You are on page 1of 3

CBM FIELD DEVELOPMENT PROJECT

TEST REPORT FOR SOLO RUN TEST FOR


MOTORS

Owner : Reliance Industries Ltd Sheet


Contractor : L&T Hydrocarbon Engineering Limited

Date of Testing :
AC MOTOR CHECKOUT/NAMEPLATE DATA
Motor Tested

Serial Number: Type:

KW: Phase:
Voltage Rating: Frequency:

Current Rating: Class:

Motor Speed:
Manufacturer:

1. MECHANICAL PREPARATION/CHECKS CHECK


1. Motor Bearings are greased. OK
2. Conduit and cable work complete. OK
3. Turn the motor/fan by hand and check for rubs. OK
4. Motor GROUNDING is done OK
5. Cable terminal block is sealed with compound filling material OK

2. ELECTRICAL TEST PROCEDURES.


1. Lock main circuit breaker in the OFF position. (Door open) OK
2. Check for loose wires or damaged components. OK
3. From the MCC, Megger the motor from phase to phase and phase to ground OK
4. Measure the resistance between motor phases. OK
5. Check the rating of the overload and set to rated full load current of the motor. OK
6. Unlock the circuit breaker, switch the selector switch to OFF and close the breaker. OK
7. Bump test the motor by switching selector to HAND, and verify correct rotation. OK
8. When the rotation is correct run the motor and record current. OK
9. Run for 4 hours and record the temperature, vibration levels, voltage and current. OK
10. Switch off and lock out motor after test. OK
Motor winding resistance:
REF Resistance Value Inductance
U1 - U2
V1 - V2
W1 - W2
Motor Insulation resistance:
REF Resistance Value
R-Y

Testing Engineer L&T RIL(Projects) RIL(O&M)


Name:
Designation:
Signature & Date:
Format No :LT/RIL/CBM/ELEC/ITP/016 Page No: 1 of 3
CBM FIELD DEVELOPMENT PROJECT
TEST REPORT FOR SOLO RUN TEST FOR
MOTORS

Owner : Reliance Industries Ltd Sheet


Contractor : L&T Hydrocarbon Engineering Limited

R-B
Y-B
R - Earth
Y - Earth
B - Earth

Direction of Rotation: ________________________________________________

RUN TEST RESULTS


Parameters/Tim START 30 MIN 60 MIN 90 MIN 120 MIN 150 MIN 180 MIN 210 MIN 240 MIN
e

R                
CURRENT
PHASE

Y                
B                
R-Y                
VOLTAGE
PHASE

Y-B                
 
B-R              
RPM
 

               
TEMPERATURE

NDE
               
               
DE
               
AMBIENT TEMP
               
WINDING TEMP                

*For motors with VFD, RPM of motor as per VFD output also shall be measured and recorded separately.

Details of test equipment’s used: SAMPLE


IR Tester

Testing Engineer L&T RIL(Projects) RIL(O&M)


Name:
Designation:
Signature & Date:
Format No :LT/RIL/CBM/ELEC/ITP/016 Page No: 2 of 3
CBM FIELD DEVELOPMENT PROJECT
TEST REPORT FOR SOLO RUN TEST FOR
MOTORS

Owner : Reliance Industries Ltd Sheet


Contractor : L&T Hydrocarbon Engineering Limited

Make: ……… Range: ……..V Sl. No: ……….. Cal due Date:
……….

Clamp meter

Make: ……… Range: ……..V Sl. No: ……….. Cal due Date:
……….

Thermometer

Make: ……… Range: ……..V Sl. No: ……….. Cal due Date:
……….

Digital Multi meter

Make: ……… Range: ……..V Sl. No: ……….. Cal due Date:
……….

Micro ohm meter

Make: ……… Range: ……..V Sl. No: ……….. Cal due Date:
……….

Digital tachometer

Make: ……… Range: ……..V Sl. No: ……….. Cal due Date:
……….

*all testing equipment details shall be added at time of preparation of final reports and
reports to be attached

Testing Engineer L&T RIL(Projects) RIL(O&M)


Name:
Designation:
Signature & Date:
Format No :LT/RIL/CBM/ELEC/ITP/016 Page No: 3 of 3