WIR Site Staff Comments
WIR Site Staff Comments
Page 1
WIR SUBJECT: AC SPLIT UNITS (WALL MOUNTED) INSTALLATION INSPECTION
DATE: 24 Jun 2021
CONTRACTOR: MODERN BUILDING LEADERS CO. LTD.
PROJECT TITLE: AL HASSAN 2020 - UMLUJ
PROJECT NUMBER: UMS-2112
ATTACHMENTS: IFC DRAWING
WIR NUMBER: MBL-P046-IR-ME-0298
DESIGN DRAWINGS, SPECIFICATION & SITE REQUIREMENTS HAVE BEEN USED FOR WIR REVIEW.
FOLLOWING ARE OCNSULTANT COMMENTS RELATED TO ATTACHED WIR:
ACTION
ITEM CONSULTANT COMMENTS
CODE
Split Outdoor Units should be installed on concrete pads and not ccepted to be rested on
1
masonary blocks.
2 Split Outdoor Units should be fixed perfectly on their pads.
Since several construction phases have been earlier executed on project site without
supervision from DIYAR consultant side. Therfore the contractor is solely responsible for all
hidden works which are inaccessible and invisible to be inspectedby Diyar engineers
FOR INFORMATION
7 including but not limited to materials, method statments, third party tests, verification
process of structural & MEP works, or any other documents which is not previousely
reviewed and approved by Diyar in accordance to project specifications and design
drawings.