Professional Documents
Culture Documents
net/publication/267607334
CITATIONS READS
2 1,412
4 authors, including:
Kazuo Miura
The University of Tokyo
36 PUBLICATIONS 108 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
Energia Geotérmica – Alternativas tecnológicas para a implantação de geração de energia elétrica geotermal híbrida no Brasil a partir de fontes de baixa temperatura
View project
All content following this page was uploaded by José Ricardo Pelaquim Mendes on 23 October 2015.
OMAE2013-10554
MODEL DESCRIPTION
This study considered the installation of a BOP under a
water depth of 2050 m by a dynamically positioned semi-
submersible drilling vessel. Riser response was calculated for
eight different moments during this operation, comprising riser
lengths varying from 250 m to 2000 m.
Figure 1 shows schematically the suspended riser under the
incidence of waves and current in the same plane. On the
bottom of Figure 1 is pictured the coordinate system adopted
for this study.
Tables 1 summarize the main data for the riser system and
the Table 2 data for other components of the riser. Table 3
describes riser configurations in the present study.
0 0 0 0
-2 0 2 4 -2 0 2 0 2000 4000 6000 100 200 300
x [m] z [m] Axial Force [kN] VM stress [MPa]
Figure 5 – Envelopes for displacements in x and z Figure 7 – Envelopes for axial force and von Mises stress
direction 1000 m riser length, Tz = 13 s, Hs = 5 m 1000 m riser length, Tz = 13 s, Hs = 5 m
Figure 6 shows the envelopes of rotation and bending Figures 8 to 10 show numerical simulation results for the
moment in the xz plane, for the 1000 m length riser. Throughout 2000 m length riser. To reach this riser configuration from the
the analysis the riser, in its entire length, was subjected to 1000 m length riser, riser joints with attached buoyancy
rotations between negative 0.7 degrees and positive 0.75 modules were lowered for 1000 m. The riser response for this
degrees. Furthermore, the bending moment is very small for condition is almost the same as found for the previous 1000 m
almost the entirety of riser length, but it increases abruptly near length riser. However, from the Fig. 10 it is observed that the
the riser top due to the connection with the spider-gimble at the effects of riser joints with buoyancy modules over 1000 m
platform. added to 1000 m bare riser joints of the previous case is very
Figure 7 show s the envelopes of axial force and von Mises small. If the yield strength for the steel riser joint as in Table 1
stress, for the 1000 m length riser. The shape of the von Mises is taken, and observing the allowable von Mises stress [API,
stress envelope follows the axial force envelope variation along 1993], it indicates that for the sea state considered running of
the riser length, showing the importance of the axial force the riser should have been suspended even before riser string
contribution to stresses. Exception is observed around the top of length reached 1000 meters.
1500 1500
1000 1000
500 500
0 0
-0.5 0 0.5 1 -600-400-200 0 200
Rotation [degrees] My [kNm]
Figure 9 – Envelopes for rotation and bending moment in
XZ plane - 2000 m riser length, Tz = 13 s, Hs = 5 m
2000 2000
Height above seabed [m]
Height above seabed [m]
CONCLUSIONS
Dynamic behavior of a drilling riser has been evaluated
during installation of wellhead equipment. A particular
installation procedure is taken when the riser with a BOP is
suspended by a spider at the floating drilling platform. Then, a
hang-off riser condition with it connected to a BOP stack is
considered, and excitation from the sea current, waves and riser
top displacements induced by sea surface vessel motions are
taken. Numerical simulations have been performed for a drilling
riser in approximate water depth of 2000 m.
Several riser configurations, representing distinct instants
during riser deployment, were evaluated, in order to delimit
maximum allowable environmental conditions throughout the
equipment installation operation. The criterion adopted to
assess operation feasibility was maximum von Mises stress
Figure 13 – Maximum allowable environmental
along riser. For all the numerical simulations, the top region of
conditions for several riser configurations (lengths in
the riser was identified as the critical region, where stresses
meters)
were higher.
The maximum environmental conditions were presented on
The observed tendency reverts when riser length reaches
operational charts that correlate the criterion adopted with
1750 m. For this length and larger lengths maximum allowable
environmental loading and vessel response. From the charts
environmental conditions increase a little. This shows the non
Abbreviations
BOP Blowout Preventer
RAO Response Amplitude Operator
ACKNOWLEDGMENTS
The authors would like to thank Capes for supporting the
present study with a scholarship, and Petrobras for the
continuous support of our research.