Project: Drone to Home Delivery Early Early


Duration
Revision No.: 0 Start Finish
Activity name and number Critical Path
Revision Date: 03/05/2021 Total Late
Late Start
Slack Finish
9 2 11 11 3 14
6 3 9 1.2.6 – Risk 1.2.2 – Budget
Management Plan estimate
1.2.1 – Schedule
0 4 4 16 7 18 18 7 21
development
1.1.2 – Engage
Stakeholders 13 7 16
2 2 6 11 3 14 14 4 18
1.5.1 – Flight Path 1.5.2 – Flight path
0 6 6 6 0 6 Engineering testing
0 0 0 6 5 11
1.1.1 – Develop Milestone – 14 3 17 17 3 21
Start 1.3.1 – Drone
Scope and Plan End Initiating
0 0 0 changes design
0 0 6 6 0 6 11 3 14 14 8 22
6 0 11
1.3.2 – Purchase 1.3.3 – Custom
0 3 3 6 3 9 materials drones structure
1.1.3 – Communication 1.2.5 – Processes 11 0 14 14 0 22
Management Plan design
3 3 6 19 13 22
6 4 10 10 4 14
14 3.5 17.5
1.4.1 – Systems 1.4.2 – Specialized
1.4.3 – Custom
changesdesign Customer order interface
Equations Management Reporting
11.5 5.5 15.5 15.5 5.5 19.5 Interface
Total Slack = TS = LF - EF = LS – ES 19.5 5.5 23
EF = ES+Dur.
LS=LF-Dur.
14 4 18 18 0 18
1.2.3 – Legal Contract Milestone –
Negotiations Contract assigned 28 0 28
21 7 25 25 7 25 Finish
28 0 28

18 2 20
1.5.3 – Pharmacy 22 2 24 24 0 24 25 2 27 27 1 28
manager drone 1.5.4 – Customization Milestone – End Flight 1.6.1 – Final 1.6.2 – Closing
operations of Flight Processing operations implementation out theproject
procedures 23 1 25 25 1 25 25 0 27 27 0 28
21 3 2
3
22 3 25
1.3.4 – Drone 25 0 25
maintenance Milestone – End
procedures Adapted drones
22 0 25 25 0 25

17.5 0 17.5
Milestone – EndIT
and App interfaces
23 5.5 23