You are on page 1of 18

General Arrangement of Nuclear Island

June 29, 2007


DOE Technical Session
Copyright© 2007 MITSUBISHI HEAVY INDUSTRIES, LTD. UAP-HF-07068-0
Contents

1. Layout Feature of US-APWR

2. Building Concept & Location

3. Layout Considerations

4. Floor Plans/Sections of Nuclear Island

5. Physical Separation from Hazards

DOE Technical Session


Copyright© 2007 MITSUBISHI HEAVY INDUSTRIES, LTD. UAP-HF-07068-1
1. Layout Feature of US-APWR

DOE Technical Session


Copyright© 2007 MITSUBISHI HEAVY INDUSTRIES, LTD. UAP-HF-07068-2
1. Layout Feature of US-APWR
Type Advanced PWR
Output 1,700MWe Class
Unit Single Unit
Containment PCCV
(Pre-stressed Concrete Containment Vessel)

Safety Feature Physically Separation for 4 Trains, &


Physically Separation against Hazards

DOE Technical Session


Copyright© 2007 MITSUBISHI HEAVY INDUSTRIES, LTD. UAP-HF-07068-3
2. Building Concept & Location

DOE Technical Session


Copyright© 2007 MITSUBISHI HEAVY INDUSTRIES, LTD. UAP-HF-07068-4
1. Building Concept & Location
P.N.

R/
(Containment A/B B
nt Vessel)
Pla th
r
No
Reactor Building PS/B PS/B
AC/B
Turbine
Building T/B

Auxiliary Building
Access Control Building Power Source
Building
DOE Technical Session
Copyright© 2007 MITSUBISHI HEAVY INDUSTRIES, LTD. UAP-HF-07068-5
1. Building Concept & Location
¾ Reactor Building (R/B)
9 Contains following safety-related facilities;
- Containment facility including inner (SC) structures and
in-containment RWSP.
- Safety-related pumps and Hx.
- Safety-related electrical, I&C and H&V.
- Main control room
- Fuel handling and storage facilities. P.N.

9 Seismic Category : I

¾ Power Source Building (PS/B)


9 Contains safety-related, non safety
power generators and safety chillers

9 Seismic Category : I

DOE Technical Session


Copyright© 2007 MITSUBISHI HEAVY INDUSTRIES, LTD. UAP-HF-07068-6
2. Building Concept & Location

DOE Technical Session


Copyright© 2007 MITSUBISHI HEAVY INDUSTRIES, LTD. UAP-HF-07068-7
2. Building Concept & Location
¾ Auxiliary Building (A/B)
9 Contains non safety-related equipment, piping(CVCS, WDS),
electrical and H&V.
9 Seismic Category : II

¾ Access Control Building (AC/B)


9 Contains access control area, chemical sampling and
laboratory. P.N.

9 Seismic Category : Non

¾ Turbine Building (T/B)


9 Contains the turbine generator,
equipment and electrical equipment
related to turbine generator.
9 Seismic Category : II

DOE Technical Session


Copyright© 2007 MITSUBISHI HEAVY INDUSTRIES, LTD. UAP-HF-07068-8
2. Building Concept & Location
¾Containment System
Type : PCCV (Pre-stressed Concrete Containment Vessel)
Number of Buttress :2
Equipment Hatch :1
Personnel Hatch :2
Buttress Dome
ID of cylinder 149’-2’’
Dimension
Total height 226’-5’’

Tension Wire
(Horizontal)
Liner Plate
Cylinder
Liner Plate Wire Anchor

Buttress Tension Wire (Vertical)

Base

Tendon Gallery
Plan View Section View
DOE Technical Session
Copyright© 2007 MITSUBISHI HEAVY INDUSTRIES, LTD. UAP-HF-07068-9
3. Layout Considerations

DOE Technical Session


Copyright© 2007 MITSUBISHI HEAVY INDUSTRIES, LTD. UAP-HF-07068-10
3. Layout Considerations
i. Hazards Protection safety systems (Physical
protection/separation from hazards.)

ii. Plant Performance Layout requirement for each systems, positional


relationship between components.

iii. Personal Safety Shielding to minimize radiation exposure and


evacuation route.

iv. Maintainability Space for maintenance/inspection, access-ability,


& provisions for replacement, grating and hoist
Personnel Workability facility.

v. Construction Integration for “Module”.


Provides corridor and hatches.

DOE Technical Session


Copyright© 2007 MITSUBISHI HEAVY INDUSTRIES, LTD. UAP-HF-07068-11
4. Floor Plan/Section of Nuclear Island

DOE Technical Session


Copyright© 2007 MITSUBISHI HEAVY INDUSTRIES, LTD. UAP-HF-07068-12
4. Floor Plan/Section of Nuclear Island
Fuel Handling area A Containment
- Spent Fuel Pool
Facility and Inner
- Fuel Transfer Canal
- SFPCS
Structure
Non Safety- - PCCV
related - RCS
Electrical and - Primary, Secondary
I&C Area Shield
- CVCS - Refueling Cavity
- WDS - MS/FW piping
- non safety-
related electrical Power
and I&C Generator

Safety-related
Electrical and
I&C Area
Safety-related
- Main Control Room
Pumps and Hx area
- Safety-related SWGR, I&C
MS/FW Piping
A
- Safety Injection Pumps
- CCWS
area - RHR/CS Pumps
- EFWPS
- RHR/CS Heat Exchangers
DOE Technical Session
Copyright© 2007 MITSUBISHI HEAVY INDUSTRIES, LTD. UAP-HF-07068-13
4. Floor Plan/Section of Nuclear Island
Containment Facility
and Inner Structure C/V

P.N. MS/FW Piping


FH/B Area
Fuel Handling
area
R/B Safety-related
- Spent Fuel Pit H&V Area
- Fuel Transfer
4F(OF)
Canal Main Control
Room
SFP cooling 3F
facilities 2F Safety-related
-SFP Cooling Hx 1F Electrical and
I&C Area
-SFP Pump
B1F - Safety-related
A-A section SWGR

Safety-related Pumps and HX Area


- CCWS
- EFWPS DOE Technical Session
Copyright© 2007 MITSUBISHI HEAVY INDUSTRIES, LTD. UAP-HF-07068-14
5. Physical Separation from Hazards

DOE Technical Session


Copyright© 2007 MITSUBISHI HEAVY INDUSTRIES, LTD. UAP-HF-07068-15
5. Physical Separation from Hazards
Typical Countermeasures against hazards
hazards Fire Pipe break Missile Internal Flood
(Combustible (high temperature (turbine/ (External flood is
facilities material) and pressure) tornado) site specific)

・Arranged
Isolate by fire above
Equipment barrier Isolate by barrier, the flood level
Including electric, Separated by or distance ・Mitigation of
I&C distance (Restraint, jet flood source
barrier, if Protected by
(contain-ment) ・Installation of
required) outer wall/roof
weir, seal door
Isolate by
Piping (Negligible) (Negligible)
distance
Isolate by fire
barrier Isolate by fire
Beyond flood
Cable Separated by barrier, or
level
distance distance
(contain-ment)
Protected by fire
Main Control Protected by - Protected by Beyond flood
barrier, or
Room barrier outer wall/roof level
distance

DOE Technical Session


Copyright© 2007 MITSUBISHI HEAVY INDUSTRIES, LTD. UAP-HF-07068-16
5. Physical Separation from Hazards
・Physical Separation Concept of 4 Redundant Trains

: A train

: B train
Reactor Building : C train Reactor Building

: D train

Fuel Handling Area Fuel Handling Area


P.N. P.N.

D A D A

Power Source Containment Containment


Building Power Source
Power Source Power Source
Building Building Building
C B
C B
C B C B
D C B A D C B A
D A D A
B1F B1MF
DOE Technical Session
Copyright© 2007 MITSUBISHI HEAVY INDUSTRIES, LTD. UAP-HF-07068-17