Professional Documents
Culture Documents
Carbon
M a n ag e m e n t
i n t h e S u pp l y C h a i n
Program for
Carbon
M a n ag e m e n t
i n t h e S u pp l y C h a i n
1 st
edition
B r a z i l i a n B u s i n e ss C o u n c i l
f o r S u s ta i n a b l e D e v e l o p m e n t ( C EB D S )
Av e n i da da s A m é r i c a s , 1 1 5 5 / s a l a 2 0 8
B a r r a d a T i j u c a – R i o d e J a n e i r o – RJ
•••
contents
Executive Summary 4
Introduction 5
Project 6
Defining par ticipant suppliers 6
Initial lists of par ticipant companies 6
Selection of the project’s 50 par ticipant suppliers 6
Awareness-raising and training 8
Subsequent individual follow-up 10
Its importance to the national reality was Strategies to forge closer relations with The two complementary approaches,
such that, today, just four years after its suppliers, and even the training of suppliers awareness-raising and training,
actual start with 27 companies, those by companies on specific matters had turned out to be relevant owing to
officially publishing their inventories have already been occurring. Some have gone the common features of the expectations
risen in number by 250% – despite the so far as to establish that in the near future held by these suppliers. The first
absence of legislation compelling or even one of the criteria for the contracting of was their possible lack of knowledge
encouraging this practice. products or services from these suppliers about climate change and its direct
will precisely be whether they take the impact on society and on business.
However, there has been an increase in inventory and control their greenhouse gas Moreover, the awareness-raising
the number of companies publishing their emissions. In line with this aim, the CEBDS seemed fundamental for these
inventories, and in their refinement. By Energy and Climate Change Thematic suppliers to manage to connect climate
investigating their sources of emissions, Chamber (CTClima), with support from change issues with the actions of their
companies obtain greater knowledge of KPMG, has proposed to concentrate these enterprises and, of course, with how
their own production process and even of individual efforts into a single task, through inventorying their emissions could
their suppliers’ production processes. In fact, the Program for Carbon Management in impact the knowledge of their own
one of the conclusions of this investigative the Supply Chain. The idea of the project business and possibly lead to efficiency
process is that depending on the type of was to bring together the largest possible gains over the course of the process.
business of the company that conducts its number of member companies’ common The complementary training element was
inventory, a major portion, or even the vast suppliers with the intent of raising their shown to be necessary, since even those
majority of its emissions do not come from awareness both of climate change and of already aware of the issues might lack the
its production processes (scope 1) or as the necessity of conducting inventories, technical outlook and specific expertise
a byproduct of the energy generated for and then training them to carry out this needed to carry out their inventories.
such processes (scope 2) but, rather, from it measurement.
supply chain (scope 3) (figure 1). The project began in late 2011 and
was concluded in May 2012, having
One of the main conclusions of this been sponsored by Vale, Votorantim,
B r a z i l’ s e m i s s i o n s
analysis is that despite any investment that Banco do Brasil and Banco Itaú.
per scope in 2010
this company makes in energy efficiency or Over 240 suppliers of the sponsors
other methods for mitigating its emissions, were initially contacted. Among the
the result will not have a major impact 2 3% most important suppliers, and those
precisely because of the considerable that were common to more than
proportion represented by its suppliers’ one company, 50 were selected
carbon footprint in the overall volume of 1% to take part in the awareness-raising
figure 1
emissions. In this sense, greater closeness and training workshops. The following
between such companies and their pages demonstrate the methodology
suppliers is indispensable – whether due to employed for the project, its main results
the possibility of more restrictive legislation 76% and conclusions, as well as the self-
regarding emissions in the future, or to criticism of those conducting the process,
the backing needed by the stakeholders an important element for the project’s
involved in the process. Scope 1 Scope 2 Scope 3 continuation and expansion.
I . M e m b e r C o m pa n i e s J o i n t h e P ro j e c t ( J u ly- D e c e m b e r 2 011)
14% 12%
50%
4 4%
IT 10 %
8%
Security IT
Consultancy Consultancy
figure 2 6% figure 5
Logistics 8% Construction
Steel and related Transport
Construction 6%
Automation
8%
Transport 6% Steel and related
Telemarketing 6% Others
6% 6%
Others 4% 6%
S u p p l i e r s p e r s tat e S u p p l i e r s p e r s tat e
(group recommended by ( pa rt i c i pa n t s o n ly )
the participant companies)
2%
2% 1% 4% 2%
4% 4%
São Paulo 5% 4% São Paulo
42%
Minas Gerais 6% Minas Gerais
8%
Rio de Janeiro Rio de Janeiro
Federal District Federal District
figure 3 8% figure 6
Paraná 51% Paraná
10 %
Santa Catarina Santa Catarina
Bahia 8% Bahia
Rio Grande do Sul Goiás
Others 17% Pernambuco
2 2%
II . Awar e n e s s - r a i s i ng an d tr a i n i ng
19 %
33%
38%
Absence
of need
figure 7 Technical figure 8
difficulty
Lack of
interest
figure 8
20 6%
18 13%
16
14
12
10
figu re 10
8
6
Yes
4
No
2
Doesn’t know 81%
0
III . S u b s eq u e nt i n di v i d ua l f o llow- u p
During the last stage of the project, KPMG on (whether the inventory was for the
maintained a continuous follow-up process whole company or just for those areas that
with the companies that attended the supplied to the participant companies),
workshop and/or answered the subsequent the version of the tool employed (it was
questionnaire. The companies were updated twice in 2012) or the sources of
accompanied over the course of their internal emissions considered. In short, these are
processes, asked for assistance on particular tasks meant to round off the information
questions and consolidated their inventories. already presented and follow up that yet to
be presented.
At the time of the last survey (August
2012), 22 companies had presented a full The number of companies that said they
(15) or partial (7) emissions inventory, were mobilizing to conduct their inventory
which means 91% of the total number of fell slightly (to 77%) in comparison with
suppliers who at the end of the workshops the previous survey, while the number
said they were willing to conduct of companies still unsure rose to 10%
91% of the total
inventories, and 69% of the total number (figure 12). This may be a reflection of a
number of suppliers
of participants. The remainder (12) have detachment between companies’ technical/
who at the end of
the workshops said not yet set a date or did not answer this managerial teams (the workshop’s target
they were willing to question (figure 11). audience) and decision-makers – thus
conduct inventories, demonstrating the possible necessity of
and 69% of the total Of the inventories received, KPMG working with staff further up the hierarchy
number of participants checks items such as the scope worked of these suppliers as well.
13%
31%
10 %
f i g u r e 11 47% f i g u r e 12 71%
6%
2 2%
Yes
Handed in Already had an inventory
In progress Still under discussion
Not conducted at the company
No
The second positive outcome is the sector of activity, size (and choice of the up the inventory-taking process on a
possibility of replicating, expanding and criterion for defining size, whether by regular basis. A relevant fact detected
continuing the project over the next revenue of by number of employees) was the extra interest displayed by
few years. As previously spelt out, even and whether inventories are already suppliers whose client companies
though the project is prone to criticism taken. In this respect, it is necessary that already have contractual demands in
and must be further perfected, its those conducting the project (CEBDS place relating to the presentation of
main focus – the training of a diverse and KPMG) have a more in-depth inventories.
and highly representative group of dialogue with participant companies’
suppliers, preferably common suppliers, purchase areas and suppliers, as well as Another point for improvement, so
of the participant companies – has been an enhanced internal dialogue at these far not touched upon in this report,
approved. And this can and should be companies, with a view to reducing is following up the destination of
replicated and continued in future rounds. possible communication problems. the inventories conducted. When
the project was initially conceived,
However, the criticism must not be On the other hand, both the participant it included the idea of a possible
relegated. A series of points will have companies and those conducting the publication of the inventories in Brazil’s
to be improved for the take-up rate project must establish even closer public registry of emissions, of the
of the project to grow satisfactorily. contact with the participant suppliers; GHG Protocol Brazilian Program. The
An initial point, for instance, is a more the former, by encouraging their scope for this later diminished, which
intense dialogue prior to the project participation, for instance, by means of a made this follow-up impossible. The
within participant companies, so as specific invitation to all points of contact, suppliers were then informed that the
to select not just the most strategic thus formalizing and legitimating the call inventories would be forwarded to their
suppliers but mainly those with a higher for them to take part in the project even client companies. We note that the
share of the total scope 3 volume – more. The latter, for their part, furnished publication of the inventories should
something that hardly took place in with ample information about these be studied in future rounds of the
this, the first project. Another point to suppliers – specifically, with a constant program, so that these emissions may
work on relates to the standardization point of contact – must do their best be made public (and on an annual basis)
of the information requested about to coordinate and ensure that all are and that the Brazilian database on the
these suppliers: data such as location, present at the workshops and to follow subject may grow.
c eb ds
Project coordinator
Fernando Malta
C TC l i m a
President
David Canassa (Votorantim)
Vice-President
Vivian Macknight (Vale)
K P MG
Project Manager
Ricardo Zibas
Consultants
Mariane Sá
Paula da Silva Carvalho
Realization
Participating companies
Support
D i s c l a i m e r : This report was published in the name of CEBDS. Even though the companies belonging to CTClima,
the participant companies, their suppliers and KPMG took an active part in the ongoing formulation and conduct
of the project, any and every opinion expressed here is restricted to the positioning of CEBDS.