This document provides information about rock bolting parameters and cycle times for tunnel development. It measures various physical dimensions of the tunnel including a width of 5m, height of 4.5m, and perimeter of 14m. It also details the bolt spacing, number of friction bolt holes, bolt length, hole depth, and pull percentage. The total meters drilled is listed as 73m. Cycle times are broken down for setup, drilling/installation, and total time per round which is calculated to be 2.4 hours. Performance metrics include delays, available shift time, rounds drilled per shift, and monthly tunnel advance of 558.3m.
This document provides information about rock bolting parameters and cycle times for tunnel development. It measures various physical dimensions of the tunnel including a width of 5m, height of 4.5m, and perimeter of 14m. It also details the bolt spacing, number of friction bolt holes, bolt length, hole depth, and pull percentage. The total meters drilled is listed as 73m. Cycle times are broken down for setup, drilling/installation, and total time per round which is calculated to be 2.4 hours. Performance metrics include delays, available shift time, rounds drilled per shift, and monthly tunnel advance of 558.3m.
This document provides information about rock bolting parameters and cycle times for tunnel development. It measures various physical dimensions of the tunnel including a width of 5m, height of 4.5m, and perimeter of 14m. It also details the bolt spacing, number of friction bolt holes, bolt length, hole depth, and pull percentage. The total meters drilled is listed as 73m. Cycle times are broken down for setup, drilling/installation, and total time per round which is calculated to be 2.4 hours. Performance metrics include delays, available shift time, rounds drilled per shift, and monthly tunnel advance of 558.3m.
Parameter Measurement Width, m 5 Height, m 4.5 Perimeter, m 14 Bolt spacing, m 1.3 Friction bolt holes 11 Rock bolt length, m 3.05 Hole depth, m 3.05 Pull, % 90 Advance per round, m 2.75 Friction bolt holes 24 Total meters drilled, m 73
Rock bolting cycle time
Component Measurement Setup Tramming speed, k/h 4 Average distance between faces, km 1 Tramming time, min 15 Setup and markup time, min 8 Total setup time, min 23 Setup time (=engine hours) per cut, h 0.4 Drilling and instalation cycle Instantaneous penetration rate, 32-mm holes, m/min 1.4 Meters drilled, 32-mm holes, m 73.2 Drilling time, 32-mm holes, min 52.3 Total drilling time, h 0.9 Holes drilled 24 Boom setup time per hole drilled, min 1.80 Bolt instalation time, min 1.00 Total set-up time, min 67.20 Total set-up time, h 1.12 Total time per round, h 2.4
Rock bolting development performance
Component Measurement Roster Days per year 360 Days worked per week 7 Days worked per month 30.0 Shifts per day 2 Shift length, h 12 Delays Shift change, h 1.2 No face available, h 0.85 No power, h 0.5 Meetings, h 0.7 Face not scraped, h 0.2 No ventilation, h 0.2 Pump/water problems, h 0.1 Maintenance/breakdown, h 0.2 Total delays, h 3.95 Productivity Balance of shift available, h 8.05 Round drilled out 3.39 Round advance per shift, m 9.31 Round advance per day, m 18.61 Round advance per month, m 558.30