You are on page 1of 4

Proceedings of Indian Geotechnical Conference

December 13-15, 2012, Delhi (Paper No.B219)

Investigations, Design and Execution of Soil Nailing Under Varied Geotechnical Environment

S.B. Suri, Chief Consultant, AECS Engineering & Geotechnical Services Pvt. Ltd., Noida, sbsuri@aecs.co
Nakul Dev, Senior Consultant, AECS Engineering & Geotechnical Services Pvt. Ltd., Noida, enndev@aecs.co
Thomas Joseph, GM (Technical), AECS Engineering & Geotechnical Services Pvt. Ltd., Noida, thomasj@aecs.co
Sanjeev Trehan, Senior Manager, AECS Engineering & Geotechnical Services Pvt. Ltd., Noida, strehan@aecs.co

ABSTRACT: Soil Nailing Technique is gaining popularity for stabilizing insitu natural & steep cut slopes. It is increasingly being
employed in urban environment for protection of underground structures like multilevel basements, underground parking lots &
shopping malls. Soil nailing involves investigations for soil parameters, analysis of slope using geotechnical software with input
parameters determined during field & laboratory investigations to determine a factor of safety and execution of soil nailing
technique using details such as diameter, spacing & length of nails obtained in analysis. Anchoring with wire mesh and shotcreting
for facial treatment/aesthetics is also often resorted to. This paper presents case histories of 3 Nos. projects wherein AECS
Engineering & Geotechnical Services Pvt. Ltd. (AECS) was associated with investigations, design & analysis and installation of
nails in one project, while in the other two projects, only investigations & execution of the soil nailing system were the
responsibility of AECS. These projects were located in different regions of the country and had varied geotechnical settings in
terms of soil type, shear strength parameters and pull out strength. Detailed methodology, analysis and steps for installation of nails
have been presented for each of the presented case studies. Based on experience gained in investigations, design, analysis and
installation, points needing special attention are enumerated.
.

INTRODUCTION
Soil nailing consists of reinforcing the soil mass by introducing
a series of thin elements called ‘Nails’ to resist tension, bending ANALYSIS & DESIGN
and shear forces. The reinforcing elements are made of round First of all, stability of an unsupported slope is checked by
cross-section steel bars called Nails which are installed sub- evaluating the factor of safety of the unreinforced slope,
horizontally and are either driven or grouted in pre-bored holes. wherein a large number (of the order of 10000 slip circles) are
analysed using the Bishop’s simplified method. The factor of
Soil nailing technique has been used for stabilising both insitu safety value of less than 1.00 indicates that the slope is in an
natural and steep cut slopes. In urban areas, this technique is unstable condition and needs to be designed for stability.
also used to construct temporary or permanent retaining
structures to support the ground close to neighbouring The design of the reinforced slope consists of determining the
structures that is sensitive to deform, for protection of factor of safety of the slope for various combinations of support
underground structures like multi level basements, underground systems to ensure adequate factor of safety and to find an
parking lots, malls and other commercial & residential high rise optimized solution. The tensile capacity of the driven/grouted
buildings and has proved to be a suitable & economical option. nails is assumed to be adequate enough so that component
It is reported in the literature that this technique can save about failure does not occur. The parameters for driven/grouted nails
10% to 30 % of the cost as compared to other retaining which are variable in the design process are:
structures [1&2]. AECS experience supports this statement. 1. Spacing of the nails
2. Length of the nails
INVESTIGATIONS 3. Inclination of the nails from the horizontal
Prerequisite for undertaking analysis of slope to be stabilized is Use of commercial software was made in the case studies
determination of the index & engineering properties of soil. presented below for analyzing the unreinforced as well as
Besides, co-efficient of friction between nail and surrounding reinforced slopes.
soil (driven nails) or between grout and soil (grouted nails) is
required. A comprehensive soil investigations programme is INSTALLATION OF NAILS
planned to obtain the required parameters and/or adopted from General Arrangement of Nailing System
available soil report. To determine the coefficient of friction, General arrangement for stabilization of the slope of excavation
pull out tests are performed in the slope cut to a desired angle using soil nailing technique with driven/grouted nails comprises
with the horizontal. of:
S.B. Suri, Nakul Dev, Thomas Joseph & Sanjeev Trehan

 Soil nailing normally starts from the top of the slope and
gradually proceeds towards bottom of the slope in stages. The project site is located on Golf link extension road of Sector
Each stage is normally between 1.5m to 2.0 m deep. - 62, Gurgaon (Haryana). The proposed site was excavated with
 Shotcrete (of adequate thickness) is applied on any layer the help of heavy duty excavating machines in stages. The
comprising of loose debris (normally removed) all along water table was encountered at about 5m depth from the
the periphery of the area to be stabilized in case the loose existing ground level. Since the water table was encountered at
debris is to be left in place. shallow depth, numerous pumps were installed for dewatering
 Face of the excavation to the designed slope is made for a the entire area.
width of 10 m and a bench wide enough to accommodate
driving hammer at the bottom at each stage. On completion Investigations
of nailing of first full length of an excavated face in the 6 Nos. pull out tests were conducted on the cut slope at
same plane, next stage is excavated and nailed. The different elevations. Tests were performed in accordance with
process is repeated till the bottom of proposed excavation Indian Standard Code [4]. A special Central Hole Jack in which
is reached. Completion process shall include nailing, fixing ram has a central hole throughout the height of the jack was
of steel mesh and welding/bolting of bearing plates to each employed. To perform these tests, suitable scaffolding
nail. arrangements were made for installation of these nails. The test
 The driven nails as per nailing scheme for stabilization of results were used to find out apparent coefficient of friction or
cut slope are installed with a ‘Pneumatic Hammer- Head’ actual pull out strength of the nail which was used in the design
without prior boring to accommodate the nail upto desired of the soil nail system.
length. The nail is driven at an angle of 10-15 degree to the
horizontal [1]. Design & Analysis
 Based on above procedure, the calculated number of top The design of the soil nailing system was carried out using
layers of ‘Driven Nails’ of given length and specified SLIDE software first for unreinforced section which gave a
diameter at designed spacing both in vertical & horizontal Factor of Safety (FOS) of 0.7. Therefore, grouted nails
directions as per approved design are installed. consisting of slotted GI pipes with a diameter of 50 mm with
 Fixing of steel mesh of designed gauge with specified suitable subsurface drainage system was considered which gave
opening size to protect the surface erosion. optimum FOS of 1.26. For analysis, it is assumed that the
 Fixing bearing plates of as per design (say 200x200x6 mm) grouted nails will be having an effective diameter of 100 mm
to each nail. (an increase in the diameter by 25 mm has been assumed due to
the grout percolating in the adjoining soil).The input parameters
 Finishing with shotcrete of suitable proportions & adequate
adopted in design are as follows:
thickness for surface protection Shotcrete provides a
Unit Weight = 16.2 kN/m3, Pullout strength – adhesion = 5
continuous supporting layer over the excavated face that
kN/m, Pullout strength – friction angle = 30°, Bond length =
can also serve to fill voids and cracks on the excavated
100%, Shear strength model – Linear.
face [3].
Fig. 1 depicts simulated excavation profile. Factors of Safety
(FOS) for reinforced section are indicated in Fig. 2. Provision
CASE STUDIES OF SOIL NAILING
of 50 mm dia. and 10.0 m long grouted nails (GI slotted pipes)
Case Study 1: Slope Stabilisation of Foundation Excavation
installed at an inclination of 15° from the horizontal (downward
at the ‘GYS Vision’ Site
direction) with 2.0 m c/c spacing (both in-plane and out-plane)
stabilizes the excavated cut-slope of 16.5 m height and 11.0 m
Background & Project Details
width and 1H : 1.5V slope was found to be satisfactory.
M/s Dignity Buildcon Pvt. Ltd is constructing a high rise
Additionally, a sub surface drainage system was also installed.
commercial complex in Sector – 62, Gurgaon. During
Need for diversion of Nallah water was emphasized. In this
excavation of the foundation, a localized slope failure occurred
project, investigations, design & analysis as well as execution
on the slopes of western & eastern faces. It was observed that
of the designed soil nailing system were carried out by AECS.
seepage of effluent from a close by surface sewage drain
(Nallah) running parallel to the excavated area was charging
into the sub-soil mass. This, along with high water table
condition, was causing instability of the slope.

To stabilize the affected slope surface of about 500m 2 and some


similar patches of the failure on the excavated face just on the
opposite side of the slide on the nallah side, Soil Nailing
Technique was employed.
S.B. Suri, Nakul Dev, Thomas Joseph & Sanjeev Trehan
on field & laboratory soil testing got conducted by the client,
the use of soil nailing for stabilization of the soil was selected.

Investigations
The investigations comprised of collection & testing of soil
samples from the embankment for use in design. One borehole
upto a depth of 6.0m was drilled from the top of the
embankment. Only disturbed samples were used to ascertain
the soil strata because of difficulty in obtaining undisturbed
samples. The tested soil was classified as sand with bulk
density of fill soil as 17kN/m3 and shear strength parameters c
(cohesion intercept) as 0 kPa and angle of shearing resistance
(φ) as 290. These parameters were adopted for design.

Fig. 1: Simulated Excavation Profile Besides, 6 Nos. pull out tests were conducted on 32mm &
28mm dia. driven nails of different lengths and 89mm dia.
perforated pipe nails with perforations 12mm@50mm c/c in
staggered manner to determine the apparent coefficient of
friction between insitu soil and nails both for grouted and
driven nails. Values of 9.0kN/m and 4.0kN/m were considered
for design of grouted and driven nails respectively.

Design & Analysis


Based on design of soil nail system, a system of grouted &
driven nails was considered. The input parameters considered
in design were as below:
Geometry of the Cut Slope: The batter of the soil mass-83.16 0
with the horizontal; the depth of overburden soil (rail top level)
above the box=1m; the height of parapet wall=0.7m.
Load Parameters: External loading (due to railway track)
including ballast-110kN/m per track as per suggestion of
Fig. 2: Factor of safety contours for the reinforced slope
railway authorities.
(effective drainage system)
Fill Soil Properties: Cohesion, c=0 kN/m 2, angle of shearing
resistance, φ=290, bulk density of fill soil=17kN/m2.
Case Study 2: Stabilisation of Vertical Slopes for
Pull out Strength: Grouted Nail=9.0kN/m, Driven
Construction of Road Under Bridge at West End of Old
nail=4.0kN/m.
Yamuna Bridge No. 249, Delhi Shahdara Section
Length of driven nails varied according to their location as per
design & details of length, diameter, spacing of nails required
Background & Project Details
for stabilizing the cut face at RUB location is presented in
Delhi PWD constructed a Bypass ring road from Salimgarh
Table 1. It is worthwhile mentioning here that at no stage of
Fort to Velodrome road as a part of Commonwealth Games
the nailing operations, the running of the trains on the railway
2010 works. A road under bridge (RUB) consisting of 3 RCC
tracks above was stopped; however, the speed was reduced to
boxes was proposed under a railway track. RUB was proposed
about half the normal speed. In this project, pull out tests &
at a location where rail level (RL 214.06) is about 6.00m above
execution of the soil nailing system were handled by AECS.
Natural Ground Level (208.46m) and the rail embankment is
contained between two long rubble stone masonry retaining
Table 1: Proposed Nailing Scheme of Stabilizing Cut Slope
walls. The said RUB was constructed by box pushing Depth Origi
Spacing (m)
technique. The precast box segments were required to be Dia. Effective
Typ from nal
pushed in highly unstable cohesionless sandy soil strata. The of Length
e of Rail Leng
rubble masonry retaining walls on reception & exit ends of the Nail Vert. Hor. of Nail
Nail Top th of
(mm) (m)
box were required to be dismantled which would expose earth (m) Nail
face of more than 8.0m height prone to collapse. This First row of Grouted nails deleted
cohesionless soil strata was required to be stabilized using 100** Gro 1.3 0.3 0.5 15 15
suitable techniques before starting pushing operations. Based uted
S.B. Suri, Nakul Dev, Thomas Joseph & Sanjeev Trehan
32** Dri 1.55 0.3 0.4 15 15 Horizontal & vertical spacing of nails=2.0m, length of
32* ven 2.3 0.2 0.3 15 15 nail=6.5m, diameter of nail=25mm, material of nail=tor steel,
32 Nail 2.6- 0.3 0.3 8 8.3 method of nailing=drilled & grouted, inclination of nail with
s 3.6 horizontal=100, Facial Material=shotcreting reinforced with one
28 3.6- 0.4 0.3 6 6.3 layer of 3mm, 75mm c/c mesh & thickness of 100mm. About
9.0 800 sq. m area was stabilized.
**These nails should be grouted to another side of the retaining Weep/drainage holes were provided through the finished slope.
wall; * indicates the nail comes under box top cover. Nails Drainage holes were constructed with perforated 75mm, 5m
should be cut at regular intervals during box pushing. long GI pipes. It was stressed that there should be no leakage
from sewage containing pipes laid on the stabilised slope as the
Case Study 3: Stabilisation of Landslide on Nainital- seepage from pipes can make the slope unstable. In this
Haldwani Road, Nainital (Uttrakhand) project, pull out tests & execution of the soil nailing system
were handled by AECS.
Background & Project Details
The landslide under consideration is located on Nainital- CONCLUDING REMARKS
Haldwani road (NH-35), about 3.5 Km from Nainital. It has Based on the case studies presented, it can be said that:
damaged a historic sewage disposal pipe system leading to Soil nailing is a suitable technique for stabilizing steeply
proposed sewage plant leading to free flow of sewage down the cut/natural slopes. Proper field investigations including pull
slope causing erosion of slope and causing further instability out tests on proposed nails i.e. driven or grouted need to be
carried out for determining soil parameters to be used as input.
Investigations Facial treatment comprising of chicken mesh held in position
Based on soil investigations got carried out by the client, the with U bolts covered with a layer of shotcreting proves useful
soil was found to be non-plastic, poorly graded sand (SP) with and enhances aesthetics of the slope. Sub-surface drainage
cohesion c of 0 kPa & angle of shearing resistance, φ as 420. system using perforated GI/PVC pipes of suitable length and
4 Nos. of pull out tests were conducted to determine field diameter filled with gravel/filter material & wrapped with
values of coefficient of friction between proposed nail and geosynthetics from outside should be provided at suitable
surrounding soil/grout [4]. The bond strength was found to vary locations emanating through the face of stabilized slope. It is
from 0.127 MPa to 0.286 MPa attributable primarily to the desirable to monitor the performance of the nailed slope using
geological condition of the drill hole, efficiency of grouting geodetic methods.
around the anchor bar, the extent of curing cement sand slurry
& surface condition of the reinforcement bar. The indicated ACKNOWLEDGEMENT
values are based on 7 days curing and are expected to be 40 to The authors would like to acknowledge the assistance &
50% higher after 28 days curing. A value of 0.25 MPa or cooperation of the clients of the all projects referred to in this
mechanical anchorage of 2.00 Tonnes/meter at failure was paper in conducting the field work.
adopted for design.
REFERENCES
Design & Analysis 1. FHWA, 2003. “Geotechnical Circular No. 7.Soil Nail
During pull out tests it was observed that anchor bars failed in Walls”, Publication FHWA-IF-03-017, U.S.
bond between bars and the 1:3 cement grout. Accordingly, rich Department of Transportation, Federal, Highway
1:1 cement grout was used and bond strength determined. The Administration, Washington, D.C.
bond strength (kg/cm2) was worked out as load taken by bar in 2. FHWA, 1998. “Manual for Design & Construction,
Kg divided by surface area of bar (cm 2) in contact with grout. A Monitoring of Soil Nail Walls”, FHWA-SA-96-096R.
berm about 2m wide was provided at mid height of 22m slope U.S. Department of Transportation, Federal Highway
that helped economise the design & later accommodated sub- Administration, Washington,
surface drainage pipe from top half of the slope for discharge 3. Tan, Y.C. and Chow, C.M. (2004), “Slope
into the sump at road level. Input parameters adopted for Stabilization Using Soil Nails: Design Assumptions
design are given below: and Construction Realities”, Malaysia-Japan
Symposium on Geohazards & Geoenvironmental
Vertical height of slope=16m, Angle of slope with the Engineering, 13-14 December, 2004, Selangor,
vertical=1, 00, φ=420, c=0.0 kPa, seismic coefficients αh=0.15, Malaysia.
αv=0.075, allowable soil pressure=250kN/m 2 & friction 4. IS:11309-1985 “Method for Conducting Pull Out Test
coefficient between grout & soil=0.60. on Anchor Bars and Rock Bolts”
Stability analysis provided the following design features:

You might also like