Professional Documents
Culture Documents
LEARNING OBJECTIVES
In this module you will learn about:
General Objectives:
MANAGEMENT
L Demand Management
Specific Objectives:
DEMAND
L Active and Reactive Power Demand and Energy,
L Three-Phase Systems,
L Power Factor,
L Power Factor Correction,
L Demand Management,
L Load Factor,
L Load Shedding,
L Load Shifting.
Performance Objectives:
After successful completion of this module you will be able to perform
the following:
TABLE OF CONTENTS
1.0 INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
5.0 ASSIGNMENT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
Electricity from the supply utility is delivered on demand to a service entry point
within consumers premises, where it is metered and distributed to end users. In
large plants the service entry point may be a substation with transformers to lower
the voltage to a level suitable for the equipment.
Motors, lighting and heating loads are the main consumers of electrical energy in
industrial plants. The number and size of these loads in service at a plant will
determine the amount of active and reactive energy supplied by the electricity
supply authority and subsequently the size of the energy bills.
This module discusses the relationship between the loads and energy, and power
factor, and covers ways of reducing the power demand and electricity bills.
V
I '
Z
Figure 5.2
Figure 5.3
EFFECTIVE OR RMS VOLTAGE
v Max
VRMS ' ' 0.707
2
Similarly for a sinusoidally alternating current:
iMax
IRMS ' ' 0.707
2
Unless otherwise noted, further references to voltage and current imply RMS
values.
Energy is the capacity for action or work. Power is defined as the rate of energy
conversion. In an ac circuit the total power input from the supply at any instant in
time is:
p ' v × i
where: p, v and i are instantaneous values.
Figure 5.6
INDUCTIVE - RESISTIVE CIRCUIT
that current in phase with the supply voltage results in positive power or active
power, i.e. power that flows into the load and is dissipated as heat energy. Power
resulting from current that is 90E (¼ phase) out of phase with the voltage alternates
equally between positive and negative. This illustrates that alternating power or
reactive power flows backwards and forwards between the supply and the load.
In other words the reactive energy is stored temporarily (for ¼ cycle) in the
inductance and then flows back to the supply. The active power is always in
phase with the supply voltage and the reactive power is always 90E (leading or
lagging) out of phase with the supply voltage. This relationship is illustrated in
power triangle, Figure 5.7, with effective or RMS values used, where:
where: O
/ is the phase displacement between the supply voltage and the circuit current.
The circuit Power Factor is the ratio of the active power to the total power:
Active Power
Power Factor PF '
Total Power
' Cos Ø
The more reactive power demanded by a plant, due to motor loads say, the lower
will be the power factor.
Figure 5.7
POWER TRIANGLE
(lighting systems) are balanced there will be zero neutral current (Figure 5.9). In
the mesh (delta) connected load (motors) there is no neutral conductor. The
voltage across each phase load is the vectorial sum of two phase to neutral
voltages.
Figure 5.8
3-PHASE WAVEFORMS
The total power in a three phase circuit is the sum of the power demands of the
individual phases:
Assuming a symmetrical, i.e. balanced system, either star or delta connected load:
VL
For a Star load: VA ' , and IA ' IL
3
IL
For a Delta load: IA ' , and VA ' VL
3
3 × VL × I L
ˆ Pt ' VA
3
' 3 × VL × I L VA
Figure 5.9
3-PHASE SYSTEM CONNECTIONS
The supply utility provides a plant with 3-phase, 600 volt power. The actual phase
to phase voltages (line voltages) were measured at 598V, 599V and 600V respect-
ively.
The measured three phase voltages, currents, and power factor levels were:
Total Power:
Pt ' VA × I A % VB × I B % VC × I C
' 345 × 220 × 0.85 % 346 × 218 × 0.84 % 346 × 215 × 0.85
' 191.1 kW
Reactive Power:
Pr ' V A × IA × SiniA % V B × IB × SiniB % VC × IC × Sin iC W
' 345 × 220 × 0.53 % 346 × 218 × 0.54 % 346 × 215 × 0.53
As the plant 3-phase loads are reasonably balanced (220A, 218A, 215A);
comparable results can be obtained by using the 3-phase formulae:
' 192.25 kW
! With a power factor less than unity, the amount of useful power that can be
supplied by the supply system's generating plant will be less than its full total
power capacity. In other words, although the generators may be delivering their
full current capacity, not all of this current results in useful power. The same
applies with the current carrying capacity of system cables, transformers and
in fact all equipment located between the generators and the consumer with the
low power factor.
! A poor power factor causes a large drop of volts in the generators requiring
larger exciters.
! Electricity Costs
When demand charges are based on the total power demand (kVA), then costs
are inversely proportional to the power factor level, i.e. a low power factor
results in higher costs.
The cost of electricity to consumers whose demand charges are based on their
kW or active demand is unaffected by the level of the plant power factor,
unless there is a low power factor penalty provision in their tariff agreement.
Improving the power factor level can save thousands of dollars in electrical
costs.
! Voltage Levels
A low power factor level causes poor voltage regulation resulting in inefficient
operation of equipment such as motors and lighting.
To produce the lagging reactive power required by inductive loads (motors), the
supply authority must over-excite their generators to make them more capacitive.
To produce the leading reactive power required by capacitive loads like
transmission lines, the supply authority under-excite their generators to make them
more inductive.
Lagging reactive power can equally well be generated by capacitors installed local
to the load, reducing the reactive power demanded from the supply utility and thus
lowering the overall plant power factor and the associated charges. Significant cost
savings on electrical bills can be realized by maintaining plant power factor levels
as high as possible. A power factor of unity is the optimum level, but this is not
always feasible.
terminals of motors, etc. This would minimize plant distribution losses caused by
transmission of the reactive current between the equipment and the capacitors.
Also, additional switchgear would not be required for the capacitors.
Power factor capacitors have the potential for causing significant damage to
existing equipment from over-voltages and the capacitors themselves are
vulnerable to effects of harmonics. Installation should only be carried out by
experts.
Useful Power
Power Factor '
Total Power
' 80 kW
! Step 2 - Calculate the existing Reactive Power Demand at 0.8 power factor:
' 60 kVAr
! Step 3 - Calculate the Total Power at the corrected power factor of 0.95:
Useful Power
Total Power '
Power Factor
80
' kVA
0.95
! Step 4 - Calculate the reactive power at the corrected power factor 0.95.
If the consumer changed his useful power demand, to say 60 kW, but the plant
power factor (uncorrected) remained at 0.8, then less capacitance would be
required to correct to 0.95. Repeating the above exercise will show that the
required capacitance would be 25.3kVAr.
Figure 5.10
Load factor is defined as the ratio of average active load (kW) to the maximum kW
demand over a day, month or year and serves as an indicator of the effectiveness
with which electricity demand is managed. A load factor of 100% indicates that the
plant demand is constant, the demand profile being a straight line, e.g. a plant with
a maximum demand of 100 kW and energy consumption of 2,400 kWh over a 24
hour period.
2400 kWh
Load Factor ' x 100 ' 100 %
100 kW x 24 hrs
With a tariff including both energy and demand charges, a higher load factor will
result in lower electricity costs per kWh consumed.
The analysis of the profile curve of a plant load over a typical 24 hour period will
establish the potential for demand management.
A load profile can be drawn from plant demand levels recorded at specific times
throughout the plant production period. Plant kW demand can be obtained from
timing revolutions of the tariff kWh meter as described in Module 4. The frequency
of kW readings required will depend on the nature of the plant load.
The individual plant load schedules will establish which loads contribute to the peak
demands. Discussions with plant operators will indicate the feasibility of shedding
or shifting these loads to periods of low demand.
A demand recorder, monitoring the plant supplies will provide a more detailed and
accurate load profile.
Figures 5.11 and 5.12 illustrate how the plant peak demand can be reduced by
shifting loads. The maximum demand has in fact been reduced by 30 kW. It
should be noted that although a reduction in demand has resulted there is no
reduction in the energy consumption. The electrical energy consumption has been
shifted in time and the area under the profile curve remains constant. The result
is that the plant load factor has been increased and the cost of electricity has been
reduced. There may be operational costs associated with rescheduling production
and the plant management must take these into account when considering overall
cost benefits.
Figure 5.11 Figure 5.12
LOAD SHIFTING (BEFORE) LOAD SHIFTING (AFTER)
Some plant management have a policy that the demand must not exceed a set
level. Such a policy, normally found in plants with very large demands, may be
necessary because of limitations of the plant electrical system, or to take
advantage of special reduced tariff charges offered by the supply utility.
Figure 5.13
BLOCK INTERVAL MAX DEMAND CONTROL
Typical non essential loads that must be energised for a certain amount of time
every day but may be shed at peak periods include water heaters, personnel air
conditioning, sewage pumps, water pumps.
The typical daily kW demand profile for an industrial plant is indicated in the figure
below. Demand charges are $22.00 / kW / month.
Review of the plant operating schedules and loads established that an independent
production line with a 200 kW demand could be shifted from the peak demand
period to the low demand period without affecting production.
The cost savings resulting from the reduction in demand would amount to:
5.0 ASSIGNMENT
! Plant Demand
Record your plant demand profile, using the SmartReader current monitor
provided in the Audit Kit, and maintain a schedule of plant loads over a seven
day period.
Investigate the feasibility of load shedding or load shifting to reduce the plant
peak demand. Where the plant load schedule is not available it may be
necessary to record demand profiles for each of the plant feeders (ref. Plant
Single Line Diagram) to identify loads contributing to peak demands. Calculate
the potential demand and cost savings.
! Power Factor
Measure and record your plant power factor at maximum demand. Calculate
the capacitance required to improve the plant power factor to 0.98, as outlined
in Section 4.5. Calculate the demand and cost savings.
Figure 5.16
TYPICAL SINGLE LINE DIAGRAM
OF PLANT DISTRIBUTION SYSTEM