Work Instructions
LCM IGBT Replacement
Capstone Model C200 MicroTurbine®/C1000 Series

Purpose and Scope


This document describes the procedure for replacing the Load Control Module (LCM) IGBT
(Phase A, B, C, Neutral) on the Capstone C200 MicroTurbine® and C1000 Series.
This procedure must be conducted by an Authorized Service Provider (ASP).

Guidelines
Review entire procedure prior to performing. Ensure you have all material, tools/equipment,
and reference documents on hand.
Conduct maintenance in a clean, well-lighted area using normal shop tooling to avoid
damage to delicate components.
Retain all parts removed for use in re-assembly, unless otherwise specified.

Safety Procedures
Become familiar with general safety precautions in the C200 User’s Manual (400008) and/or
C1000 User’s Manual (400024). Follow all warnings and cautions in this work instruction.

Symbols
The following symbols are used throughout Capstone documents to alert you to potential
hazards to people or equipment and tips for proper operation of the equipment.
ELECTRICAL WARNING: Identifies an electrical hazard that can result in personal
injury or death.

WARNING: Identifies a hazard that can result in personal injury or death.

CAUTION: Alerts you to a hazard that can result in equipment damage.

NOTE: Clarifies instructions or highlights important information.

440186 Rev A (January 2011) Page 1 of 9


This information is proprietary to Capstone Turbine Corporation. Neither this document nor the information contained herein shall be copied, disclosed to others, or used for any
purposes other than the specific purpose for which this document was delivered. Capstone reserves the right to change or modify without notice, the design, the product
specifications, and/or the contents of this document without incurring any obligation either with respect to equipment previously sold or in the process of construction.
Copy is uncontrolled; user is responsible for verifying current revision.
Capstone Turbine Corporation • 21211 Nordhoff Street • Chatsworth • CA 91311 • USA
C200/C1000 Series Work Instructions: LCM IGBT Replacement

Material Information
The part(s) being replaced is one or more of the following

Part # Description IGBT Phase

511641-XXX IGBT, SKIIP2, 2 pack, 600A, 1200V SMTH HTSK A or B

511642-XXX IGBT, SKIIP2, 2 pack, 600A, 1200V SRTD HTSK C

518299-XXX LCM NEUTRAL IGBT C6X Neutral

Required Tools and Equipment


Tools/materials required for this procedure are listed below. Refer to Capstone
Recommended Tools (400003) for more detailed requirements and recommendations.
 10 mm socket (for power board assembly, IGBT brackets, small DC cables)
 12 mm socket (for Flexibar)
 13 mm socket (for C200 panels, large DC cables)
 Torque wrench
 5/16 inch Allen wrench (for bay doors)
 #2 Phillips-head screwdriver (for module covers)
 #3 Phillips-head screwdriver (for power board assembly, brackets)
 Flat-head screwdriver (for opening C1000 Controller)
 Anti-static bags (for control board and power board assembly storage)
 Digital multimeter (DMM)
 Anti-static wrist strap
 Personal Protective Equipment
• Mechanic’s gloves with lining

Reference Documents
The following Capstone documents are referenced in these Work Instructions:
 400003 Recommended Tools, Capstone MicroTurbine
 440000 Microturbine Standard Maintenance Schedule
 400008 Model C200 User’s Manual
 400024 C1000 Series User’s Manual
 512298 Field Service Report

440186 Rev A (January 2011) Page 2 of 9


This information is proprietary to Capstone Turbine Corporation. Neither this document nor the information contained herein shall be copied, disclosed to others, or used for any
purposes other than the specific purpose for which this document was delivered. Capstone reserves the right to change or modify without notice, the design, the product
specifications, and/or the contents of this document without incurring any obligation either with respect to equipment previously sold or in the process of construction.
Copy is uncontrolled; user is responsible for verifying current revision.
Capstone Turbine Corporation • 21211 Nordhoff Street • Chatsworth • CA 91311 • USA
C200/C1000 Series Work Instructions: LCM IGBT Replacement

Procedures
1. Prepare for procedure as follows.

ELECTRICAL WARNING: High voltage! Follow Step 1 sub-steps to avoid electrical


hazard. Failure to observe this warning can result in personal injury or death.

WARNING: Fuel hazard! Shut off fuel supply. Failure to observe this warning can
result in personal injury, death, and/or equipment damage.
a. For C200 microturbine(s):
(1) Issue Stop command for affected microturbine.
(2) Shut off fuel inlet supply.
(3) Ensure that microturbine chassis remains properly grounded throughout
procedure.
(4) If microturbine is connected to grid, disconnect and lock out from utility in
accordance with local electrical regulations.
(5) If battery packs are installed, turn OFF and lock out main battery pack circuit
breakers, and disconnect battery cables.
(6) Fully isolate microturbine from any other power sources (for example, solid
state relays on user communications board).
(7) Wait at least ten minutes to fully discharge power from the system.
(8) Use DMM to verify that there is no voltage on DC bus and no voltage on high
voltage AC terminal block.
b. For C1000 Series:
(1) Issue Stop command for affected bay(s).
(2) Open C1000 Series Enclosure electrical panel door to access circuit breakers.
(3) Turn OFF and lock out main circuit breaker for affected bay(s).
(4) Turn OFF and lock out auxiliary circuit breaker for affected bay(s).
(5) Open engine-side door on affected bay(s) and prop open.
(6) Shut off fuel inlet supply to bay at ball valve located inside bay door.
(7) Ensure that C1000 enclosure remains properly grounded throughout
procedure.
(8) If battery packs are installed in affected bay, lock main battery pack circuit
breakers in OFF position and disconnect battery cables.
(9) Fully isolate microturbine from any other power sources (for example, solid
state relays on user communications board).
(10) Wait at least ten minutes to fully discharge power from the system.
(11) Use DMM to verify that there is no voltage on DC bus and no voltage on LCM
AC output.

440186 Rev A (January 2011) Page 3 of 9


This information is proprietary to Capstone Turbine Corporation. Neither this document nor the information contained herein shall be copied, disclosed to others, or used for any
purposes other than the specific purpose for which this document was delivered. Capstone reserves the right to change or modify without notice, the design, the product
specifications, and/or the contents of this document without incurring any obligation either with respect to equipment previously sold or in the process of construction.
Copy is uncontrolled; user is responsible for verifying current revision.
Capstone Turbine Corporation • 21211 Nordhoff Street • Chatsworth • CA 91311 • USA
C200/C1000 Series Work Instructions: LCM IGBT Replacement

2. Remove LCM IGBT as follows.


a. Remove enclosure panel(s) as needed to access LCM.
CAUTION: Handle Electrostatic Discharge (ESD) sensitive devices properly. Failure to
observe this caution can result in equipment damage.
b. Remove screws from LCM cover and remove cover.

NOTE: If wires/cables are not labeled, label or color-code them before disconnecting.

c. Disconnect ribbon cables from IGBTs. See Figure 1.


d. Disconnect all cables except ribbon cables from control board.
e. Carefully pull ICB P11 and P12 cables through hole in tray.
f. Remove screws (2 on LCM exterior side, 1 on LCM interior side) from control board
tray.
g. Remove control board tray and store in anti-static bag.

Ribbon cable
(1 of 4)

Contactor CMD ICB P11 cable


cable
ICB P12 cable

Left tray screw


(1 of 2)
Hole in right
CapComm B side of tray
(cable not
shown)
Right tray
CapComm C screw (1)
(cable not
shown)

Left tray screw


(1 of 2)

Ribbon cable

Figure 1 – Removing Control Board


440186 Rev A (January 2011) Page 4 of 9
This information is proprietary to Capstone Turbine Corporation. Neither this document nor the information contained herein shall be copied, disclosed to others, or used for any
purposes other than the specific purpose for which this document was delivered. Capstone reserves the right to change or modify without notice, the design, the product
specifications, and/or the contents of this document without incurring any obligation either with respect to equipment previously sold or in the process of construction.
Copy is uncontrolled; user is responsible for verifying current revision.
Capstone Turbine Corporation • 21211 Nordhoff Street • Chatsworth • CA 91311 • USA
C200/C1000 Series Work Instructions: LCM IGBT Replacement

h. Remove screws, nuts, and washers from top and bottom of power board assembly.
See Figure 2.
NOTE: Nuts securing power board assembly include one washer on either side of
board. Use caution when removing assembly so as not to lose washers in LCM.
i. Disconnect IGBT and GND cables from top and bottom of power board assembly.

IGBT cable

GND cable

Nut (1 of 8) and
Washer (2 per
nut)

Screw (1 of 8)

Screw (1 of 8)

Nut (1 of 8) and
washer (2 per
nut)

GND cable

IGBT cable

Figure 2 – Disconnecting Power Board Assembly

440186 Rev A (January 2011) Page 5 of 9


This information is proprietary to Capstone Turbine Corporation. Neither this document nor the information contained herein shall be copied, disclosed to others, or used for any
purposes other than the specific purpose for which this document was delivered. Capstone reserves the right to change or modify without notice, the design, the product
specifications, and/or the contents of this document without incurring any obligation either with respect to equipment previously sold or in the process of construction.
Copy is uncontrolled; user is responsible for verifying current revision.
Capstone Turbine Corporation • 21211 Nordhoff Street • Chatsworth • CA 91311 • USA
C200/C1000 Series Work Instructions: LCM IGBT Replacement

j. Disconnect remaining cables from power board assembly. See Figure 3.

Large DC
cables (2 of 4)

Small DC cable
(1 of 2)

J2

J3

J1

Figure 3 - Disconnecting Cables from Power Board Assembly

k. Remove bracket screws from both ends of power board assembly. See Figure 4.

CAUTION: Do not damage isolating paper beneath power board assembly.

l. Remove power board assembly and store in anti-static bag.

Bracket screw
(1 of 4)

Isolating paper

Figure 4 - Removing Power Board Assembly

440186 Rev A (January 2011) Page 6 of 9


This information is proprietary to Capstone Turbine Corporation. Neither this document nor the information contained herein shall be copied, disclosed to others, or used for any
purposes other than the specific purpose for which this document was delivered. Capstone reserves the right to change or modify without notice, the design, the product
specifications, and/or the contents of this document without incurring any obligation either with respect to equipment previously sold or in the process of construction.
Copy is uncontrolled; user is responsible for verifying current revision.
Capstone Turbine Corporation • 21211 Nordhoff Street • Chatsworth • CA 91311 • USA
C200/C1000 Series Work Instructions: LCM IGBT Replacement

m. Remove Flexibar on affected IGBT. See Figure 5.


n. Remove side bracket screws of affected IGBT.
NOTE: Phase A and Phase B IGBT require removal of bracket fitted against LCM
enclosure. Phase C and Neutral require removal of bracket on LCM interior side.
CAUTION: Do not damage plastic washers beneath bracket nuts, rubber on edge of
brackets against enclosure, or paper beneath IGBTs.
o. Remove bracket nuts and remove bracket on affected IGBT.
p. Remove IGBT by sliding out.

Side bracket
screws (6 per
IGBT)

Side bracket
screws (6 per Flexibar screw
IGBT)

Bracket Bracket
mounting nut mounting nut
(1 of 2 per (1 of 2 per
bracket) bracket)

Figure 5 - Removing Affected IGBT


440186 Rev A (January 2011) Page 7 of 9
This information is proprietary to Capstone Turbine Corporation. Neither this document nor the information contained herein shall be copied, disclosed to others, or used for any
purposes other than the specific purpose for which this document was delivered. Capstone reserves the right to change or modify without notice, the design, the product
specifications, and/or the contents of this document without incurring any obligation either with respect to equipment previously sold or in the process of construction.
Copy is uncontrolled; user is responsible for verifying current revision.
Capstone Turbine Corporation • 21211 Nordhoff Street • Chatsworth • CA 91311 • USA
C200/C1000 Series Work Instructions: LCM IGBT Replacement

q. Contact Capstone Call Center to determine if removed part should be returned to


factory. If yes, Capstone Call Center will issue Return Material Authorization (RMA)
instructions. If no, dispose of part(s) according to local recycling and/or environmental
regulations.
3. Install new LCM IGBT as follows.
a. Slide new IGBT into place of removed IGBT. See Figure 5.
b. Secure IGBT with side bracket screws (6) tightened to 45 in-lbs.
c. Secure Flexibar and tighten to 90 in-lbs.
d. Re-install power board assembly. See Figure 4.
NOTE: Paper beneath power board assembly MUST prevent contact between power
board assembly and enclosure.
e. Secure power board assembly with bracket screws (4) tightened to 45 in-lbs.
f. Reconnect cables to power board assembly. See Figure 3. Tighten DC cables to 90
in-lbs.
g. Secure power board assembly using screws (8), nuts (8), and washers (2 per nut)
tightened to 45 in-lbs. See Figure 2.
h. Reconnect IGBT and GND cables to power board assembly.
i. Re-install control board tray and secure with screws (3).
j. Carefully thread ICB P11 and P12 cables through hole on control board tray and
connect to control board. See Figure 1.
k. Reconnect cables to control board and IGBTs.
l. Re-install LCM cover.
4. Return system to operation as follows.
a. For C200 microturbines:
(1) Re-install panels.
(2) Reconnect microturbine to power sources.
(3) If applicable, reconnect battery cables and turn main battery pack circuit
breakers ON.
(4) Open system fuel supply.
(5) Issue Start command.
(6) Test system for proper operation.
b. For C1000 Series:
(1) If battery packs are installed in affected bay(s), reconnect battery cables and
turn main battery pack circuit breakers ON.
(2) At electrical panel, turn main circuit breaker and auxiliary circuit breaker ON for
affected bay(s).
(3) Open fuel inlet supply to bay(s).
(4) Close bay door(s).
(5) Issue Start command for affected bay(s).
(6) Test system for proper operation.

440186 Rev A (January 2011) Page 8 of 9


This information is proprietary to Capstone Turbine Corporation. Neither this document nor the information contained herein shall be copied, disclosed to others, or used for any
purposes other than the specific purpose for which this document was delivered. Capstone reserves the right to change or modify without notice, the design, the product
specifications, and/or the contents of this document without incurring any obligation either with respect to equipment previously sold or in the process of construction.
Copy is uncontrolled; user is responsible for verifying current revision.
Capstone Turbine Corporation • 21211 Nordhoff Street • Chatsworth • CA 91311 • USA
C200/C1000 Series Work Instructions: LCM IGBT Replacement

Responsibility
It is the responsibility of Capstone to:
• Make these procedures available to Authorized Service Providers so they can
successfully complete this task.
It is the responsibility of the Authorized Service Provider to:
• Read this document, understand its contents, and effectively complete procedures.
• Explain service benefits provided to end user.
• Upon completion of service, submit a Field Service Report (512298) to
@capstoneturbine.com.

Capstone Technical Support


If you have questions or need assistance, please contact the Capstone Call Center:
E-mail: @capstoneturbine.com
Toll Free Telephone: (866) 4-CAPSTONE or (866) 422-7786
Direct Telephone: (818) 407-3600 • Fax: (818) 734-5382

Capstone Document Library


The latest revisions of all Capstone product documents are available on our website,
www.capstoneturbine.com . Select Document Library link under Quick Links box on lower left
side of home page.
Capstone values your feedback. Please email comments or suggestions for improving
documentation to service@capstoneturbine.com and enter "Documentation" in the subject
line.

© 2011 Capstone Turbine Corporation. All rights reserved.

440186 Rev A (January 2011) Page 9 of 9


This information is proprietary to Capstone Turbine Corporation. Neither this document nor the information contained herein shall be copied, disclosed to others, or used for any
purposes other than the specific purpose for which this document was delivered. Capstone reserves the right to change or modify without notice, the design, the product
specifications, and/or the contents of this document without incurring any obligation either with respect to equipment previously sold or in the process of construction.
Copy is uncontrolled; user is responsible for verifying current revision.