Estimate For Grouted Riprap
Estimate For Grouted Riprap
I.EARTHWORKS
1.)Excavation
Volume of excavation=1.5(12)(3.5)+4.85(12)(2.9)+3.9(12)(2.3)+3(1.8)(12)
=404.22cum
=1706.4cum
=1224.78 cum
Volume of Excavation=6(6.2)(3.5)+6(4.8)(2.9)+6(3.4)(1.3)
=240.24
=3575.64cum
B.Backfill
Volume of backfill=404.22-12(.5)(.25+3.5)(6.2)+12(0.25+2.9)(.5)(4.85)+12(3.9)(0.25+2.30)
(0.5)+12(0.25+1.8)(0.5)(3)
=76.49cum
%Volume of Backfill=76.49/404.22
Volume of Backfill=20%(1706.4cum)
=341.28cum
=244.96cum
=48.04 cum
=710.77 cum
II.MASONRY WORKS
Total Volume=12(.5)(.25+3.5)(6.2)+12(0.25+2.9)(.5)(4.85)+12(3.9)(0.25+2.30)(0.5)+12(0.25+1.8)
(0.5)(3)
=327.73cum
2. @Section “B”
Total Volume={24(6.2)(0.25+3.5)+12(5.7)(3.4+0.25)+24(5.2)(3.10+.25)+12(4.7)(2.8+0.25)+12(4.2)
(2.5+0.25)+12(3.7)(2.2+0.25)+12(3.2)(1.9+0.25)+12(2.7)(1.6+0.25)+12(2.2)(1.3+0.25)+12(1.7)
(1+0.25)+12(1.2)(0.7+0.25)+12(0.70)(0.40+0.25)}{0.50}
=936.6cum
3. @Section “C”
Total Volume={27(6.5)(3.5+0.25)+12(5.7)(3.4+0.25)+12(4.7)(2.8+0.25)+12(3.7)(2.2+0.25)+12(3.7)
(2.2+0.25)+12(2.7)(1.6+0.25)+12(1.7)(1+0.25)}{0.50}
=691.40 cum
4. @Section “D”
Total Volume=0.5(6){6.2(3.5+0.25)+4.8(0.25+2.9)+3.4(1.3+0.25)}
=130.92cum
=2086.65 cum
Volume={12}{0.15}(3.5+2.9+2.3+1.8)
=18.9 cum
Volume={12}{0.15}(3.4+2.8+2.5+2.2+1.9+1.6+1.3+1+0.70+0.30)+24(0.15)(3.5+3.10)
=55.62 cum
3. .@ section “C”
Volume=12(0.15)(3.4+2.8+2.2+2.2+1.6+1)+27(0.15)(3.5)
=37.94 cum
Volume=6(0.15)(3.5+2.9+1.3)
=6.93 cum
=119.39 cum
Volume={12}{0.10}(3.5+2.9+2.3+1.8)
=12.6cum
Volume={12}{0.10}(3.4+2.8+2.5+2.2+1.9+1.6+1.3+1+0.70+0.30)+24(0.10)(3.5+3.10)
=37.08 cum
3. .@ section “C”
Volume=12(0.10)(3.4+2.8+2.2+2.2+1.6+1)+27(0.10)(3.5)
=25.29 cum
Volume=6(0.10)(3.5+2.9+1.3)
=4.62cum
=79.59 cum
For Beam
Total Length=345 m
345/5.5
=63 pcsx4
For stirrups,
Spacing=0.20m
Total no of Stirrups=345/0.20
=1725 stirrups
Length=4(.30)-4(.05)+.2
=1.2m
=5 pcs
Total no of bars=1725/5
Volume of beam=.30(.30)(345)
=31.05cum
FOR FENCING
Total area=1.3(345)
=448.5 sqm
No of CHB=448.5*12.5
For plaster
No of cement=448.5(0.11)
For reinforcements;
Total length=345
Spacing=0.6 m
Total no of Bars=345/0.6
=575 pcs
=4 pcs
No of 12 mm x 6 m bars=575/4
=1210.95 m
=1210.95/6
Total no of pc =345/2
For Formworks
=414sqm
Total no of plywood=414/2.88
=70 pcsx 4
=56.2 days/4
=13.38 days/4
Concreting of beam
No of days=31.05/0.50
=62.1days/4
Reinforcement
Total no of kgs=396(5.33)+552(3.7)
=4154 kgs
=373.86 hours/8
=47/8
=6 days
For plastering
Total area=448.5x2
=897sqm
No of days=897/8
=113/4
=29 days