PEKERJAAN FISIK FASILITAS UMUM 

volume sat
 pembersihan / land clearing  19533.00  ls 
 galian  302.19  m3 
 tanah urug  151.10  m3 
 pondasi keliling  727.00  m' 
 pondasi kavling  1333.82  m' 
 pondasi jalan  1357.82  m' 
 pekerjaan beton Talud 9.00  m3 
 paving jalan lingkungan  4862.00  m3 
 pagar keliling  727.00  m' 
 pagar depan dan papan nama  41.00  m' 
 taman depan  89.65  m2 
 pos satpam  8.00  m2 
 drainase  1357.00  m' 
Biaya
10000.00 195,330,000.00
15000.00 4,532,850.00
20000.00 3,022,000.00  kedalaman 60 cm 
75000.00 54,525,000.00  per 1 m3 = 2.00 m1 
75000.00 100,036,500.00  per 1 m3 = 3.36 m1 
75000.00 101,836,500.00  per 1 m3 = 7.69 m1 
1250000.00 11,250,000.00
35000.00 170,170,000.00
125000.00 90,875,000.00  tinggi 2.0 m 
250000.00 10,250,000.00
150000.00 13,447,500.00
75000.00 600,000.00
75000.00 101,775,000.00
               
               
               