Professional Documents
Culture Documents
SF COOLER 70001622-1
VIGERSLEV ALLÉ 77 - 2500 VALBY - DENMARK 2040 AVENUE C - PA 18017-2188 BETHLEHEM – USA CAPITAL TOWERS 180. KODAMBAKKAM HIGH ROAD, NUNGAMBAKKAM,- CHENNAI 600 034 - INDIA
2 70001622-1
CONTENTS: PAGE:
1. GENERAL INFORMATION 4
3. INSTALLATION 9
4. OPERATION 10
5. MAINTENANCE 25
6. REMEDIAL ACTION 30
7. APPENDICES 39
70001622-1 3
APPENDICES:
Switchover system V
Pump unit VI
The diagrams shown are generic and for reference only. For
job specific diagrams, see the manual from the supplier
Approved by: TMF Translated by: JaRG Checked by: LBJ MGN code: 3A100
4 70001622-1
NOTE!
The present instruction manual is concerned with the situations which,
according to the experience of FLS, are the most likely to occur. An
exhaustive enumeration of all conceivable situations which may occur
during the erection, operation and maintenance of the cooler cannot be
provided.
1. GENERAL INFORMATION
The frames of the cooler are moved backward and forward by means
of the electro-hydraulic equipment.
Two linear transducers are fitted on each of the movable frames; they
continuously provide the PLC unit with specific positional data.
Based upon the positional indications of the cylinders, the PLC unit re-
leases a signal to the main pumps when a reversal in the direction of
pumping, and thus the directional movement of the piston, is to be
made.
Ball valves (605+655) are fitted between the pumps and cylinders to
shut off the oil supply from a pump and to initiate the oil flow from
the standby pump.
The ball valves (605+655) are equipped with micro switches so that
the screen of the control panel will indicate which connections are
open and can be started.
Frame
All the frames are identical, but must be operated independently of
one another. A frame is driven by cylinders (01) connected in a row.
One of the position transducers continuously feeds a signal to the
PLC unit to determine the exact timing for the reversal of movement.
The second transducer is used as a back-up unit and for alarm trip-
ping if there is no movement of the frame.
The total stroke length of the cylinders is 200 mm, of which only 150
mm is normally required by the frame, thus leaving 25 mm at either
end as an oil cushion and as a reserve for conveyance. Therefore,
shock impacts in the system resulting from the piston striking against
the ends of the cylinder will not occur.
However, the "rocker cam" of the pump does not stop at the zero-
point, but continues in the same direction until its position is reversed,
causing oil to be pumped in the opposite direction.
This will lead to a change in the direction of movement of the cylin-
ders, causing them to accelerate to the same velocity in the opposite
direction.
The cylinders have through-going piston rods, ensuring an identi-
cal velocity of the conveying and return stroke of the frame.
6 70001622-1
The forces required to push the clinker forward and to pull the frame
backward through the clinker layer are not of equal strength.
Therefore, there will be a slight difference in the pressure in the two
directions.
2.2 Oil conditioning - booster pump, servo pump and shuttle valve
As previously noted, the main pumps and cylinders operate in closed
circuits, and this means that it is basically the same oil which is being
circulated in the individual circuits.
The two pipelines carrying the oil for all the cylinders of a frame are
equipped – after the last cylinder - with a valve block with built-on
shuttle valve (1130). See Appendix III.
To prevent the same oil from being circulated from the pump to
the cylinders (01), the pipe system is equipped with a shuttle
valve. The shuttle valve is governed by the pressure differential
between the input flow and the return flow in the main circuit.
Thus, the booster pump ensures that a sufficient oil volume is con-
stantly maintained on the suction side of the main pump. To further
ensure that this is the case, a hydraulic accumulator (460) is incorpo-
rated between the booster pump and main pump to ensure that the
necessary quantity of oil is present in case of rapid flow variations.
The additional booster oil for the main pumps is ensured by an inter-
nal pressure relief valve set at 35 bar.
To maintain the quality of the oil, the oil is continuously cleaned and
cooled.
The return oil from the shuttle valve (1130) and the drained oil from
the main pumps are passed through the filter (150).
The circulation pump (200) see appendix I is used to condition the oil
(heat, cool and filter the oil) and it supplies the main pumps with oil.
70001622-1 7
This oil helps secure the oil supply to the bearings of the main pumps
and it fills up the pumps prior to start up.
When the main pumps are at standstill and with the extra pump (200)
running, the oil will flow through filter (165), through all pumps and
through to the drain line and the filters (150), causing the pumps to be
flushed and the oil to be cleaned.
In this way, the oil in the tank can be cleaned, subject to utilization of
the filters (165) and (150).
When heating of the oil is necessary, use the circulation pump (200)
for heating by closing the electrically operated pressure relief valve
(210). This introduces a pressure drop causing the oil to be heated.
See instruction manual for electrical equipment. Pump (200) can thus
be used for heating, but only when the main pumps are stopped.
Filtration of the oil is done simultaneously through the filters (150) +
(165).
Therefore, the pump (200) should remain in operation during any kiln
shutdown of short duration in order to maintain the oil temperature at
a high level, while, simultaneously, cleaning of the oil is being carried
out.
NOTE!
If any parts of the servo- or booster oil circuit require dismantling, it will
be necessary to relieve the accumulator pressure prior to dismantling.
Normally, the pressure will be eliminated quickly through the accumu-
lator safety block, but checking is necessary on the pressure gauge
(455).
At the bottom of the tank there is a drain valve for collecting conden-
sation, if any. When the plant is in normal operation, the oil tempera-
ture will be high enough to prevent condensation, but collection of
condensation in the tank may occur during the periods when the plant
is at standstill.
The tank is equipped with a hand pump (690) which can be connected
to the pipe sections towards the cylinders so that the latter can be
moved manually when the pump station is inoperative, for example in
connection with maintenance work involving the movable frames of
the cooler.
Ball valves (605) and (655) are located between pumps and cylinders
for shutting-off. The ball valves are also used for switching the opera-
tion to the standby pump. The ball valves feature micro switches for
recording the position – shown on display in control panel – and thus
for checking of switchover prior to starting of standby pump.
70001622-1 9
3. INSTALLATION
Installation to be carried out in accordance with drawings and pipe
diagrams and otherwise as directed in the instruction manual 19871,
HYDRAULIC PLANTS.
Do not remove the plugs in the cylinders and do not connect them to
the pipe system until the system has been flushed and is ready to be
pressure tested. Otherwise there is a risk of contaminating the cylin-
ders.
10 70001622-1
4. OPERATION
Fill the tank to the upper mark on the oil level glass (120).
Fresh oil does not have the necessary degree of cleanliness, and,
therefore, the oil must be cleaned after being charged to the system.
The circulation pump (200) is used to clean the oil in the tank and the
equipment on the pump station by diverting the oil through the filter
(150). First, the oil is heated by maintaining the heating circuit – valve
(210) activated – in operation until the oil temperature has been raised
to the highest possible level (preferably 60ºC). With the valves (311) in
closed position, to prevent contaminated oil from reaching the main
12 70001622-1
pumps, there will be a pressure drop across the valve (210) and (133)
until the rise in the oil temperature has been halted.
The pump must be maintained in operation until the system has been
effectively cleaned. Minimum 24 hours. Measuring of cleanliness level
can be done using special equipment or, in this situation, based on
the observation that constant pressure drops across the filters have
been achieved.
Requirements in terms of cleanliness: ISO 4406, class 18/16/13. Oil
samples must be taken during the flushing process and analyzed until
the required cleanliness has been achieved.
When the filtration process is completed the flushing can begin. Start
with cold oil app. 20Cº and let it during the flushing process heat up to
the highest possible temperature (preferably 60 Cº)
Open all valves (311) ensuring clean and warm oil to all main pumps,
but keeping all valves (655) closed ensuring isolation of the still con-
taminated piping system.
This method must only be used when the pipes are clean, i.e. pipes:
“Precision Steel Tubes” (phosphated and oiled) as well as cleaned
with clean rags/dry compressed air – N². Rust in pipes must not occur.
The pipes must be protected against contamination and corrosion be-
fore and during installation.
NOTE!
The plugs in the cylinders must remain fitted until flushing of the pipe-
lines has been carried out.
The next step involves selection of the frame and pipe system which
are to be flushed first.
All ball valves (655) must be closed.
The ball valves (1150) on Appendix III must be connected to the two
hoses (1020) and (1021) which in term will be connected to the cylin-
ders (01) at the subsequent operational stage of the plant. The hoses
(1060) and (1061) near the shuttle valve must be connected to the ball
valve (1151) so that all oil is forced back to the pump, in order to pre-
vent contaminated oil from reaching the shuttle valve (1130). In the
beginning all ball valves (1150) must be closed, and the valve (1151)
must be open. Please refer to Appendix III.
The pump (200) must be started and the ball valves (311) must be
open to ensure lubrication of the main pumps and this will ensure that
the pumps are filled with oil.
The ball valves (1125) must be kept closed, and subsequently the
pump is started without angling, with the pump being cautiously an-
gled until it has been definitely established at which side of the pump
angling is to take place. This can be determined by touching the
hoses, or by checking the pressure gauges (620) and (670) when the
pump delivers oil to port B. This must be done with a low maximum
pressure which is adjusted on the local control panel.
14 70001622-1
The pump can then be started without angling, with subsequent open-
ing of the ball valves (1125) in direction from the standby pump to the
pipe section which is to be flushed, thereby initiating the flushing pro-
cedure. The rate of angling of the pump is slowly increased towards
the maximum limit while the oil pressure and filter are closely moni-
tored; after the oil has been cleaned, the ball valves (1150) at the cyl-
inders must be opened one by one, starting with the cylinder in imme-
diate proximity of the shuttle valve. When the first valve (1150) has
been opened the valve (1151) at the shuttle valve must be closed.
Only one ball valve (1150) is to be open at any one time – however,
see information subsequently provided in this section. After the oil has
been cleaned, the ball valve (1150) is cautiously opened at the next
cylinder from the shuttle valve, and (1150) nearest the shuttle valve is
cautiously closed. The procedure is repeated for the hoses for all the
cylinders in a row, with only one hose opened at any one time and in
the exact sequence from the shuttle valve.
Now the pipes must be pressure tested, open all valves (1150) and
(1151) at the shuttle valve (1130), close the valve (1125) in the A line
only. NOTE: This is important only close valve in A-line, when
pressure testing all pipes will then have pressure except the line
from valve (1125) to the flushing filter at the pump station. Pres-
sure test the lines up to 300 bar and the pump must be angled to
same side as when flushing, port B (VERY IMPOTRTANT). Otherwise
only the hose from the A port will be pressure tested. Throughout this
process, one person must be ready at the emergency stop so the
pump can be stopped immediately in case of severe leakage from a
pipe joint. CAUTION, wear protective glasses and keep unauthorized
personnel away from the pipes. When pressure testing is being
conducted, the operating personnel must be a safe distance away
from the pipe system to eliminate the risk of injuries to skin and/or
eyes.
The remaining part of the pipe system will be pressure tested later.
Having achieved effective cleaning of the pipes and oil, the pump is
stopped and the ball valves (1125), (1151) and (1150) are closed to
minimize spillage of oil when the coupling of the two hoses at the shut-
tle valve is dismantled and the hoses are connected to the shuttle
valve. See Appendix III.
shuttle valve and simultaneous flushing of its pipeline. This can be de-
tected by feeling the temperature rising in the drain pipe.
Prior to shipment, the local control panel has been set for a pressure
of approximately 50 bar, and this pressure may have to be increased
during the flushing procedure when the entire oil flow is to pass across
one ball valve (1150). At a pressure drop above 50 bar, two ball
valves must be kept open simultaneously. At a pressure drop above
100 bar, the oil is heated and the motor is severely strained; as a con-
sequence hereof, high pressure drops should be of short duration. For
this reason, the pressure compensation set point of the pump must be
approximately 120 bar during the entire flushing procedure.
This limitation of pressure is of even more importance
in order to protect the filter cartridge against rupture in
the event of a sudden blockage, entailing risk of severe
damage to the pump!
During the flushing process, the pressure drop across the flushing fil-
ter must be strictly monitored and the filter cartridge must be replaced
immediately in case of any signs of obstruction.
During the flushing process, the oil temperature must always be main-
tained within the range 55-60º C to ensure at the same time a low
viscosity of the oil for optimizing the cleaning process.
The return filters (150) must be continuously monitored and a re-
placement of the filters will be necessary if an alarm indicating ob-
struction of the filters is tripped. See Appendix I.
After flushing of all drives, the hoses from the stand-by pump must be
disconnected from the check valves and attached to the foreseen
joints with metal blind plugs in. The blind plugs are to be used for the
check valves. Please observe strict discipline to avoid contaminating
the now clean system.
The pipe systems have now been cleaned and the hoses can be con-
nected to the cylinders; always ensure that these connections have
been cleaned prior to assembly. The ball valves (1125) must be
closed.
16 70001622-1
The remaining pressure test of A-lines from the pump station to ball
valves (1125) can be done now. They too should be pressure tested
to 300 bar. Throughout this process, one person must be ready at the
emergency stop so the pump can be stopped immediately in case of
severe leakage from a pipe joint. CAUTION, wear protective glasses
and keep unauthorized personnel away from the pipes. When pres-
sure testing is being conducted, the operating personnel must be a
safe distance away from the pipe system to eliminate the risk of inju-
ries to skin and/or eyes.
4.1.5 Start-up
a) Check that all suction valves (430) are open.
b) The cylinders must not be connected to the frame at this point in
time but the cylinders must be supported to allow them to move
freely.
70001622-1 17
e) The stop limits for the movement of the cylinder must be set as
indicated below before the pump units are started, viz.:
115 mm FORWARD STOP
40 mm REVERSE STOP
Important!
Prior to operating the frames with the pump units, the move-
ment of the frame must be checked by means of tackles or similar
equipment, i.e. 150 mm + 25 mm at both ends of the stroke.
If the system is flushed and the cylinders are connected the hand
pump (690) may advantageously be used to perform the checking.
Cleaning MUST be carried out before the connections are estab-
lished.
It must be possible to move the frames at a low pressure (∼30 bar).
The recommended approach involves connecting the hand pump to
the quick-action coupling (685).
It is essential to prevent contaminated oil from reaching the cylin-
ders. Therefore, the oil in the tank must be cleaned before the hand
pump is used.
It should be noted that the frame is placed at an inclination, and, as
a result, its weight will attempt to pull it in downward direction.
25 mm REVERSE STOP
175 mm FORWARD STOP
70001622-1 19
n) The no-load operation of the pumps (0° angling), i.e. the posi-
tion of the rocker cam inside the pump, must be checked.
4.2.2 Heating
In case the oil temperature is lower than 25°C, the pump station must
be put into operation well ahead of the start-up of cooler operation in
70001622-1 21
order to ensure that the oil is properly heated so that the oil will have
the viscosity required to make the pumps work.
Heating is done through circulation from pump (200), by forcing the oil
through the pressure relief valves (210) - Appendix IV -. in order to raise
the temperature in situations where the temperature is within the range
5 - 10°C.
It will not be possible to start the main pumps if the oil temperature is
lower than 9°C.
See also the instruction manual for electrical equipment.
4.3 Controlling of frames - starting position for operation
See description in the instruction manual for electrical equipment.
The hydraulic pump is started in no-load condition (0°-angling), its an-
gling being subsequently altered so that the piston of the cylinder is
forced against that end of the cylinder which is furthest away from the
starting point.
I_____I_____I____________________I____I______I_____
0 RS RAS FAS FS 200
RS REVERSE STOP
RAS REVERSE AUTO STOP
FAS FORWARD AUTO STOP
FS FORWARD STOP
From the starting position, movement is started at the velocity
requested by the central control panel or the local control unit.
The pistons of the cylinders move forward at the preset velocity until
they reach the point FAS. The angling of the pump is then adjusted to
0° within the duration of the braking length to the point FS.
After the "rocker cam " has reached 0-position (0° pump angle), the oil
flow is diverted to port B by moving the "rocker cam " to the opposite
22 70001622-1
side. This is done within the time period allowed for "Reverse Up
Ramp".
Fig. 1
Oil flow from port A STOP AUTO FORWARD
forward is reached
The pistons of the cylinders then move forward again and the process
will continue as described.
The positions FAS and RAS are calculated by the PLC unit on the ba-
sis of the applied set points for RS and FS and the current values of
braking and acceleration cycles and the pump capacities.
Also, the pumps will be swiftly directed towards the ZERO point in
case the RS and FS parameters are exceeded.
The values below must be applied as default set points for the posi-
tions and accelerations, but they can be adjusted in the PLC unit:
RS = 25 mm
FS = 175 mm
Acceleration and braking cycles must be set for 250 ms.
It is essential to ensure that the limits for the forward and reverse
movement are correctly adjusted in relation to one another, as
illustrated in Fig. 1.
70001622-1 23
4.5 Cooling
See Appendix IV.
The oil is continuously cleaned and cooled; to ensure that this is the
case, the pump (200) and the built-in servo- and boost pump of the
main pumps (315) will constantly pump oil through the filters at the in-
take points (165) and (450) of the pumps and from the drain lines to
an oil cooler (140) and the filters (150).
The filters are provided with contamination indicators and alarms in
case of clogging of the filter.
If the oil temperature should rise to a level above 60°C, a water valve
(145) will admit cooling water to the oil cooler (140).
If, despite such precautionary measures, the oil temperature should
rise to 65°C, an alarm for high oil temperature is activated. This is a
pre warning to indicate that the fan has not been started or that the
thermostatic valve is improperly adjusted. In case of a further rise in
the temperature to 70°C, the pump station is cut out via the local con-
trol panel. The temperature settings can also be adjusted in the con-
trol panel.
5. MAINTENANCE
The cylinders and pump station must be inspected and maintained in
strict accordance with the instructions given by the equipment sup-
plier.
The temperature of both pipes to and from the cylinders must be high;
otherwise, only one unit will be drained and the same oil will be present
in the cylinder of the second unit all the time. Contact FLS if the oppo-
site is ascertained to be the case during normal operation of the plant.
• Check for any leakage from the cylinders and assemblies inside
the cooler. Use the observation ports in cooler wall to check this.
• Check for any leakage from the screwed connections.
• Check hoses.
• Check for any leakage from the pump station. Re-tighten
assembly points in case of leakage.
• Check the operating pressure. In case of abnormally high or very
low pressures, contact the operating and maintenance personnel
for information as to whether the abnormal pressure is due
to specific operating conditions, e.g. very coarse clinker in the
cooler.
• Check oil temperature and systems for oil cooler.
• Check the oil level and check for any foam formation in tank.
26 70001622-1
5.2 Weekly checks
Attention must be given to the risks involved in case of ignition of
spilled oil.
• Check for any indication of filter contamination. Replacement of
filter cartridge can take place in connection with forthcoming shut-
down. See instruction manual for filter (5.5).
• The filter elements in filter (150) can be replaced one at a time by
directing the oil to the other filter element by operating the handle
on the filter house
• Check that there is no oil flow across the non-return valve
(215), since this would prevent the oil from being cooled and
cleaned in (150). This can be checked by touching the valve
house to determine whether its external temperature is high.
• Check the function of the oil cooler by physically touching the oil
pipes, and check the oil temperature.
• Check the movement of the grate, 150 mm on the display unit and
by observing the cylinders.
Clean the pipes and hoses thoroughly and check the parts for any
signs of wear. Damaged or worn parts must be replaced and pro-
tected against future wear. For example, by preventing the cooling air
fan from blowing dust at a high velocity against the components.
Note: Due to safety reasons no personnel must enter the cooler when
the flame is ignited or being ignited in the pyroprocessing sys-
tem. Before personnel enter the machine ensure that there is
enough oxygen in the air and that no toxic fumes exist. Normal
lock out procedures for electrically equipment must be followed.
Also make sure that all valves (1125) see Appendix III are closed
before any work is done inside the cooler
The fresh oil must be circulated through the filters (150) by means of
pump (200) for as long as it takes to ensure absolute cleanliness
of the oil before the main pumps are put into operation. See sub-
section 4.1.1.
Venting
Removal of air in the oil at the cylinders must be done through the
shuttle valve block (1130) by inserting hoses in measuring nozzles,
allowing oil foam to be collected in a bucket; see sub-section 4.1.5,
item g.
Be careful to avoid jet flow from the hose.
If the pipes are located above the pump station and the shuttle valve
block, accumulation of air may occur at this location. If so, vent con-
nections must be fitted in the screwed connections.
Vent connections must always be provided at the highest possible
locations. Alternatively, venting can be done by loosening very care-
fully one of the screwed connections.
NOTE!
Any metal particles or any other foreign objects detected in
the filters or in the filter housings (165) or (450) may origi-
nate from the circulation pump or the servo-/booster pump.
Therefore, an immediate examination of these units must
be carried out.
Air filters
The air filter (115) – Appendix IV - of the tank must be replaced on a
regular annual basis.
5.6 Accumulators
The accumulators will ensure that there will always be enough oil to
effect a change in the operating direction of the pump, thus prevent-
ing the risk of cavitations. The pre-charging pressure of the accumu-
lators must be checked three times a year, in connection with a mi-
nor stoppage or a major, prescheduled shutdown. A kiln shutdown of
short duration can be used to check the performance of the accumu-
lator with the accumulator pre charge kit supplied with the pump sta-
tion. The precharged pressure should be 10 bar. Recharge if neces-
sary.
If damage to the bladder of the accumulator is observed, the stand-
by pump must be used until reconditioning or replacement of the ac-
cumulator has been carried out.
5.7 Cylinders
The spherical plain bearings at each end of the cylinder are maintenance
free type, but must be cleaned and inspected in connection with major
overhauls. See supplier’s documentation. Check also whether the bearings
are stuck by tilting/rotating the cylinder about its longitudinal axis. It should
be able to rotate freely both in cylinder body end and in the piston end.
30 70001622-1
6. REMEDIAL ACTION
Fault detection and corrective action
Proper installation and commissioning of the cooler, in combination
with regular inspections and control procedures, will ensure trouble-
free operation of hydraulic installations for many years.
In case of operational irregularities, the causative condition(s) must be
identified by means of the hydraulic and electrical diagrams.
6.1 Cylinders
Check whether the cylinders show any sign of leakage. In case of se-
vere leakage (i.e. more than 1 liter per 24-hour period), the cylinder
must be replaced or reconditioned.
Do not forget to check that the length and stroke length of the
new cylinder are identical to those of the cylinder that is to be re-
placed. If not, compensation for any variations must be made at the
suspension arrangement of the cylinder.
In case of piston rod seizure, the piston rod must be reconditioned or
replaced; otherwise, the seals are liable to suffer renewed destruction
within a very short period of time.
If there is any dust in the areas around and on the piston rods, we
would recommend an arrangement which provides mechanical protec-
tion.
Check for presence of abrasive particles etc. which may have a nega-
tive impact on the functionality of the seals. In case the seals are worn
out prematurely, the quality of the oil must be analyzed.
CAUSE 3:
Irregular oil flow from pump. Check that the pressures gauges (620)
and (670) indicate pressure in the lines. If no pressure is able to build
up, try again with ball valves (1125) closed to identify the problems on
ether side of them. If it is suddenly able to build up pressure the prob-
lem is at the cylinders (01) or the shuttle valve (1130), and if it is still
not able to build up pressure the problem is at the pump station. Pos-
sibly the proportional valve may not be working with the required level
of regularity, possibly due to the need for adjusting the pump card. If
the pump card is improperly adjusted, this may have a negative effect
on the calibration of the proportional valve, entailing need to recali-
brate the proportional valve. Therefore, it is essential to ensure that
the pump card is adjusted immediately in connection with the observa-
tion of any operational irregularities.
It will be possible to check the zero-point calibration of the proportional
valve by interrupting the electrical connection to the valve, where after
the “rocker cam” of the pump must assume a position at the centre,
resulting in minimum flow rate and oil pressure. Needless to say, this
must not be done in case of normal operating operations.
In case of need to check the pump card of the proportional valves, the
pump concerned must be stopped and the stand-by pump must be
put into operation.
The A and B-strings of the pump must be short-circuited. As a result, it
will be possible to test the pump card and the control system, but, of
course, without any application of pressure in the A and B-line.
REMEDY:
Replace or repair the electrical equipment.
See instruction manual for pump card. In case of improper calibra-
tion of the proportional valve, the valve must be dismantled for exe-
cution of re-calibration procedure.
CAUSE 4:
Error signals from transducer. Check signals from transducer.
REMEDY:
Replace transducer. Do not forget to adjust the transducer. It is essen-
tial to ensure proper alignment of the transducer.
CAUSE 5:
Malfunctioning of the pump. There is nothing wrong with the perform-
ance of the electrical equipment, but there is a mechanical fault in the
pump.
REMEDY:
Repair the pump or affect a switchover to the stand-by pump. If the
pump or booster pump is to be dismantled or prepared for renova-
tion procedure, the pump must be isolated by closing the ball valves
and plugging the drain lines, if this should become necessary. All
32 70001622-1
opened pipes and hoses must be immediately closed with clean
plugs.
CAUSE 6:
Malfunction in shuttle valve.
REMEDY:
Replace or repair valve.
CAUSE 7:
Unstable proportional control valve, or irregular supply of servo
oil to the valve.
REMEDY:
There may be a malfunction of the proportional control valve, neces-
sitating replacement of valve.
Check first for any signs of unstable servo pressure, pressure gauge
(455). See manual from supplier.
Alternatively, the adjustment of control card of the pump is incorrect,
necessitating a re-adjustment of the card. See instruction manual for
electrical equipment.
CAUSE 2:
Water supply failure.
REMEDY:
Check the filter (147) in the line in front of valve and clean the filter or
determine the exact point where the water supply is interrupted and
re-establish the connection.
CAUSE 3:
In operation, the hydraulic equipment generates too much heat.
REMEDY:
Determine, by throttling, the exact location where heat is being gener-
ated. An oil pressure exceeding the normal level should be observed
simultaneously with this condition.
Remove any foreign elements or any other obstruction.
CAUSE 4:
Inadequate oil circulation.
REMEDY:
Check the filters (150) and pump (200).
70001622-1 33
CAUSE 2:
Inadequate oil circulation. Only during start-up and in cold environ-
ments.
REMEDY:
Check the heating valve (210) and pump (200).
CAUSE 2:
There is no change in the direction of operation of pump.
Reason: Flawed longitudinal transducer or proportional control valve
or its control card or the servo pressure is too low; the latter condition
is ascertainable by checking the reading on pressure gauge (455).
REMEDY:
Replace the longitudinal transducer.
In case of any malfunction of the proportional control valve/control
card, the back-up pump can be put into operation. This also applies if
the servo pressure is low.
CAUSE 3:
The cylinder has moved to the bottom due to malfunctioning in the
control system or the transducer. Evidence of irregularity is provided
by the cylinder or frame or the panel of the electrical control cabinet
and by the fact that the oil pressure of pump is maximized.
For identification of underlying cause, an attempt should be made to
move the frame with the hydraulic system in “local test” mode.
REMEDY:
Repair/replace the electrical equipment.
CAUSE 5:
Blockage of frame. Irregularity is evidenced by the fact that movement
of frame is halted, with oil pressure at maximum level.
REMEDY:
Check that the cooler is not filled completely, which would impede its
movability. Check that the movable frame on the cooler is capable of
unimpeded movement.
If the cooler is filled with hot clinker which are thoroughly “baked” to-
gether, such formations must first be aerated, with the fans of the
cooler being operated at maximum capacity.
Try to move the frame backward and then forward again in the usual
manner. If this cannot be done, this would indicate that the clinker bed
in the cooler is thoroughly baked together. The preset pressure of
about 240 bar can be increased temporarily to a level around 260 bar.
See sub-section 4.1.5. The pressure can subsequently be adjusted
downward to the pressure which is deemed to be necessary.
70001622-1 35
6.3 Pumps
Cavitations
Check, on a daily basis, whether the noise level of the pumps during
operation is very high, e.g. due to cavitations. Within a very short time
period, this will cause the pumps to sustain severe damage, and,
therefore, the operation must be immediately switched to the back-up
pump.
The underlying cause must be identified, and, apart from the pos-
sibility of the pipelines being clogged, the problem may be due to
failure of the accumulators or flaws in the booster pump or the
pressure relief valve.
Pump must be restored to full functionality or the pressure must be
adjusted.
The pressure of the accumulators can be checked using
the accumulator precharge kit supplied with the pump sta-
tion and a nitrogen cylinder. Checking the precharge pres-
sure must only be done with the oil pressure released,
which should be ensured by the accumulator safety block
(465) at the instant the pump is stopped. But checking at
gauge (455) is still recommended.
36 70001622-1
CAUSE 2:
Loose connections at pump.
REMEDY:
Tighten any loose assemblies.
CAUSE 3:
The oil level is too low.
REMEDY:
Refill with fresh oil. Check that the level alarms function properly and
determine the source of oil leakage.
CAUSE 1:
Falling of coatings or crust from kiln.
If the high pressures are due to coatings falling from the kiln and con-
gestion in the cooler, there will also be a short-term pressure rise. This
will be evident from the operation of the cooler.
CAUSE 2:
Obstruction in cooler.
High pressures may occur if the cross bars and sealing profiles exert
pressure against the underlying parts, as a result of heat impacting
and deformation.
In case of this situation giving rise to a fall-through of hot material in
the cooler, the operation must be strictly monitored, and, if neces-
sary, corrective action must be taken to prevent any ignition of
spilled oil/oil hoses.
REMEDY:
Adjust the operation of the cooler to eliminate jamming exerted by
hot cross bars and the sealing profiles. The necessary repairs must
be carried out at the earliest possible date.
Excessive build-up of material in inlet
In case the inlet of the cooler is filled with material and the frames are
stopped, the fans of the cooler must be in operation to enable the
drive unit to push away the clinker and to ensure effective cooling
of the grates/cross bars and the clinker bed before any pushing is
done.
The preset pressure of maximum 240 bar can then be used to level
out the piled-up formation, but always remember not to apply the full
grate speed; the maximum allowable speed is 50%. If necessary, the
pressure can be raised temporarily to a level around 260 bar. See
sub-section 6.2.3.
CAUSE 2:
Shock impacts in the pipes, which may be caused by air in the oil, bot-
toming of the cylinders or a malfunction of the shuttle valve. These ir-
38 70001622-1
regularities normally occur during start-up with air in pipes and particu-
larly in the drain line, and will normally disappear within a reasonably
short period of time.
REMEDY:
- Venting
- Check and adjust the movement of the cylinder
- Replace or recondition the shuttle valve
CAUSE 2:
Incorrect adjustment of pump control unit, e.g. excessive duration of
braking and acceleration cycles. Alternatively, the maximum rate of
angling of the pump is restricted on the pump card. See manual for
the piston pump and pump control card.
REMEDY:
Adjust the control unit.
CAUSE 3:
Worn seal in cylinders pistons or internal leak in cylinders.
Remedy:
Change the cylinders and renovate them.
70001622-1 39
7. APPENDICES
Appendix I
I
42 70001622-1
II
II
44 70001622-1
III
01 Cylinder
1001 Hose
1007 Vent Valve
1020 Hose for cylinder
1021 Hose for cylinder
1060 Hose
1061 Hose
1062 Hose
1125 Ball Valve
1130 Shuttle Valve
1135 Ball Valve
1140 Flow Switch
1150 Ball Valve for flushing only
1151 Ball Valve for flushing only
70001622-1 45
III
46 70001622-1
IV
100 Tank
115 Air filter
120 Fluid level indicator
125 Level Switches
130 Resistance Thermometer
140 Oil Cooler
145 Water Valve
147 Water Filter
150 Double filter for return oil
155 Clogging Indicator
185 Quick Coupling
186 Quick Coupling
187 Hose
190 Ball Valve, 3-Ways
200 Circulation Pump
210 Pressure Relief Valve
215 Pressure Relief Valve
225 Pressure Gauge, Circulation Oil
680 Hose
682 Connection from Hand Pump
690 Hand Pump
70001622-1 47
IV
48 70001622-1
V
360 Pressure Transmitter
605 Ball Valve, Stand-by Pump
610 Limit Switch
620 Pressure Gauge, A-Line
625 Throttle Valve
635 Valve Block
655 Ball Valve, Main Pump
660 Limit Switch
670 Pressure Gauge, B-line
675 Throttle Valve
685 Connection to Hand Pump
695 Pressure Test Connector
70001622-1 49
V
50 70001622-1
VI
VI
---oOo---