Professional Documents
Culture Documents
METHODOLOGY FOR
BITUMINOUS CONCRETE
___________________________________________________________________________________
1
PUNJ LLOYD LIMITED
EAST WEST CORRIDOR PROJECT AS-4 (PFIN06)
(Km. 1121.00 to Km. 1093.00 of NH-31)
___________________________________________________________________________________
1. Name of activity:
Bituminous Concrete
2. Activity No. :
BOQ Item no. 4.09
3. Description of Activity:
Providing and Laying Bituminous Concrete wearing course using crumbed rubber modified
bitumen complete as per Technical Specifications
4. References:
c) Ref. to Drawing(s):
c.1) Approved Good For Construction Drawings
d) Ref. to relevant clauses of the conditions of the contract (Part-I & Part-II) or otherwise,
if any :
Nil
2
5. Construction Method:
Manpower
for approval. The materials shall be Supervisor. 01
Task-1 -NA- -NA-
collected directly from the Surveyor. 01
stockyard / storage tank and shall be Assistant
checked for various physical surveyor. 01
requirements. Material
Engineer. 01
Batch type Hot Mix Plant of 160T / HMP. 01 160 TPH
hr. capacity shall be installed at Paver. 01 11 m
Camp and shall be used for width
Equipment
3
The finish surface shall be jointly
checked with consultant by recording
the levels of the finished surface and
Task-6 comparing them with desired wet
mix level. The compaction achieved
in the field shall be checked either by
Sand Replacement Method or
Nuclear Density Gauge.
Cores shall be taken from the work
executed with Asphalt Core cutting
machine and all necessary tests shall
Task-7
be conducted to check conformance
of the work done with technical
specifications.
The newly laid surface shall be
opened to traffic until and unless the
Task-8 temperature of mix has reached
ambient temperature or after 24
Hours, whichever is earlier.
a) Caution Boards shall be placed at the beginning and end of working site and also at
risky locations.
b) Barricading tape will be placed along the paving surface
c) Signal man will be placed at heavy traffic locations at the time of Execution.
d) Reflective sign boards will be placed during night near risky locations.
e) Hot Mix plant shall be kept in good condition to minimize pollution.
f) All necessary measures shall be taken to maintain all plants and silencing equipments
in good conditions so as to maintain air and noise emission during the operation.
g) All necessary measures shall be taken to control the disposal of all forms of waste
generated by the construction operations and in all associated activities.
h) All necessary measures and precautions shall be taken to avoid any nuisance or
disturbance arising from the execution of the work.
a) The manpower & machinery proposed is indicative only. The requisite qty. of
resources may vary based upon site condition.
b) Any modification in execution of activity shall be done with prior information with
consultant.