If the temporary
load exceeds the
final construction
load, the excess
refers to as
surcharge load.
Conventional Preloading cont.
• The temporary surcharge can be removed when the
settlements exceeds the predicted final settlement.
• This should preferably not happen before the
remaining excess pore pressure is below the stress
increase caused by the temporary surcharge.
• By increasing the time of temporary overloading, or
the size of the overload, secondary settlement can
be reduced or even eliminated.
• This is because by using a surcharge higher than the
work load, the soil will always be in an over
consolidated state and the secondary compression
for over consolidated soil are much smaller than that
of normally consolidated soil. This will benefit greatly
the subsequent geotechnical design.
B. Vacuum Preloading
• Sometimes soft soil may be so weak that even a
common 1.5 m embankment might cause
stability problems. Then it can be suitable to use
the method of vacuum preloading.
• In 1952 Kjellman was the first who introduced
vacuum preloading to accelerate consolidation. In
vacuum consolidation the surcharge load is
replace by atmospheric pressure.
• In its simplest form the method of vacuum
consolidation consists of a system of vertical
drains and a drainage layer (sand) on top.
Vacuum Preloading Conti….
• The common advantages of vacuum preloading
are that there is no extra fill material needed, the
construction times are generally shorter and it
requires no heavy machinery. Moreover, no
chemical admixtures will penetrate into the
ground and thus it is an environmental friendly
ground improvement method.
Vacuum Preloading cont.
Vacuum Preloading cont.
Possible problems associated with vacuum
preloading are:
• To maintain an effective drainage system under
the membrane that expels water and air
throughout the whole pumping duration.
• Keeping non-water saturated medium below the
membrane.
• To maintain an effective level of vacuum.
• To maintain a leak proof system in particular at
the pumps / membrane connections and over the
entire membrane area.
Vacuum Preloading cont.
• Anchoring and sealing of the system at the
periphery.
• Reducing lateral seepage towards the vacuum
area.
Principles of Preloading
Figure illustrates schematically a vertical stress profile
when a vacuum load (assuming 100 % efficiency) is
applied to the ground surface in comparison with initial
conditions and conventional surcharge.