JUNE 16 SKIM COAT OF EXTERNAL WALL (BUILDING EXTENSION) START 8 DAYS 4
JUNE 17 TESTING OF ELECTRICAL DEVICES (CAPELCO) START 5 DAYS 13
JUNE 18 POLISHING OF INTERCONNECTING PIPEWORK START 4 DAYS 9
PRIMER PAINTING OF INTERCONNECTING PIPEWORK START 5 DAYS 10 INSTALLATIONS OF ELECTRICAL DEVICES START 14
JUNE 19 FABRICATION OF TAPPING CHAMBER CONCRETE COVER FINISH 1
JUNE 21 SITE LAY OUT AND SETTING OFOR ROAD WORKS START 2 SKIM COAT OF INTERNAL WALL (BUILDING EXTENSION) START 5
JUNE 22 PLASTERING OF EXTERNAL WALL (BUILDING EXTENSION) FINISH 3
POLISHING OF PROCESS TANKS FINISH 6
JUNE 23 TOP COAT PATING OF PROCESS TANKS START 8
JUNE 24 TOP COAT PATING OF INTERCONNECTING PIPEWORK START 11
CHLORINE CONTACT TANK FABRICATION FINISH 12 TESTING OF ELECTRO-MECHANICAL EQUIPMENT START 15 WTP PHASE 1 KEY MILESTONES
DATE ACTIVITY DURATION FINISH DATE REF. NO.
ONGOING 1 FABRICATION OF TAPPING CHAMBER CONCRETE COVER - JUNE 19 1 2 PLASTERING OF EXTERNAL WALL (BUILDING EXTENSION) - JUNE 22 3 3 POLISHING OF PROCESS TANKS - JUNE 22 6 4 CHLORINE CONTACT TANK FABRICATION - JUNE 24 12 JUNE 15 5 PRIMER PAINTING OF PROCESS TANKS 9 DAYS JUNE 24 7 JUNE 16 6 SKIM COAT OF EXTERNAL WALL (BUILDING EXTENSION) 8 DAYS JUNE 24 4 JUNE 17 7 TESTING OF ELECTRICAL DEVICES (CAPELCO) 5 DAYS JUNE 22 13 JUNE 18 8 POLISHING OF INTERCONNECTING PIPEWORK 4 DAYS JUNE 22 9 9 PRIMER PAINTING OF INTERCONNECTING PIPEWORK 5 DAYS JUNE 23 10 10 INSTALLATIONS OF ELECTRICAL DEVICES - - 14 JUNE 21 11 SITE LAY OUT AND SETTING OFOR ROAD WORKS - - 2 12 SKIM COAT OF INTERNAL WALL (BUILDING EXTENSION) - - 5 JUNE 23 13 TOP COAT PATING OF PROCESS TANKS - - 8 JUNE 24 14 TOP COAT PATING OF INTERCONNECTING PIPEWORK - - 11 15 TESTING OF ELECTRO-MECHANICAL EQUIPMENT - - 15