Professional Documents
Culture Documents
Lecture 9 – Design
(T-Beams)
15 October 2015
RC14-1334: Concrete Structures 1
Lecture Goals
Finish Doubly Reinforced Beam Example
Design of T-Beams
Known section dimensions
Example Problem
Doubly reinforced beam with known dimensions,
fc = 6000 psi & fy = 60 ksi.
Max + Mu = 435.0 k-ft
Use a double layer at the bottom of the beam
Example Problem
Select a k factor (c/d), which will cause the tension
steel to yield.
Example Problem
Compute Ru
Example Problem
Compute bd2
Example Problem
Assume that b =0.45d
Example Problem
Calculate the Atotal for a singly reinforce beam:
Example Problem
Assume A’s=0.40Anet
Example Problem
Select the steel to meet the requirements. Chose 5#9
bars for the tension steel and 2 #8 in compression
steel.
Example Problem
Compute c for the new beam and assume compression
steel has yielded
Example Problem
Check to see if the compression steel has yielded
Example Problem
Compute the actual c value
Example Problem
Compute the actual c value
Example Problem
Compute a and f’s
and
and
As (provided) As (min)
Minimum Area
Calculate the minimum amount of steel
Example Problem
T-Beam with unknown dimensions, hf = 6 in.(slab)
fc = 4500 psi & fy = 60 ksi.
Three spans continuous beam, simply supported on
walls. Spans are (25ft, 30 ft. and 25 ft.) The beam
spacing is 14 ft center to center
Example Problem
Example Problem –
Negative Moment
Calculate the – moment term, where the bottom
section is in compression. Max –Mu = 435 k-ft.
Example Problem-Value
Determine the 1 term for the concrete
Use = 0.9
Example Problem – Mn
Calculate the moment capacity of the beam
Example Problem –
Summary
Summary of the beam with M 435 k-ft.
Example Problem –
Positive Moment
Calculate the + moment term, where the bottom
section is in compression. Max +Mu = 300 k-ft.
Example Problem –
Capacity
Calculate the moment capacity of the beam with
d= 22.5 in. and hf = 6 in.
Example Problem – Mn
Compute the moment capacity of the beam with the
minimum amount of steel 6.19 in2.
Example Problem –
Summary
Use 8 #8 bars As = 6.32 in2. Check to see that the
steel will fit. It will not be within 10% of the
ultimate moment capacity of the beam. However,
the minimum amount steel will preside.