Professional Documents
Culture Documents
3
What to do with multiple streams?
T
55
TPA
6 Feed
Residue
1 LP steam
MPA HGO BPA
KERO
6 MPA
LGO TPA
1 LP steam KERO
BPA
LGO Overheads
6
1 LP steam
HGO DH
7 • Many different ways of coupling the
6 hot and cold streams
• Is there an optimal way of exchanging
Residue heat?
4
Heat Exchanger Network Representation
5
Conventional Process Flowsheet
Simple questions:
1. Where is the Pinch?
2. What is the degree
of heat recovery?
3. How much utilities
are used?
6
HEN representations
A little better:
• Only heat transfer operations
• Simple representation
− Cold streams horizontal
− Hot streams vertical
BUT
• The Pinch is possible to mark
but still difficult to see
• Problem with sequencing
heat exchangers
• Temperature representation
unclear 7
HEN representations
Swapping the positions of E3 and E4
H H
1 E1 E2 C 1 E1 E2 C
2 E3 E4 2 E4 E3
3 4 3 4
HOT 2 C
COLD 1
COLD 2
MP Steam
HOT 1
HOT 2 C
COLD 1
COLD 2
CW
Alternatively, cold utilities can appear at the top and hot utilities at the bottom
10
Constructing a Grid Diagram
• Hot streams run left to right
11
Showing the Pinch
HOT 1
HOT 2 C
COLD 1
COLD 2
PINCH
12
Pinch Implications
Allowed Not allowed
13
Moving Heat Exchangers
Conventional HEN flowsheet The Grid Diagram
1 E1 E2 C
2 E3 E4
14
Rules for HEN Design
Rules so far:
15
HEN Design Procedure
16
A four-stream heat recovery problem
Stream data
Δ𝑇𝑚𝑖𝑛 = 10°C
17
A four-stream heat recovery problem
The Grid Diagram
CP
kW/°C
250° 40°
2 15
200° 80°
4 25
180° 20°
1 20
230° 140°
3 30
18
Hot and Cold Composite Curves
Δ𝑇𝑚𝑖𝑛 = 10°C
280
240
200
Pinch
Temperature (°C)
160
80
40
𝑄𝑟𝑒𝑐 = 5150 kW
0
0 1000 2000 3000 4000 5000 6000 7000 8000
Heat Flow (kW)
𝑄𝐶𝑚𝑖𝑛 = 1000 kW 𝑄𝐻𝑚𝑖𝑛 = 750 kW
200° 80°
4 25
180° 20°
1 20
230° 140°
3 30
20
Divide at the Pinch
The Grid Diagram
CP
PINCH
kW/°C
250° 150° 40°
2 15
230° 140°
3 30
21
Pinch Design Principle
𝑇
PINCH
PINCH 𝑇 PINCH
CP
kW/°C 4
250° 150°
2 15
Δ𝑇𝑚𝑖𝑛
200° 150°
4 25
1
HEAT EXCHANGER MATCH
180° 140°
1 20 𝐻
23
Design Above the Pinch (contd.)
However, if at the pinch CPH ≤ CPC …
PINCH 𝑇 PINCH
CP
kW/°C 4
250° 150°
2 15
Δ𝑇𝑚𝑖𝑛
200° 150°
4 25
3
HEAT EXCHANGER MATCH
180° 140°
1 20 𝐻
24
Design Below the Pinch
If at the pinch CPH < CPC …
PINCH 𝑇 PINCH
CP
kW/°C 2
150° 40° Δ𝑇𝑚𝑖𝑛
2 15 1
150° 80°
4 25
140° 20°
1 20 𝐻
The match is
INFEASIBLE!
25
Design Below the Pinch (contd.)
However, if at the pinch CPH ≥ CPC …
PINCH 𝑇 PINCH
CP
kW/°C 4
150° 40° Δ𝑇𝑚𝑖𝑛
2 15 1
150° 80°
4 25
140° 20°
1 20
26
CP Tables. Essential matches at Pinch
A) Above the Pinch B) Below the Pinch
CP CP
PINCH PINCH
kW/°C kW/°C
250° 150° 150° 40°
15 2 2 15
230° 140°
30 3 27
Sizing the Matches
CP
PINCH
kW/°C
250° 150°
15 2
200° 150°
25 4
180° 140°
20 1
230° ? 140°
30 3
?
Having identified feasible matches,
how big should we make them?
28
Tick-off Heuristic (Above the Pinch)
CP 𝑄𝑆𝑇𝑅𝐸𝐴𝑀
PINCH
kW/°C kW
250° 203.3° 150°
15 2 1500 700
25 4
200° ✓ 150°
1250 0
20
180° ✓ 140°
1 800 0
800 kW
230° 181.7° 140°
30 3 2700 1450
1250 kW
1. Maximise loads to "tick off" streams starting from the pinch and
moving away (keeps capital costs down)
2. Update temperatures of unsatisfied streams
29
Fill in the Rest
CP Place non-essential matches 𝑄𝑆𝑇𝑅𝐸𝐴𝑀
PINCH
kW/°C kW
15 2
250° ✓ 203.3° 150°
1500 700 0
25 4
200° ✓ 150°
1250 0
20
180° ✓ 140°
1 800 0
800 kW
30
✓ 230°
H
205° 181.7° 140°
3 2700 1450 750 0
2
150° 106.7°
C
✓ 40°
15 1650 1000 0
1000 kW
4
150° ✓ 80°
25 1750 0
1750 kW 650 kW
1. Maximise loads to "tick off" streams starting from the pinch and
moving away (keeps capital costs down)
2. Update temperatures of unsatisfied streams
3. Process-to-process heat transfer is no longer possible, place utilities
31
Below the Pinch
CPH ≥ CPC Note: this match violates CP rules!
CP 𝑄𝑆𝑇𝑅𝐸𝐴𝑀
PINCH
kW/°C kW
2
150° 106.7°
C
✓ 40°
15 1650
1000 kW
4
150° ✓ 80°
25 1750
1750 kW 650 kW
34