Work Instructions: GCM Igbt Replacement Capstone Model C200 Microturbine /C1000 Series Purpose and Scope
Work Instructions: GCM Igbt Replacement Capstone Model C200 Microturbine /C1000 Series Purpose and Scope
Work Instructions
GCM IGBT Replacement
Capstone Model C200 MicroTurbine®/C1000 Series
Guidelines
Review entire procedure prior to performing. Ensure you have all material, tools/equipment,
and reference documents on hand.
Conduct maintenance in a clean, well-lighted area using normal shop tooling to avoid
damage to delicate components.
Retain all parts removed for use in re-assembly, unless otherwise specified.
Safety Procedures
Become familiar with general safety precautions in the C200 User’s Manual (400008) and/or
C1000 User’s Manual (400024). Follow all warnings and cautions in this work instruction.
Symbols
The following symbols are used throughout Capstone documents to alert you to potential
hazards to people or equipment and tips for proper operation of the equipment.
ELECTRICAL WARNING: Identifies an electrical hazard that can result in personal
injury or death.
Material Information
The part(s) being replaced is one or more of the following
Reference Documents
The following Capstone documents are referenced in these Work Instructions:
400003 Recommended Tools, Capstone MicroTurbine
440000 Microturbine Standard Maintenance Schedule
400008 Model C200 User’s Manual
400024 C1000 Series User’s Manual
512298 Field Service Report
Procedures
1. Prepare for procedure as follows.
WARNING: Fuel hazard! Shut off fuel supply. Failure to observe this warning can
result in personal injury, death, and/or equipment damage.
a. For C200 microturbine(s):
(1) Issue Stop command for affected microturbine.
(2) Shut off fuel inlet supply.
(3) Ensure that microturbine chassis remains properly grounded throughout
procedure.
(4) If microturbine is connected to grid, disconnect and lock out from utility in
accordance with local electrical regulations.
(5) If battery packs are installed, turn OFF and lock out main battery pack circuit
breakers, and disconnect battery cables.
(6) Fully isolate microturbine from any other power sources (for example, solid state
relays on user communications board).
(7) Wait at least ten minutes to fully discharge power from the system.
(8) Use DMM to verify that there is no voltage on DC bus and no voltage on high
voltage AC terminal block.
b. For C1000 Series:
(1) If system is configured in MultiPac mode, perform the following steps.
i. Set Override Start to FORCED OFF via CRMS-APS.
ii. Once system is in Stand by mode, disable MultiPac via CRMS.
(2) Continue with the following for all systems.
i. Open C1000 Series Enclosure electrical panel door to access circuit
breakers.
ii. Turn OFF and lock out main circuit breaker for affected bay(s).
iii. Turn OFF and lock out auxiliary circuit breaker for affected bay(s).
iv. Open engine-side door on affected bay(s) and prop open.
v. Shut off fuel inlet supply to bay at ball valve located inside bay door.
vi. Ensure that C1000 enclosure remains properly grounded throughout
procedure.
vii. If battery packs are installed in affected bay, lock main battery pack circuit
breakers in OFF position and disconnect battery cables.
viii. Fully isolate microturbine from any other power sources (for example, solid
state relays on user communications board).
ix. Wait at least ten minutes to fully discharge power from the system.
x. Use DMM to verify that there is no voltage on DC bus and no voltage on
LCM AC output.
440185 Rev A (November 2011) Page 3 of 11
This information is proprietary to Capstone Turbine Corporation. Neither this document nor the information contained herein shall be copied, disclosed to others, or used for any
purposes other than the specific purpose for which this document was delivered. Capstone reserves the right to change or modify without notice, the design, the product
specifications, and/or the contents of this document without incurring any obligation either with respect to equipment previously sold or in the process of construction.
Copy is uncontrolled; user is responsible for verifying current revision.
Capstone Turbine Corporation • 21211 Nordhoff Street • Chatsworth • CA 91311 • USA
C200/C1000 Series Work Instructions: GCM IGBT Replacement
NOTE: If wires/cables are not labeled, label or color-code them before disconnecting.
CHS Wire
(1 of 2) PDM #1
Temp/J20
PDM-PDB Cable ICB P11 cable
(zip tie, cable not
shown)
Hole in right
Dump Valve Cable side of tray
(cable not shown)
k. Remove screws, nuts, and washers from top and bottom of power board assembly.
See Figure 2.
NOTE: Nuts securing power board assembly include one washer on either side of
board. Use caution when removing assembly so as not to lose washers in GCM.
l. Disconnect IGBT and GND cables from top and bottom of power board assembly.
IGBT cable
GND cable
Nut (1 of 8) and
Washer (2 per
nut)
Screw (1 of 8)
Screw (1 of 8)
Nut (1 of 8) and
washer (2 per
nut)
GND cable
IGBT cable
m. Disconnect remaining cables, except control board cable, from power board
assembly. See Figure 3.
Large DC (4)
Small DC (1)
SPS Power/J5,
J4
Voltage
sense/J3
Control board
cable (not
shown)/J1
n. Remove bracket screws from both ends of power board assembly. See Figure 4.
Bracket screw
(1 of 4)
Nomex paper
Side bracket
screw
(6 per IGBT) Flexibar
h. Secure power board assembly using screws (8), nuts (8), and washers (2 per nut, 1
either side of power board) tightened to 45 in-lbs. See Figure 6.
i. Re-connect IGBT and GND cables to power board assembly.
IGBT cable
GND cable
Screw (1 of 8)
Nut (1 of 8) and
washer (2 per nut) Nut (1 of 8) and
Washer (2 per
nut)
GND cable
Screw (1 of 8)
IGBT cable
j. Re-install control board tray and secure with screws (3). See Figure 7.
k. Re-install PDM-PDB cables and secure connectors to control board tray with zip ties.
l. Bind PDM-PDB cables to sides of control board tray using zip ties and plastic anchors
on tray.
m. Re-connect CHS cable (1 per side) to each side of control board tray.
n. Carefully thread ICB P11 cable through hole on control board tray and connect to
control board.
o. Re-connect cables to control board and IGBTs.
Ribbon cable
(1 of 4)
Zip tie (1 of 2
CHS Wire on tray)
(1 of 2)
PDM #2
Left tray screw Temp/J19
(1 of 2)
PDM-PDB Cable
(zip tie not shown) Ribbon cable
(1 of 4)
(3) If applicable, reconnect battery cables and turn main battery pack circuit breakers
ON.
(4) Open system fuel supply.
(5) Issue Start command.
(6) Test system for proper operation.
a. For C1000 Series:
(1) If battery packs are installed in affected bay(s), reconnect battery cables and turn
main battery pack circuit breakers ON.
(2) At electrical panel, turn main circuit breaker and auxiliary circuit breaker ON for
affected bay(s).
(3) Open fuel inlet supply to bay(s).
(4) Close bay door(s).
(5) If system is configured in MultiPac mode, perform the following steps.
i. Enable MultiPac via CRMS.
ii. Set Override Start to AVAILABLE via CRMS-APS.
(6) Continue with the following for all systems.
i. Test system for proper operation.
Responsibility
It is the responsibility of Capstone to:
• Make these procedures available to Authorized Service Providers so they can
successfully complete this task.
It is the responsibility of the Authorized Service Provider to:
• Read this document, understand its contents, and effectively complete procedures.
• Explain service benefits provided to end user.
• Upon completion of service, submit a Field Service Report (512298) to
service@capstoneturbine.com.