DATE ACTIVITY MILESTONE DURATION REMARKS REF.

JUNE 15 PRIMER PAINTING OF PROCESS TANKS START 7

JUNE 16 SKIM COAT OF EXTERNAL WALL (BUILDING EXTENSION) START 8 DAYS 4

JUNE 17 TESTING OF ELECTRICAL DEVICES (CAPELCO) START 5 DAYS 13

JUNE 18 POLISHING OF INTERCONNECTING PIPEWORK START 4 DAYS 9


PRIMER PAINTING OF INTERCONNECTING PIPEWORK START 5 DAYS 10
INSTALLATIONS OF ELECTRICAL DEVICES START 14

JUNE 19 FABRICATION OF TAPPING CHAMBER CONCRETE COVER FINISH 1

JUNE 21 SITE LAY OUT AND SETTING OFOR ROAD WORKS START 2
SKIM COAT OF INTERNAL WALL (BUILDING EXTENSION) START 5

JUNE 22 PLASTERING OF EXTERNAL WALL (BUILDING EXTENSION) FINISH 3


POLISHING OF PROCESS TANKS FINISH 6

JUNE 23 TOP COAT PATING OF PROCESS TANKS START 8

JUNE 24 TOP COAT PATING OF INTERCONNECTING PIPEWORK START 11


CHLORINE CONTACT TANK FABRICATION FINISH 12
TESTING OF ELECTRO-MECHANICAL EQUIPMENT START 15
WTP PHASE 1
KEY MILESTONES

DATE ACTIVITY DURATION FINISH DATE REF. NO.


ONGOING 1 FABRICATION OF TAPPING CHAMBER CONCRETE COVER - JUNE 19 1
2 PLASTERING OF EXTERNAL WALL (BUILDING EXTENSION) - JUNE 22 3
3 POLISHING OF PROCESS TANKS - JUNE 22 6
4 CHLORINE CONTACT TANK FABRICATION - JUNE 24 12
JUNE 15 5 PRIMER PAINTING OF PROCESS TANKS 9 DAYS JUNE 24 7
JUNE 16 6 SKIM COAT OF EXTERNAL WALL (BUILDING EXTENSION) 8 DAYS JUNE 24 4
JUNE 17 7 TESTING OF ELECTRICAL DEVICES (CAPELCO) 5 DAYS JUNE 22 13
JUNE 18 8 POLISHING OF INTERCONNECTING PIPEWORK 4 DAYS JUNE 22 9
9 PRIMER PAINTING OF INTERCONNECTING PIPEWORK 5 DAYS JUNE 23 10
10 INSTALLATIONS OF ELECTRICAL DEVICES - - 14
JUNE 21 11 SITE LAY OUT AND SETTING OFOR ROAD WORKS - - 2
12 SKIM COAT OF INTERNAL WALL (BUILDING EXTENSION) - - 5
JUNE 23 13 TOP COAT PATING OF PROCESS TANKS - - 8
JUNE 24 14 TOP COAT PATING OF INTERCONNECTING PIPEWORK - - 11
15 TESTING OF ELECTRO-MECHANICAL EQUIPMENT - - 15