsetting influence is the requirement situation was brought under control by only, thus using the top line wire as a
of keeping the lines serviceable under sleet the use of arcing horns or grading shields shield or ground wire and diverting the
conditions, which requires the use of a (so-called) which, with proper design, lightning to ground through the tube.
smaller conductor than required for free- held the short-circuit arc clear of the in- This practice has been reported as success-
dom from corona, radio influence, and sulator porcelain and minimized damage ful.
thermal limitations. to the insulators and conductors. It is
The use of copper for line conductors in worth noting that when this development Grounding Practices
the early days has given way in a large took place, relatively long relay times on
degree to aluminum with steel core in the transmission lines permitted a long dura- In this country "solidly grounding" is
high-voltage field and long span construc- tion and heavy concentration of short-cir- the preponderent method of grounding of
tion. Today consideration also is being cuit power, which was the inherent cause systems in all voltage classes above 23 kv.
given to all-aluminum conductors and of insulator damage. Ungrounded and reactance-grounded sys-
their use may prove feasible. Over-all Today, however, due to the high speed tems are found principally in the 23- and
economy of line construction and the cost clearing of line faults, arcing horns or 34.5-kv systems and at lower voltages.
and availability of the two metals will, of grading shields generally are omitted on Also, in voltages below 25 kv (distribution
course, set the pattern for the future. new lines. range) is found the 4-wire system, a type
that appears to be indigenous to this
Insulators, Arcing Horns, and Protector Tubes continent. It consists of a grounded-
Grading Shields neutral wire which runs the entire length
As a further means of preventing light- of the circuit and fans out with each
As mentioned previously, line insula- ning flashover of line insulators, protector single-phase lateral. Loads may be taken
tors in the early days were one of the tubes came into use on an experimental from such a system either from phase to
major obstacles in going to higher trans- basis about 1933. Some of the first in- phase or from phase to neutral, the fourth
mission voltages. This limitation was re- stallations were made on 110-kv and 132- wire carrying the unbalanced components

970 Crary, Gross, IVagner-Progress in Electric Transmission OCTOBER 1 952


of load. The ground-fault neutralizer, use of lightning arresters of lower ratings. Table V. Maximum Continuous Load Range
variously called the Petersen coil or the The use of the ground-fault neutralizer of Self-Contained and Pipe Cable
resonant grounding coil, is used mainly in is found most frequently on the systems
the intermediate and lower voltage sys- around 34.5-kv. In America this type of Voltage
Rating,
Oil-Filled
Cable in Ducts,*
Buried
Pipe Cable,**
tems such as 34.5 kv. grounding is used at about this voltage Kilovolts Megavolt-Amperes Megavolt-Amperes
Various reasons have been given for the for the two following reasons: 1. the cost
strong popularity of the grounded-neutral incentive of lower insulation applicable to 69 . 140 to 175 ....... 90 to 100
system. Solidly grounding permits a re- higher voltages is no longer present in this 138 . 265 to 300 ....... 150 to 175
230 . 370 to 405 ....... 220 to 245
duction in the equipment insulation range; and 2. lines in this category are * Conductor size 3,000,000 circuLlar mils. If directly
through the lowering of the rating of the less likely to be equipped with ground buried, increase loading approximately 30 per cent.
lightning arresters that are applied for its wires and are therefore more subject to ** Conductor size 1,500,000 circular mils.
protection. Solidly grounding simplifies lightning flashovers. This condition in- Five types of cable are currently available for use
at high voltages:
the relaying system and provides it with creased the need for a self-clearing de- 1. High-pressure self-contained oil-filled cable.
greater discrimination and positiveness. vice, such as the ground-fault neutralizer, 2. Low-pressure self-contained oil-filled cable.
Solidly grounding also reduces the mag- to clear the line-to-ground faults on the 3. High-pressure oil-filled cable.
nitude of switching surges and reduces the line. The application of the ground-fault 4. High-pressure self-contained gas-filled cable.
5. High-pressure gas-filled pipe cable.
possibility of arcing grounds and double neutralizer is more difficult to justify on
or consequent faults. It is also more systems with ground wires because the
adaptable to interconnection. It further faults that originate as single-line-to- 1921 this type of insulation was used up
permits the use of graded insulation on the ground faults constitute a smaller propor- to 33 kv and by 1926 up to 69 kv.
transformer neutral end. On the other tion of the total system faults. With The voltage range available for under-
hand, solidly grounding can increase the ground-fault neutralizers only the line-to- ground cable use was increased radically
maximum fault current and in rare cases ground faults are self-extinguishing; all when the first oil-filled cables (138 kv)
increases the flow of harmonic currents in other faults must be cleared by circuit- were put in operation in 1927. Oilostatic
the ground circuits. The latter on oc- breaker operations. While the propor- was first used in 1932, and high-pressure
casion has been the source of trouble in tion of single-line-to-ground faults lies be- gas-filled pipe cable in 1941. Self-con-
parallel telephone circuits. However, the tween 50 to 80 per cent, the proportion tained gas-filled cable of the low-pressure
improvements in telephone systems and varies with the type of system and with type was introduced in 1939, the medium-
the understanding co-operation between tower footing resistance. pressure type was introduced in 1944, and
the power utilities and the telephone the high-pressure type in 1949.
companies have advanced to such a High-Voltage Cable Underground cable can compete eco-
stage that today this phase of the problem nomically with a-c overhead transmission
is of little consequence. The reduction The earliest underground power "cable" only where a short cable line can be sub-
in cost, consequent to the reduction in in- installed in this country in 1879 was a stituted for a much longer overhead line.
sulation, applies particularly to the sys- 220-volt Edison Tube. This consisted of Underground cable lines rarely exceed 10
tems of 115 kv and above. Below 115kv three copper rods insulated with jute and to 13 miles in length; this limit, however,
the economy in going to the next lower asphalt and installed in an iron pipe. By is economic and not technical. Longer
insulation level is not so significant, and as 1888 lead-covered rubber cables were submarine crossings are being studied.
a result these systems usually use full in- operating at 1,000 to 2,000 volts. Solid- Cables often are used as links in trans-
sulation. In many cases, in the 34.5-kv type oil-impregnated paper insulation mission lines. Otherwise for long cable
and 69-kv classes, solidly grounding is ap- was introduced in England in 1890 and
lengths the economic considerations will
plied for relay protection, and permits the reached this country soon afterward. By require interconnection through trans-
formers to the higher voltage system.
2.2 The maximum required loads per circuit
which can be handled by 138-kv duct
2.0 cable are increasing. In the near future
loads justifying the use of 230-kv cable
are expected to be reached. Table V in-
1.8Al dicates possible cable loadings.
1I.6
z System Outages
w 1.4 As mentioned before, the pioneers rec-
ognized reliability of service as one of the
1.0~~ prime requisites of the electric power art.
This, of course, comprises not only the
transmission line but all the major equip-
0
ment entering into a power system.
Since the early 1920's when 110- to 132-
Figure 6 (left). Typical radio- kv transmission lines were in service, and
influence effects 100 feet from shortly thereafter 220-kv lines, a great
under line conductor for vari- deal of time and effort has been spent in
ous line-to-line voltages and studying the outage performance (par-
450 conductor diameters. Fair- ticularly lightning) of lines of this voltage.
weather conditions In a 1946 report16 covering the operation

OCTOBER 1 952 Crary, Gross, Wagner-Progress in Electric Transmission 971


of all 220-kv lines in this country and with rubber equipment. In the higher system requirement to obtain high cir-
Canada, it was shown that lightning out- voltage lines, however, even 12 kv, such cuit kilowatt loadings with a minimum of
ages per hundred miles of line per year rubber equipment is not considered satis- system investment. With the increased
with an isokeraunic level of 50 ranged factory protection, and certainly is use- reliance placed on the switchgear be-
from 0.14 to a high of 45, and with those less at the higher voltages. For this cause of the solidly bussed high-voltage
lines built with special consideration to reason, so-called "hot-line maintenance" type of system, it has been necessary to
lightning resistance, were in the order of has been adopted as standard procedure attain a very high degree of reliability
about 3.8 outages per hundred miles of in many companies in this country. It is of the circuit breakers and relaying.
line per year. being used on voltages up to and includ- High-speed reclosing also was improv-
With our present knowledge of light- ing 288 kv. Special tools, such as tongs, ing the reliability and economy of sys-
ning and its effect on transmission lines clamps, wrenches, and even tools for ap- tems at the same time. Originally, re-
and remedial measures, these outages can plying armor rods where used on the con- closing was accomplished in 35 or more
be brought within control and down to ductors, have been developed and are in cycles. Development in the circuit-
nearly any practical value, although in practical use throughout the country. breaker art has made it possible to de-
some cases other means of controlling the Defective insulators in both the suspen- crease the reclosing time to 30 cveles and
power outages, such as high-speed re- sion and strain position can be replaced then to 20 cycles. Some present circuit-
closing circuit breakers and duplicate by the use of such tools. Many other breaker mechanisms are capable of 13)
lines in service, also produce effective re- operations such as repairing conductors, cycles, or even less, although actual use of
sults. installing armor rods, applying vibration less than 20 cycles in the field is very
dampers, changing grading shields, and rare.
making and removing tap connections are Single-phase reclosing has found an im-
Transformer Failures now regular procedures with lines ener- portant but limited field of application.
Another factor which influences the gized as high as 288 kv. A recent survey of high-voltage line out-
service reliability of electric power is the ages'7 indicates that single-pole reclosing
transformer which supplies the trans- constitutes less than 5 per cent of the total
Circuit Breakers number of high-speed reclosing applica-
mission lines. Without the transformer
the line is useless. In the transmission tions, whereas 3-phase automatic reclos-
System operation in the 1920's directed ing is used for almost 40 per cent of the
range there were in the early days trans- attention to the need for quicker fault
former failures which were a serious prob- total number of high-voltage circuit
clearing in order to overcome the stability breakers reported. The sur-ev empha-
lem. Today, however, with the better limitations as produced by multiphase
understanding of voltage stresses placed sized the desirability of quick reclosing in
faults. In the early 1930's the first high- that 91 per cent of the reported outages
on transformers in service including light- speed high-voltage circuit breakers having
ning, switching, and long-time power fre- were capable of either quick or immediate
an opening time of 8 cycles were de- reclosure. It is accordingly expected
quency voltage, the transformer, by veloped and placed in operation. This
reason of improved design and adequate that high-speed reclosing will find in-
was followed shortlv by the development creasing application for high-voltage sys-
lightning protection, has become one of of 3-cycle circuit breakers of 2,500,000
the most reliable pieces of equipment in tems.
kva interrupting capacity for the Hoover
the electric power system. In fact, so re- Dam to City of Los Angeles transmission
liable has the large power transformer be- line. With the subsequent interconnec- Protective Relaying
come today that the general practice in tion of systems and the greater concentra-
most cases, where practicable, is to use the tion of power in a single generating station Protective relaying has been improved
lower cost single 3-phase transformer in- it became desirable to develop circuit continually to provide faster disconnec-
stead of the former practice of four single- breakers of higher interrupting capacity. tion of faulted transmission-svstem ele-
phase units, one serving as a spare. In- In 1945, 3-cycle circuit breakers of 5,000,- ments. The evolution of carrier-current
deed, the failure of large power trans- 000 kva interrupting capacity were de- pilot relaying for transmission lines has
formers in service is an infrequent occur- veloped for 138 kv, 161 kv, and 230 kv. reduced the operating time from a 6 to 12-
rence, and this feature is of such minor The desirability of obtaining flexibility cycle range to a 1 to 3-cycle range. To-
concern today that a search of the records of operation at the Grand Coulee Station day, the microwave-pilot channel is
fails to show any broad range accumula- emphasized the need for higher interrupt- available as an alternative to carrier cur-
tion of data on "percentage of transformer ing capacity circuit breakers, rather than rent wherever conditions justify its use.
failures per year." to use electrical impedance between the Developments in high-speed bus and
This reliability of present-day large individual bus sections. This need led to power-transformer differential relaying
power transformers, of course, affects the the development of 10,000,000-kva 230- have kept pace with transmission-line re-
system layout and contributes to the more kv circuit breakers. This trend toward laying so that today economical and re-
economical first cost of the system. the use of a solidly bussed high-voltage liable high-speed relaying is available
transmission system has continued, re- for all elements of the high-voltage trans-
Line Maintenance sulting in switchgear designed for 15,000,- mission system.
000 kva interrupting capacity and 1,600 It is most significant that this progress
No matter how well the line may be de- amperes continuous current at 330 kv. has made feasible the standardization of
signed and built, it requires maintenance The high-voltage circuit-breaker develop- transmission-system relaying practices.
during various periods of its useful life. ment in the last decade has been charac- Only slight modifications are necessary to
In the early days with voltages not ex- terized by the reduction in switching time, adapt the equipment to such special ap-
ceeding 5 kv, maintenance was done, in increase in interrupting capacity, and plications as series capacitors and single-
many cases where the line could not be de- increase in continuous current capability. phase switching. Such progress has been
energized, by protecting the workmen These developments were the result of the made possible by the development of

972 Crary, Gross, Wagner-Progress in Electric Transmission OCTOBER 1952


analytical tools and techniques to the ity for each of the interconnected sys- kw from the mainland of Sweden to the
point that basic and hence widely ap- tems; the best use of the diversity load island of Gotland,18 a distance of 60 miles.
plicable solutions to the many problems factor for the different systems connected; It is contemplated that the first stage of
have been achieved. Future develop- supply of emergency power in case of building will consist of a single conductor
ments will continue to stress this aspect equipment breakdown; and abnormally cable with current return through the
as well as simplification and still faster low rainfall in case of a major hydroelec- ocean. The voltage will be 100 kv. D-c
operation. tric system. transmission across the British Channel is
Cases have occurred where acceptable under consideration.
power requirements have been supplied to A considerable amount of work also
Sleet Melting an interconnected system even though one was done in Germany during the late war.
of its major plants has been interrupted. In this case cable also was used but buried
One of the causes of line outages which, This practice has so many advantages in the earth. It has been stated that stra-
although not frequent, is particularly that it has grown enormously in recent
troublesome when it does occur is that due tegic considerations were an important
years. It is still expanding and will con- element in this work as it was believed
to accumulation of sleet and ice under
tinue to do so in the future. that such a line might not present as con-
weather conditions around freezing tem-
venient a target for aerial bombing as an
perature. If ice is allowed to form on the
overhead line.
conductors under these conditions, not D-C Transmission
only does it produce extra-heavy loads A number of important problems re-
which under extreme conditions may main to be solved, such as the develop-
Because of the higher voltages at which ment of high-voltage tubes for conversion
cause a break in the conductor or tower overhead transmission lines apparently
damage but also it may create conditions at both ends of the line, circuit breakers,
can be operated with direct current as and lightning arresters. In the absence
where the unloading of the ice from the contrasted with alternating current, the
conductors creates a short circuit result- of d-c circuit breakers it will be necessary
increased efficiency of transmission for the to use the conversion tubes to clear the
ing in a permanent line fault. To guard same conductor has presented an attrac-
against such conditions, several methods faults and to provide switching. The
tive advantage. The permissible ratio of lightning arrester presents a formidable
of sleet melting have been devised for direct voltage to alternating voltage is
high-voltage lines, and even for lines as problem as an entirely new principle must
still problematic as it depends upon such be devised, the a-c lightning arrester de-
low as 12 and 33 kv in special cases. One factors as corona threshold voltage and
method consists of short-circuiting one pending for its operation upon the peri-
the relative characteristics of insulators odic passage of the voltage through zero.
end of the transmission line known to be under alternating and direct potentials.
in trouble and applying full voltage at the A definite limitation in d-c transmission is
The advantages of d-c transmission may its inflexibility with regard to taking off
other end, if sufficient line length can be be either partially or completely balanced
made available to control the current. additional loads or adding generating sta-
out by the cost of the conversion equip- tions either initially or as the system
For shorter lines reduced voltage from ex- ment at both ends of the line. Economic
isting lower voltage lines sometimes is grows as each additional tap requires
studies made in this country indicate that expensive terminal equipment.
used. Another method of overloading the d-c transmission with overhead lines can
stricken line is by switching of other cir- The improvements and developments
only become attractive for projects in- that are continually being made in a-c
cuits. volving the transmission of loads in ex-
Melting times vary from 20 minutes to transmission progressively increase the
cess of about 350,000 kw, a straightaway
11/2 hours, depending on the current difficulty of justifying d-c transmission on
distance of at least 320 miles. a purely economic basis. The reduction in
available. Melting currents of the order This country has been bountifully sup-
of two to three times rated current are insulation levels occasioned by the im-
plied with natural fuel resources such as provements in lightning-arrester charac-
used. Circuit breakers and carrier-cur- hydraulic power sites, coal, gas, and oil.
rent line traps must be suitable for these teristics and the possibilities provided by
There is hardly a location in which fuel in series capacitors completely eliminates d-c
currents and durations. good supply is not available within 350
To detect the approach of ice formation transmission as a serious contender
miles of a point of substantial consump- against a-c transmission in the United
an ingenious scheme is in use by at least tion. D-c transmission in this country
one company where significant variations States.
therefore does not possess attractive pos-
in the carrier-current magnitude which sibilities. In addition, there are very
normally flows in the line give warning many technical problems to be solved be- Economics of High-Voltage
that glaze is forming fore d-c transmission can become prac- Transmission
tical.
System Interconnections Where transmission by cable over con- The economics of high-voltage trans-
siderable distances is necessary, the ad- mission is determined essentially by the
System interconnections of high-voltage vantages of d-c transmission are more following principles:
transmission lines were first put into use pronounced. The ratio of the permissible The cost per kilowatt of transmission-
some 25 to 35 years ago, and their value direct to alternating voltage is much line capability goes down with increasing
from many aspects has been so beneficial greater in cables than for overhead lines voltage, whereas the cost per transformer
that the practice has grown rapidly and is and, in addition, the limitations of charg- kilovolt-ampere for a given size increases
with increasing voltage, and the cost per
still increasing. One company reports 16 ing current which are more important for kilovolt-ampere decreases with increasing
interconnections with other companies in cables are not present. The Swedish transformer bank capacity rating. Accord-
a large 132-kv network. State Power Board, in co-operation with ingly, higher voltage becomes more eco-
Among the benefits derived from such Allmanna Svenska Elektriska Aktie- nomical when it is used to transmit a large
block of power using large transformer
interconnection are the lower require- bolaget (ASEA), is working on a d-c proj- banks at the step-up and step-down ter-
ments for total installed generator capac- ect involving the transmission of 20,000 minals. The higher voltage also becomes

OCTOBER 1952 Crary, Gross, Wagner-Progress in Electric Transmission 973


more favorable as the transmission-line are relatively low compared to generating transmission may well be considered,
distance increases as the line investment station costs per kilowatt. broadly speaking, in the pioneer stage.
becomes greater relative to the transformer
investment. Today, with modern concepts However, transmission of electric en- The approach to the extra-high-voltage
of circuit loading, higher voltages can be ergy even moderate distances is not com- transmission problem has been studied
justified at much shorter distances than petitive with pipe-line transmission of en- and analyzed so thoroughly, and so much
were considered economical previously. ergy by oil or gas the same distance. At research work has been done prior to the
For example, depending upon local condi- the shorter distances oftentimes electric building of such lines, that we can look
tions, it may be entirely practical with a
voltage such as 330 kv to transmit 500,000 transmission may be cheaper than coal by forward with confidence to the successful
kw, if required, a distance of 50 miles. railway and therefore may fully justify a operation of these lines as was the case in
For a double circuit tower this would be large generating station at the coal mine. developing 110-, 1.39-, 220-, and 288-kv
1,000,000 kw. For distances from 200 miles to 600 transmission.
From the studies which have been made miles, the series capacitor provides a
of higher voltage systems, a pattern of means of realizing an almost constant cost
of transmission per kilowatt-hour per References
design has evolved which includes:
mile. It is expected that the higher volt- 1. STATISTICS OF ELECTRIC UTILITIES IN THE
1. A system configuration such that the ages will continue to be studied and ap- UNITED STATES. Federal Power Commission,
paralleled line may be kept equally loaded plied, particularly during this period of Washington, D. C., 1950.
and relatively short by the use of high- high rate of increase of kilowatt system 2. STATISTICS OF PUBLICLY-OWNED ELECTRIC
tension bussing at either end of the line UTILITIES. Federal Power Commission, Washing-
and by the use of intermediate switching capacity. ton, D. C., 1930.
stations for the longer lines. It is highly desirable that utilities in a 3. TRANSMISSION HOLDS RECORD PACE. Electrical
World (New York, N. Y.), January 28, 1952, page
2. The use of step-up transformers directly given area adopt the same voltage for 134.
from the generators to the high-voltage bus their bulk power systems. The cost per 4. DIRECT STROKES-NOT INDUCED SURGES-
with possibly an autotransformer tied kilowatt-mile for transmission facilities is CHIEF CAUSE OF HIGH-VOLTAGE LINE FLASHOVER,
from the new high-voltage system to the C. L. Fortescue. The Electric Journal (East Pitts-
fairly flat as a function of voltage which burgh, Pa.), volume 27, August 1930, pages 459-62.
existing lower voltage systems at the gener- permits utilities of different sizes to adopt Also AIEE LIGHTNING REFERENCE BOOK. AIEE,
ator end of the high-voltage line as well as 1937, pages 546-49.
at the receiving end. a common voltage without large penalty
5. TRANSMISSION AND DISTRIBUTION REFERENCE
to either large or small ones. The choice BOOK (book), Central Station Engineers. West-
3. The use of large conductors of 800,000 inghouse Electric Corporation, East Pittsburgh, Pa.,
circular mils of copper equivalent or greater. of a common voltage provides the nucleus fourth edition, 1950, pages 589-90.
of a high-voltage network for the area. 6. METHOD OF SYMMETRICAL CO-ORDINATES AP-
4. Use of double circuit towers to reduce PLIED TO THE SOLUTION OF POLYPHASE NETWORKS,
the cost of transmission, particularly where C. L. Fortescue. AIEE Transactions, volume 37,
the right-of-way costs are high. part II, 1918, pages 1027-1140.
Extra-High-Voltage Transmission 7. FINDING SINGLE-PHASE SHORT-CIRCUIT CUR-
5. Use of quick reclosing circuit breakers RENTS ON CALCULATING BOARDS, R. D. Evans.
and quick relaying. The highest transmission voltage in Electrical World (New York, N. Y.), volume 85,
April 11, 1925, pages 760-65.
6. The use of reduced insulation levels for this country, as mentioned earlier, is 288 8. SYMMETRICAL COMPONENTS (book), C. F.
both the transformers and circuit breakers kv, the Boulder-Los Angeles transmission Wagner, R. D. Evans. McGraw-Hill Book Com-
(230 kv and above) as determined by the system, and there is being built a 330-kv pany, New York, N. V., 1933.
lightning-arrester protective levels for 9. FIRST REPORT OF POWER SYSTEM STABILITY,
solidly grounded neutral systems. system, one line of which is now in opera- AIEE Committee Report. Electrical Engineer ing
tion at 138 kv, and later will form part of a (AIEE Transactions), volume 56, February 1937,
7. The use of planned emergency measures pages 261-82.
to cope with severe line outages. system of several hundred miles of 330 kv
superimposed on the extensive 132-kv 10. POWER SYSTEM STABILITY VOLUME II, TRAN-
SIENT STABILITY (book), S. B. Crary. John Wiley
One of the important advantages of the network of the American Gas and Elec- and Sons, Inc., New York, N. Y., 1947.
use of higher voltage systems is that it tric Company. 11. SYNCHRONOUS MACHINES, R. E. Doherty,
provides a means to effect a more efficient Another system is under construction C. A. Nickle. Parts I and II, AIEE Transactions,
volume 45, June 1926, pages 912-42. Part III,
transmission system as the old lower by the Aluminum Company of Canada at AIEE Tranisactionts, volume 46, February 1927,
pages 1-14. Part IV, AIEE Transactions, volume
voltage systems usually were built with 288 kv in British Columbia. The B.C.E. 47, April 1928, pages 457-87. Part V, AIEE
relatively large resistance-reactance ratios Electric Company, Vancouver, British Transactions, volume 49, April 1930, pages 700-14.
from 0.2 to 0.5. The losses in such lower Columbia, has under construction a 345- 12. TWO-REACTION THEORY OF SYNCHRONOUS
MACHINES-GENERALIZED METHOD OF ANALYSIS-
voltage systems become prohibitively kv insulated line, to be operated initially PART I, R. H. Park. AIEE Transactions, volume
high when used to transmit only moderate at 230 kv. 1 Reports are now current of 48, July 1929, pages 716-27.
blocks of power. considerations being given by others to 13. POWER SYSTEM OVERVOLTAGES PRODUCED BY
FAULTS AND SWITCHING OPERATIONS, AIEE Com-
High-voltage systems (230 kv and system voltages higher than 288 kv.20 mittee Report. AIEE Transactions, volume 67,
above) are expected to increase, par- In Sweden there is in operation a 380-kv part II, 1948, pages 912-21.
ticularly in the highly industrial areas system. A line exists in France designed 14. TRANSIENTS IN POWER SYSTEMS (book), H. A.
Peterson. John Wiley and Sons, Inc., New York,
where it is becoming increasingly difficult for 400 kv and now operated as a 2-cir- N. Y., 1951.
to obtain sites for generating stations near cuit 220-kv line. In England a 275-kv 15. PREFERRED VOLTAGE RATINGS FOR A-C
SYSTEMS AND EQUIPMENT, Joint Edison Electric
the load. Transmission distances of 50 to line is being built which is the beginning Institute-National Electrical Manufacturers Asso-
100 miles from fuel burning stations have of a projected system of 1,000 miles. ciation Report. EEI Publication Number R-6,
NEMA Publication Number 117 (New York, N. Y.),
become quite common in order to use Extra-high-voltage transmission is cer- May 1949.
favorable generating sites. tainly with us today, and with its de- 16. LIGHTNING PERFORMANCE OF 220-KV TRANS-
Higher voltage transmission makes velopment and our present knowledge of MISSION LINES-II, AIEE Committee Report.
Electrical Engineering (A IEE Transactions), volume
more attractive the use of larger turbine- the art, still keeping in mind the funda- 65, February 1946, pages 70-76.
generator units and in this way also ef- mentals of the original pioneers that elec- 17. REPORT OF JOINT AIEE-EEI SUBJECT COM-
fects further economies. Transmission tric energy must be reliable and economi- MITTEE ON LINE OUTAGES, AIEE Committee Re-
port. AIEE Transactions, volume 71, part III,
costs per kilowatt of capability for moder- cal, it is believed that we are at the point 1952 (Proceedings T52-6).
ate distances at the higher voltage level where the extension of extra-high-voltage 18. THE HIGH-VOLTAGE D-C POWER TRANS-

974 Crary, Gross, Wagner Progress in Electric Transmission OCTOBER 1 952


MISSION FROM THE SWEDISH MAINLAND TO THE tion, and a lead sheath extruded over the pany of Buffalo, N.Y., still doubtful about
SWEDISH ISLAND OF GOTLAND, Ake Rusck, B. G. core was a telephone cable designed by John paper, adopted Dr. Habirshaw's rubber in-
Rathsman, U. Glimstedt. Pqper Number 406, sulation for its 11,000-volt lines in 1897.
International Conference on Large Electric High- A. Barrett, of the American Telephone and
Tension Systems (Paris, France), 1950. Telegraph Company. It was a 52-pair, We have not been able to find anything
19. B. C. ELECTRIC PIONEERS 345-Kv TRANS- Number 19 American Wire Gauge cable, each definite about the first impregnated paper
MISSION, T. Ingledow. Electrical West (New York, wire insulated to a diameter of 1/8 inch. cable used for power except that it was on
N. Y.), M\ay 1952, pages 71-73. The order was placed in January 1888 by the system of the Chicago Electric Light
20. BONNEVILLE WILL TRANSMIT AT 300-345 Kv, Mr. Sargent, of the New York and New Company, now the Commonwealth Edison
S. E. Schultz, R. S. Gene. Electrical West (New Jersey Telephone Company, with the Nor- Company. It may be a 3-conductor 4,500-
York, N. V.), March 1952, pages 80-81. volt paper-lead cable was purchased by that
wich Insulated Wire Company of Harrison,
N.J. The cable was completed and tested company in 1897.
in May 1888. The Norwich Company, It is probable that 1895 marks the prac-
which was equipped with taping machines tical beginning of impregnated paper cable.
for making dry core cable, was not able to Shortly after this date several companies
started to make impregnated taped paper
Discussion perform the other manufacturing operations.
Therefore, when they had applied the paper cable. In 1897, the first 13,000-volt paper-
tape, they sent the singles to the Kerite insulated cable was made by the National
W. A. Del Mar (Phelps Dodge Copper Company, who performed the cabling opera- Conduit and Cable Company and installed
Products Corporation, Yonkers, N. Y.) and tion. The oven drying and impregnation, at Minneapolis and St. Paul, Minn. Some
L. F. Hickernell (Anaconda \Wire and Cable with a mixture of London Oil (rosin oil) early paper-insulated cables also were made
Company, Hastings-on-Hudson, N.Y.): and rosin, was carried out under Barrett's by John A. Roebling's Sons Company.
Only one brief section, entitled "High-Volt- direction in the basement of the John The National Conduit and Cable Com-
age Cable," and one table, Table V, in this Robertson plant in Brooklyn, and the sheath pany shipped about 400 miles of 5,000-volt
otherwise admirable paper are devoted to was applied by the same Robertson Com- paper cable to England and Ireland in 1895,
high-voltage cable, an amount hardly com- pany, then a well-established maker of which was installed under the direction of an
mensurate with the importance of the sub- presses. American engineer named Reid. This was
ject. One statement in this section that Impregnation of fabric with oily com- Europe's introduction to this type of cable.
may be questioned is that solid-type oil- pounds was well known before the days of That the uncertainty about paper per-
impregnated paper insulation reached this paper cable, but it was thought that the sisted to 1899, when a 25,000-volt system
country after its introduction in England in mere immersion of the fabric in hot oil was projected for St. Paul and Minneapolis,
1890. The reference to England relates to would drive out the moisture by evaporation is shown by the fact that in 1900 both rub-
Ferranti's famous 20-foot rigid mains which and the air by expansion. It was J. T. ber and paper cables of that voltage were
were insulated for 10,000 volts with wide Jaques, of Boston, Mass., then associated installed on that system.
sheets (not tapes) of brown paper steeped with the Faraday Electric Cable Company, By 1902 paper insulation was fully estab-
in Ozokerite wax, not oil. This audacious who patented in 1885 a process combining lished and, substantially unchanged from its
installation was really an extension of the vacuum drying with hot impregnation under original type, proved adequate to all needs
Edison Tube system, substituting paper for pressure. However, for many years after until the time of World War I, when the use
jute, and was in no sense a cable, but an in- the Jaques patent was issued, the open im- of electricity increased with unprecedented
sulated bus. mersion process was used in America and rapidity and introduced new loading condi-
There are many early instances of the use was used until recently in Europe for low- tions. Since that time the cable engineer's
of paper insulation, and its use on electric voltage cables. problem has been to find ways and means to
power wires dates, in several cases, to 1880 The Norwich Wire Company began to sell increase the voltage and current-carrying
or earlier. These isolated cases are not, the product of its Harrison plant in 1887, capacities of cables without increasing their
however, the ancestors of our paper cable, acquired a lead press in 1890, and sold out diameter beyond the 3 or 4 inches imposed
for they all died without leaving issue. to the National Conduit and Cable Com- by duct diameters.
A dry paper-wrapped wire that carried the pany (a predecessor of the Anaconda Wire Cables for voltages as high as 380,000
life germ which developed into the present- and Cable Company) in 1891. volts are now in use.
day cable was made about 1872 by a paper It was in 1891 that the General Electric
manufacturer of Richmond, Va., named Company manufactured for the Chicago
John H. \Vortendyke, who used it for an Edison Company some Siemens-type 500- H. L. Melvin (Ebasco Services Incorporated,
electric bell system in his home. Worten- volt cable insulated with three wraps of New York, N.Y.): There is little to add to
dyke made a crude taping machine for this paper, three wraps of jute, which were dried such an excellent paper as the authors have
purpose but apparently made no attempt to and impregnated with a resinous compound, prepared. Not only does it cover the prog-
commercialize his wire. About 1883, and lead covered by a cold slug process. ress and future trends, as the title implies,
Wortendyke had in his employ one Edwin This cable was put in service in 1892 and but it also summarizes the basic stages in the
0. McCracken, who was interested in this used as a feeder to the World's Fair in 1893, history and early development of electric
wire, made further developments in the tap- and continued in operation until 1932. transmission. This has been of particular
ing machine and applied for a patent in As late as 1897 Standard Underground interest to those of us who have partici-
February 1884, which was granted as Cable Company recommended saturated pated in the problems from the early days.
Number 304,539, September 2, 1884. This fiber yarn for voltages up to 2,800 whereas I do not believe it is strictly accurate to
patent covered: "An electric wire having a paper was offered only for the lower voltages. say that "the use of protective gaps as a
covering consisting of a spirally wound and The success of Ferranti's daring installa- primary protection in substations is being
lapping strip or strips of paper composed of tion fortunately helped the cause of cables abandoned rapidly." On the contrary, on
pure vegetable fiber and applied in its un- more than that of rigid tubes for, by the time many systems the continued use of such gaps
changed fibrous condition to the wire, the the Deptford mains were installed, Mc- is made both on old and new substations.
paper forming, of itself, the insulating cover- Cracken's patent on wire insulated with However it is true that much greater use is
ing for the wvire." paper tape, then 6 years old, came to be being made of lightning arresters, as a means
At this time, in spite of voluminous noticed and people began to ask whether of preventing interruptions to service, in the
court testimony, it does not appear pos- taped cable might not be good for 3,000 volts many instances where the performance of
sible to apportion the credit for this inven- or even 6,600 volts if rigid conductors in- the lightning arresters and gaps can be co-
tion between Wortendyke and McCracken. sulated with wide sheets were good for 10, ordinated without sacrificing opportunities
McCracken, however, is the man who set 000 volts. of economies in investment.
things in motion, for he and his associates Things must have moved very rapidly be- There is one point that I believe is worth
organized and reorganized a series of un- tween 1895 and 1898 for on December 30, bringing out as a corollary to this paper.
successful companies to promote his patent: 1898, we find Alex. Dow writing as fol- Power-system stability becomes less of a
first, the Norwich Insulated Wire Company, lows in Engineering News: "Electric light problem as the system capacity increases,
of Norwich, N.Y., and finally of Harrison, practice today is about evenly divided be- and as interconnections between systems in-
N.J. tween paper insulated cables and rubber in- crease. The increased inertia and lower im-
The first impregnated paper cable having sulated cables, both lead covered." pedance which accompany added generating
helically applied paper tapes, oil impregna- The Cataract Power and Conduit Com- capacity and transmission lines should make

OCTOBIER 1952 Crary, Gross, TWagner Progress in Electric Transmission 975


system instability a very rare occurrence in rather conspicuously at the present time: which went into experimental operation in
the eastern half of the United States within 1. A nation-wide trend to 230-kv trans- 1926.
about 10 years. That this is recognized may mission superimposed on present 138-kv and The latter part of the paper gives some
be justification for the recent proposal to 115-kv systems, especially for medium-size, information about extra-high-voltage trans-
lower the short-circuit ratio on large turbine rapidly growing systems serving important mission for overhead lines here and abroad,
generators so that more kilowatt capacity power consuming areas. in service and contemplated. It might be
may be obtained for a given size frame. 2. The combined importance of both 230 mentioned that the 380-kv system in
However, power-system stability prob- kv and the higher transmission voltages in Sweden includes a small amount of high-
ably will be a problem in the western states the future power development and growth pressure, self-contained, lead-covered, oil-
for a long time because the distances be- in the United States. filled cable. Also, some oil-filled cable has
tween load centers are so great and, at the 3. A development of higher transmis- been ordered for use in the 288-kv system
present time, there is a large percentage of sion, above 230 kv, throughout the world. mentioned for the Aluminum Company of
hydroelectric power which is usually remote Canada; some of that cable will have alu-
from load centers. But, even in the west To enlarge on the report by Crary, Gross, minum as the sheath material.
where long transmission lines are necessary, and Wagner, attention may be called to the
there are an increasing number of inter- fact that the Northwest is another region of
connections between power systems. large power developments. Hydro plants S. B. Crary, I. W. Gross, and C. F. Wagner:
This brings up the second point I want to are in course of construction which involve All of the discussers have contributed to the
add in this discussion, which is: tie-line bulk transmission in each instance well up material of this paper. The discussions by
load control. With the probability of in- to 1,000,000 kw and distances from 100 to Mr. Hickernell and Mr. Del Mar and by
creasing interconnection of major areas of 250 miles. Economic studies call definitely Mr. Halperin add considerably to the his-
the United States, the use of tie line load for transmission voltages up to at least 345 torical information regarding the develop-
control will make such interconnections kv for trunk lines to transmit the bulk of ment of high-voltage cable. The inforina-
physically manageable. I believe that inter- power from the new sites of generation to the tion given is much appreciated.
connections between power systems cannot load centers of this region. Certainly power cable is an important
be discussed without comments on the prob- The next few years will see transmission element of the transmission system, and the
lems and developments in tie-line load con- voltages in the United States up to 345 kv fact that so little space was given to it in the
trol. In early work in the Northwest phase- and possibly higher in years to follow. In original paper should not be considered as
angle control was just installed to combat the interest of standardization, the transmis- either an oversight or a lack of appreciation
the stability problem which later was modi- sion voltages selected for the higher voltages by the authors of its place in the electric
fied to tie-line bias control. Bias tie-line and especially the basic insulation levels transmission system.
control seems to provide the flexibility that (BIL's) should be limited to a minimum in Mr. Melvin has questioned the accuracy
fits in with the advantages of system inter- keeping with the over-all technical and of the statement that "The use of protec-
connections. economic requirements for the future ap- tive gaps as a primary protection in sub-
In closing I would like to commend the plications. It is of paramount irnportance stations is being abandoned rapidly." Per-
authors on this paper which should stand in adjacent regions where higher voltages are haps it might have been more accurate to
as a milestone with which to make interest- considered that the same voltage be adopted have stated, "Protective gaps as primary
ing comparisons at intervals in the future. to facilitate future interconnection. protection in substations have been used to
some degree in the past, but at the present
time are not being extended appreciably."
P. L. Bellaschi (Consulting Engineer, Herman Halperin (Commonwealth Edison Mr. Melvin's comment that system sta-
Portland, Oreg.): The determining factors Company, Chicago, Ill.): The information bility becomes less of a problem as system
in the selection of higher voltages are the in this very interesting paper on electric capacity increases, and as interconnections
lower annual transmission costs and the transmission could be supplemented by the between systems increase, is, in general, cor-
greater power capability. Viewing current following additional data that applies to the rect. Also tie-line load control is a factor in
developments, we find on the one hand the section entitled "High-Voltage Cable." the present-day operation which has been
need for higher transmission capabilities The first commercial operation of 69-kv used to considerable advantage.
and the urge foi more economical transmis- cable in this country was in Cleveland in Mr. Bellaschi's presentation on the power
sion of larger bulks of power, both attain- 1924, not 1926. This was followed by the situation in the 'Northwest as relating to the
able through the use of higher voltages. On installation of such cable in 1925 in Phila- transmission system amplifies in a sense the
the other hand, technical advances in recent delphia, and in 1926 in Chicago. In con- authors' comments that we are at a stage
years now make possible greater power nection with the oil-filled cables mentioned now where the extension of extra-high-volt-
capabilities and economies at 230 kv in in the second paragraph as being put into age transmission may be considered in the
amounts required for many cases, without operation (commercial) in 1927, the first oil- pioneer state.
recourse to higher voltages. There are cer- filled cable made in this country was for the We wish to thank the discussers for their
tain trends and conclusions which stand out experimental 138-kv installation in Chicago, very pertinent remarks on the paper.

976 Crary, Gross, Wagner Progress in Electric Transmission OCTOBER 1952

You might also like