Production Drill

Physical development parameters


Parameter Measurement
Width, m 5
Height, m 4.5
Area, m2 22.5
Stope width, m 15
Stope height, m 20
Area, m2 300
Area total, m2 277.5
Rock density (wet), t/m3 2.4
Stope burden, m 2.5
Stope space, m 2.5
Metric tons per row, t 1665.0
Number of charged holes 16
51-mm-diameter face holes, meters drilled, m 216.0
Metric tons per meters drilled, t/m 7.7

Production drill cycle time


Component Measurement
Setup
Tramming speed, k/h 4
Average distance between stopes, km 0.0025
Tramming time, min 0.0375
Setup and markup time, min 10
Total setup time, min 10.0375
Setup time (=engine hours) per cut, h 0.2
Drilling Cycle
Instantaneous penetration rate, 51-mm holes, m/min 0.57
Meters drilled, 51-mm holes, m 216.0
Drilling time, 51-mm holes, min 378.9
Total drilling time, h 6.3
Holes drilled 16
Setup time per hole drilled, min 5.5
Total set-up time, min 88
Total set-up time, h 1.5
Total set-up and drill time, h 7.8
Total time per face, h 7.9

Production drill performance


Component Measurement
Roster
Days per year 360
Days worked per week 7
Days worked per month 30.0
Shifts per day 2
Shift length, h 12
Delays
Shift change, h 1.2
No stope available, h 0.85
No power, h 0.5
Meetings, h 0.7
No ventilation, h 0.2
Pump/water problems, h 0.1
Maintenance/breakdown, h 0.4
Total delays, h 3.95
Productivity
Balance of shift available, h 8.05
Rows drilled out 1.01
Meters drilled per shift, m 219
Meters drilled per working day, m 437
Meters drilled por month, m 13,123
Metrics tons per shift, t 1,686
Metrics tons per working day, t 3,372
Metrics tons per month, t 101,160