Professional Documents
Culture Documents
: CEC-CP-1
Rev. No.: a Date Issued: 28 OCT ,2020
Block works
METHOD STATEMENT
REVISION HISTORY
Rev. No. Revision Information
Rev. 0 First Issue
1
Contract No.: CA-680-CNP-082020 Doc. No.: CEC-CP-1
Rev. No.: a Date Issued: 28 OCT ,2020
TABLE OF CONTENT
TABLE OF CONTENT ………….............................................................................................................2
1. OBJECTIVE...................................................................................................................................3
2. MATERIALS...................................................................................................................................3
3. RESPONSIBILITIES......................................................................................................................3
4. HANDLING AND STORAGE.........................................................................................................4
5. SAMPLING ...................................................................................................................................4
6. TOLERANCE IN BLOCK WORK..................................................................................................4
7. PREPARATORY WORK................................................................................................................4
8. LAYING BLOCK MASONRY.........................................................................................................5
9. MORTAR OF CONSTRUCTION....................................................................................................3
10. JOINING OF DISSMILAR MATERIALS........................................................................................3
11. JOINTS..........................................................................................................................................3
12. LINTELS........................................................................................................................................4
13. PRECAUTION TO BE TAKEN .....................................................................................................4
6. TOLERANCE IN BLOCK WORK..................................................................................................4
7. PREPARATORY WORK................................................................................................................4
1. Objective
This Method Statement defines the sequence and describes the control procedures to be followed for Architectural
Finishes – Plastering Work for NON PROCESS FACILITY PROJECT -NPF, The purpose of this Method Statement is
to establish the rules to complete blockworks, and related items such as stiffners and lentels. This method statement
covers:ScopeThis work procedure covers Concrete Block masonry work to be executed in the substructures/super
structures of different buildings as specified in the approved drawings.
2. Materials
2
Contract No.: CA-680-CNP-082020 Doc. No.: CEC-CP-1
Rev. No.: a Date Issued: 28 OCT ,2020
3.1 Concrete Blocks (Including Hollow Block, Solid Block and Insulated Block all sizes): Blocks shall be regular in
size & shape and shall be of specified strength & quality conforming as per approved specs.
3.2 The texture of the blocks shall be such that plaster will adhere to it. They shall be sound, free from cracks,
honeycombing, broken edges and other flaws. They shall have plane rectangular faces with parallel sides and sharp
straight angled edges. They shall have a fine, compact, uniform texture and thoroughly dried.
3.3 Cement: as per approved specifications.
3.4 Sand: as per approved specifications.
3.5 Water: Water used for masonry shall be clean and free from injurious amount of deleterious materials.
3.6 Jointing Mortar: Mortar application as per manufacturer recommendation.
3.7 Dimensions and Mix Proportions: As per the approved specifications.
3. RESPONSIBILITIES
1. The site Engineer shall be responsible for the overall implementation of the Company safety &
Quality Plan and ensure efficient execution of work following Project specifications.
2. QA/QC team shall oversee all the activities, whether all are executed as per the Project Quality
Plan and Specifications.
4. The supervisor shall monitor the execution of all works, Foreman shall lead the workforce and
workmanship during the execution of the work.
5. QC Supervisor shall ensure that all works are carried out as per IFC with Project QC Inspector
for inspection.
6. QC Inspector shall ensure that all works are carried out as per IFC drawings, project
specifications, and standards.
7. Helpers /Laborers: Perform tasks involving physical labor at building, assist the skilled workers,
remove the trash, and residual building debris.
3
Contract No.: CA-680-CNP-082020 Doc. No.: CEC-CP-1
Rev. No.: a Date Issued: 28 OCT ,2020
5. Sampling
5.1 A sample of blocks shall be taken from every consignment of 30000 blocks of the same size, batch and
manufacturer for conducting tests for Quality Department.
5.2 All blocks shall be checked for dimension and inspected for visual defects, and to send it for laboratory for
testing the compressive strength.
6. Tolerances in Block work
As per approved specifications.
7. Preparatory Work
a- Mark on the surface to establish the wall lines to attain proper layout of block work & maintain mark till the first
course is fully laid.
b- Scrub & clean with proper tool, Hack the concrete surface where new block work is to be done.
c- Before commence block work, check reference point such as bench mark, damp proof course level, lintel level,
bed block level, cross beam level etc. & be sure where to terminate the top most block course, after the same is
studied in detail as stated above.
d- Mix quantity of mortar, which will be consumed in next 2 hours only. Mixing shall be done with proper
measurement of ingredients. Mixing platform must be clean.
e- These blocks need not be wetted before or during the laying in the walls; in case the climatic condition so
required, the top and the sides of the blocks may be slightly moistened so as to prevent absorption of water from
the mortar and ensure the development of the required bond with the mortar.
4
Contract No.: CA-680-CNP-082020 Doc. No.: CEC-CP-1
Rev. No.: a Date Issued: 28 OCT ,2020
5
Contract No.: CA-680-CNP-082020 Doc. No.: CEC-CP-1
Rev. No.: a Date Issued: 28 OCT ,2020
filling with a resilient material along the contact area and edges filled with sealant. Provide chicken/ synthetic mesh firmly
over all dissimilar joints of concrete/block masonry prior to plastering. For external wall joints need to be grouted or properly
treated to avoid water ingress and crack formation.
11. Joints
a- Horizontal (bedding) joints: Adhesive shall be spread over the entire top surface of the block including front and
rear shall as well as the webs to a uniform layer of around 3mm thickness.
b- When filling in the wall between the corners Vertical (cross) joints for vertical joints, adhesive shall be applied on
the vertical edges of the front and rear shall the blocks.
c- The adhesive shall be applied on the edges of the succeeding unit when it is standing vertically and then placing
it horizontally well pressed against the previously laid unit so as to provide well compacted vertical joints.
d- The thickness of both horizontal and vertical joint shall be around 3 mm. Ranking & pointing is not required.
e- The face of concrete block masonry shall be kept cleaned and all adhesive droppings removed promptly.
f- All block work shall be plumb, square and properly bonded. The thickness of the courses shall be uniform with
courses horizontal.
g- All connected work shall be carried out at nearly one level and no portion of the work shall be left more than one
course lower than the adjacent work.
12. Lintels
Precast or cast –in-situ concrete shall be used in block masonry, over all openings as per approved specs.
6
Contract No.: CA-680-CNP-082020 Doc. No.: CEC-CP-1
Rev. No.: a Date Issued: 28 OCT ,2020
7
Contract No.: CA-680-CNP-082020 Doc. No.: CEC-CP-1
Rev. No.: a Date Issued: 28 OCT ,2020