Professional Practice 3
Professional Practice 3
a. PD.1000
b. PD. 49
c. Acoustics
d. PD.344
a. Mural Paintings
b. Interior Design
c. Acoustics
d. All listed items
4. Under PD.1096 what should be the proportion of sidewalk width to that of the
road right-of-way?
a. ½
b. 1/3
c. ¼
d. 1/6
5. What code holds the architect responsible for the building structure he
designed for a certain period of time?
a. People
b. Client
c. Contractor
d. Colleagues and Subordinates
8. What type of bond guarantees payment on all obligations arising from the
contract?
a. Performance
b. Payment
c. Guarantee
d. Proposal
a. Public
b. Manufacturers/Dealers
c. Contractor
d. Client
a. Performance
b. Payment
c. Guarantee
d. Proposal
11. Under the Civil Code, under what conditions can the Contractor be held liable
for damages within fifteen years after project completion?
12. Under the owner-architect agreement, which of the following is/are included
in project construction cost?
a. Fire-fighting equipment
b. Plumbing/Electrical Fixtures
c. Elevator/Escalator
d. All listed items
13. A well written set of specifications is important to at least four actors in the
building industry. Who of the following is able to check the character and
quality of materials and workmanship during construction?
a. Construction Superintendent
b. Fabricator
c. Estimator
d. Architect
14. Which of the following is NOT included in the set of contract documents
which forms an integral part of an owner-contractor agreement?
a. Labor force
b. Drawings, plans, elevations, etc.
c. Detailed/itemized drawings
d. General conditions
a. 2.0%
b. 1.0%
c. 3.0%
d. 2.5%
a. PD.223
b. PD.1098
c. PD.474
d. PD.1081
a. Quality of Materials
b. Aesthetics
c. Construction System
d. Use and Occupancy
18. Within what period should the owner release the retention after the date of
final payment?
a. 4 months
b. 3months
c. 2months
d. 5months
19. In the architect’s range of services under which services does cost, time and
quality control of work fall?
a. Comprehensive planning
b. Design Build
c. Construction
d. Specialized Allied
20. What legal mandate obliges owner to repair or demolish dangerous or ruinous
buildings?
21. Under PD 1185, what is the maximum width (meters) of a single door in a
doorway?
a. 1.5m
b. 0.9m
c. 1.22m
d. 1.4m
a. Movable Furniture
b. Five sets of contract documents
c. Income taxes on professional fees
d. Structural/electrical/sanitary engineering
23. How many copies of drawings specifications and other contract documents are
usually given to the owner by the architect?
a. 10
b. 5
c. 7
d. 6
26. In the architect’s range of services, under which phase does site utilization and
land use fall? (PP001 & Architect’s National Code p.21)
a. Pre-Design services
b. Design services
c. Construction services
d. Specialized and allied services
27. What is the time frame for the release of the amount retained by the owner
after the date of final payment? (PP015 & CDEP handout)
a. 15 days
b. 120 days
c. 60 days
d. 3 months
28. You are hired as the architect for a 6-storey condominium project on a design-
build service with a guaranteed maximum cost of P 120 million. After
completion, the actual costs incurred for the project reached P 135 million.
Which of the following condition is TRUE: (PP007 & Architect’s National
Code p.73)
29. What do you call the outline set of specifications enumerating the type / trade
names of materials? (PP009)
a. supplementary specifications
b. breakdown of work and corresponding value
c. schedule of materials and finishes
d. brand-name specifications
31. Which organization has the power to approve, issue, limit, or cancel permits
for foreign architects who will be practicing architecture in the Philippines?
(PP076/PP090)
a. United Architects of the Philippines (UAP)
b. Integrated and Accredited Professional Organization of Architects
(IAPOA)
c. Professional Regulatory Board of Architecture (BOA)
d. Department of Labor and Employment (DOLE)
32. According to PD 223, which of the following is(are) grounds for filing a
complaint against a professional or an examinee: (CDEP p.I-1 & PD223
Art.4)
a. 4
b. 1,2 and 4
c. 1,2,3 and 4
d. None of the Above
33. Unless extended for just cause, The Board of Architecture shall submit to the
PRC the ratings obtained by each examiner within how many days/months?
a. 120 days
b. 3 months
c. 30 days
d. 2 months
34. What is the correct order of the 16 Specifications Divisions: (PP063 & CDEP
p.I-22)
35. What type of bond guarantees payment on all obligations arising from the
contract?
a. Guarantee bond
b. Proposal bond
c. Performance bond
d. Payment bond
36. Which of the following limitations in the registration of a corporation is
correct as prescribed under RA9266 Section 37? (PP081/PP100)
a. performance specifications
b. reference specifications
c. descriptive specifications
d. multi-product specifications
38. What is the condition for a bid to be automatically disqualified using the
Agency Approved Estimate (AAE) as basis?
a. 30% lower or 15% higher than AAE
b. 30% lower or 10% higher than AAE
c. 20% lower or 10% higher than AAE
d. 20% lower or 15% higher than AAE
39. What is the architect’s minimum basic fee for the design of an exhibition hall
with a project cost below P 50 million? (PP002-PP003)
40. Which of the following describes the lump sum or fixed fee method of
architect’s compensation?
a. generally used in government projects
b. all listed items
c. entails more paper work and processing of supplementary works
d. disadvantageous to both client and architect
41. How much should an architect charge if he is engaged by the owner to
perform full-time supervision as part of the architect’s construction services?
(PP005)
42. Architect XYZ proceeded to design a project with questionable legal / exigent
conditions in order not to lose the prospective commission. His action is
unethical with respect to his relation with whom? (Code of Ethical Conduct)
a. manufacturer / dealer
b. contractor
c. public / people
d. client
43. You are to design twelve (12) housing units to be constructed on a single site.
If one housing unit costs 1 million pesos, how much would you charge your
client for this particular housing project so as to conform with UAP documents
– schedule of minimum basic fees?
a. P 1,200,000
b. P 600,000
c. P 700,000
d. P 800,000
44. A method of selection most often employed by committees representing
institutions, corporations and government agencies. (Architect’s National
Code p.74)
a. direct selection
b. comparative selection
c. design competitions
d. none of the above
45. After the contract documents phase, where does the remaining 15% of the
architect’s basic fee go?
a. 10% for construction; 5% for architect’s liabilities under the Civil
Code
b. 10% for architect’s liabilities under the Civil Code; 5% for
construction
c. 7.5% for construction while 7.5% for liabilities under the Civil Code
d. 7.5% for retention while 7.5% revolving capital for construction
46. Which of the following types of specifications is impossible to combine?
(PP063)
47. This type of compensation establishes a fixed sum over and above
reimbursement for the architect’s technical time and overhead. An agreement
on the general scope of the work is necessary in order to set an equitable fee.
a. professional fee plus expenses
b. multiple of direct personnel expenses
c. per diem plus reimbursable expenses
d. lump sum or fixed fee
48. The Breakdown of Work & Corresponding Value is submitted by the
contractor within 15 days from receipt of what? (UAP Doc.301 Art.22.1 &
CDEP lecture)
a. Notice to Proceed
b. Building Permit
c. Certificate of Occupancy
d. Certificate of Payment
49. The preparations of forms for contract letting, documents for construction,
forms for invitation and instruction to bidders, and forms for bidders'
proposals falls under what phase of the architect's design services?
a. schematic design phase
b. design development phase
c. contract documents phase
d. construction phase
50. What are the components of the Project Manual? (CDEP p.I-22)
a. 30 meters
b. 60 meters
c. 50 meters
d. any distance as long as the trees/plants are inside the property line
53. An on-site office during the construction phase of the project shall be erected
with a minimum area of ____ square meters.
a. 18
b. 15
c. 12
d. 10
54. which of the following describes General Conditions in construction work?
56. How many sets of drawings and specifications will the owner furnish the
contractor free of charge?
a. 2 sets
b. 3 sets
c. 4 sets
d. 5 sets
e. 1 copy only
57. Comprehensive planning falls under what service of the architect? (Architect’s
National Code p.35 & PP004)
60. For interior design services, the architect shall be paid in the following
schedule with the corresponding percentage of the interior design fee:
(Architect’s National Code p.37, CDEP p.I-13 & PP004)
a. preliminary design – 30 % ; final design – 20 % ; completion – 50 %
b. preliminary design – 50 % ; final design – 30 % ; completion – 20 %
c. preliminary design – 50 % ; final design – 20 % ; completion – 30 %
d. preliminary design – 30 % ; final design – 50 % ; completion – 20 %
a. P 1.2 million
b. P 1,050,000
c. It is unethical to charge the owner for this type of project
d. P 9 million
63. Which of the following is a condition for the contractor to have the right to
terminate the contract
a. Bankruptcy by owner
b. Owner fails to pay any sum 15 days after arbitration
c. Architect failed to act on request for payment within 30 days
d. Owner fails to pay any sum 15 days after approved request for
payment
64. Which of the following services are expected from the architect serving as
building and grounds administrator?
a. building maintenance
b. monitoring security and janitorial services
c. evaluates the actual use of the facility and the effectiveness of the plan
d. equipment maintenance
66. All permits/licenses pertinent to construction are paid by whom? (CDEP p.I-
19)
a. Architect
b. none of the listed items
c. contractor
d. project manager
67. What do you call the study which determines the viability of a project, such as
the cost of development which brings about a potential return to the owner?
(PP001)
68. The structures below are grouped accordingly with respect to their design
complexity. Which among the groupings have examples of
buildings/structures that DOES NOT belong to the corresponding group?
(PP002-PP003 & CDEP p.I-11 to I-12)
71. No further retention shall be made on the balance of the Contract when ____
% of the Contract has been accomplished. (PP013 & PP056)
a. 98 %
b. 65 %
c. 50 %
d. 85 %
a. 50 %
b. 98 %
c. 85 %
d. 65 %
73. Which of the following describes the percentage of project cost as a method of
compensation for the architect’s services? (PP007-PP008)
74. Which of the following describes architectural programming as part of the pre-
design services of the architect? (PP001)
75. Analyze the CPM scheduling of a simple project below. Which of the
following condition(s) is(are) TRUE: (PP030 & CDEP p.I-29)
H