PHASE 1 - VISIONING
INTRODUCTION
Sustainable Livelihood Enhancement for farmer beneficiaries through the Agrarian Reform
Beneficiaries Organization (ARBOs) this aims to sustain the productivity of the provided land
and to provide other opportunities for the beneficiaries to increase their level of productivity
these coordinates is estimated at 11.0 meters or 36.1 feet above mean sea level.
Zamboanga Sibugay is one of the Agrarian Reform Beneficiaries Organization of the agency.
The organization composed of 36 females and 47 males, a total Eighty- Three (83) Agrarian
Reform Beneficiaries (ARB). The community engaged into coconut plantation, vegetables
gardening and other livelihood income generating. With the low cost of coconut product, the
beneficiaries need to innovate a value adding product out of “tuba” to help boost the income
generating activity of the organization out of the raw materials available in the area and to
Page | 1
uplift the socio-economic of the community. However, it’s still enough to sustain their needs
every day because of other related factors influencing directly and indirectly the development
process of Barangay Buluan which will be deliberate in this the another phase of this project.
Beneficiaries have the guaranteed opportunities of development that enables them exercise
OBJECTIVES:
To promote livelihood promotion and social inclusion services to the Agrarian referom
To promote value based education among the beneficiaries for holistic development
Zamboanga Sibugay conducted a need assessment survey among the beneficiaries. Discussions
have also been conducted among the Buluan Agrarian Community Cooperative (BACOMCO)
of Barangay Buluan, Ipil Zamboanga Sibugay and Department of Agrarian Reform Team.
Even other government agency such as; Department of Trade and Industry (DTI), Department
Page | 2
Development(DSWD) introduce and implement programs to that Barangay. All the above
schemes are aimed at improving the living conditions of the community by directly involving
the appropriate target groups. Still, livelihood is the major problem for the Agrarian Reform
Beneficiaries. Based on the priority of the need and demand from the community, Department
of Agrarian Reform has taken this initiative to design a community based sustainable
thorough assessment and analysis. The project mainly focus on capacity building for skill
development on agriculture, vegetable and alternative livelihood options, capital and tools
institutionalize.
IMPLEMENTATION STEPS
Page | 3
functioning & appropriate response
gap in livelihoods
need
TARGET PEOPLE/BENEFICIARIES:
e l l
BACOMCO 67 46 113 3 - 3 115
The overall goal of this project is to uplift the socio-economic status of the Agrarian reform
beneficiaries by the end of 2 years through various training and activity to be given to them by
Activity 1.1 Conducting need assessment including baseline survey and collect detailed
Page | 4
Activity 1.7 Procurement of Quality seeds for paddy cultivation
Activity 1.9 Procurement of storage bin units will be procured and distributed to beneficiaries
for creating grain banks , metal storage bins and safety net during period of food insecurity
Activity 1.10 Orientation sessions will be organised for ARB beneficiaries on the maintenance
of the unit.
Activity 1.11 Procurement of Vegetable seeds for promotion of kitchen garden Activity.
Activity 1.15 Capital support to start alternative income generating activities will be provided
like dairy farm, Goat farm and poultry farm and leaf plate making
existing schemes
Activity 1.17 Seminars on Right to Information (RTI) Act. Right to Information Act is
Activity 1.18 Networking with financial institutions to establish and increase micro-credit
Activity 1.20 Training on organisation development and management will provide basic
Page | 5
understanding about the organisational dynamics, development and management.
Activity 1.22 DAR will provide on-going technical support to strengthen the society
BUDGETARY REQUIREMENTS
The Total financial requirement is 10, 295,000.00; towards entire project cost for 2 years. The
allotted fund from the Project Beneficiaries Development Division Fund Particular on
Mr. Anthony M. Teves, Chief for Program Beneficiaries Development Division (PBDD)
represents the organization in all legal and contractual obligations. He will also be responsible
for implementation of the project and reporting in all related matters. He will appoint project
staff, develop project work plans and review project progress on regular basis. In addition, the
project will require five full time paid staff (including a Project Manager) for implementation
of the project. The project Manager will manage day to day project operations and report to
Chief for Program Beneficiaries Development Division (PBDD). The organogram of project
Page | 6
project management under the framework of the
stakeholders
Livelihood Coordinator Post Graduate Certificate in The person will be
Exploring marketing
stakeholders on livelihoods.
Accounts Admin Officer Accounting/ Commerce with Assist the project coordinator
to maintain project
field staff
Community Mobilisers Graduate and two years’ The community Mobilisers
Page | 7
(three) experience in community are primarily responsible for
mobilisation activities as
initiatives.
PROPOSAL LETTER
SAMSONA L. AUTIDA
BACOMCO Manager
Buluan, Ipil, Zamboanga Sibugay
Dear Madam:
The Department of Agrarian Reform Team enjoyed discussing the opportunity to work with
you on our Project: Sustainable Livelihood enhancement for our Agrarian Reform
Beneficiaries. We began working on this project last week after our initial email, and are
On May 25th, we discussed your growing concerns regarding the status of life of our Agrarian
Beneficiaries. We see that one of the concerns of our beneficiaries is their livelihood; we can
help to increase the productivity and level of quality of life of our beneficiaries through this
For this project, we estimate a budget of roughly P10, 295,000.00 for two years. We can
Page | 8
discuss the plan in more detail if you choose to proceed, and can adjust the budget based on
If you would like to move forward with our proposal, please send me an email so we can begin
discussing and planning the next steps right away. I will follow up with you through email next
Thank you kindly for reviewing our proposal. If you have additional questions, I am available
Sincerely,
ANTHONY M. TEVES
Chief, PBDD
The Project Approval Review is an important hurdle for a new project to pass. At this review,
executive or senior management will determine whether there is sufficient technical and
Estimate Baseline
Prioritize Project
Cost and Schedules
Page | 9
Evaluate Funding
Alternatives & Scenarios
Approve or Reject
Apply
Funding Allocate Funding Project Rejected
Scenarios
Approved The project will proceed. At a minimum, funds and resources will be
Not Approved There is not sufficient merit to proceed with this project
No
Activity Year 1 Year 2
.
Activities Related Setting up the Q1 Q2 Q3 Q4 Q1 Q Q3 Q4
Project 2
1. Recruitment of Project Staff
2. Setting up of Project Office
3. Procurement of office equipment,
Page | 10
4. Inception workshop for project staff to
demographic information of
beneficiaries
6. Formation & orientation on Agrarian
Reform Beneficiaries
bookkeeping.
10. Exposure visits to other NGOs
11. Procurement of Quality seeds for
paddy cultivation
cultivation.
Page | 11
maintenance of the unit.
15. Procurement of Vegetable seeds for
livelihood opportunities
19. Capital support to start alternative
Philippines
22. Networking with financial institutions
Activity
24. Training on organisation development
Page | 12
management.
25. Training on financial procedures and
linkages.
27. DAR will provide on-going technical
reports
31. Interim report to the Donor
32. Final report to the donor within three
months of completion
Activity description:
1. Community Assessment and Base line Survey: Conducting need assessment including
Beneficiaries of BACOMCO. The details will include information on the households and their
status in terms of functioning. The project will also identify existing vocational skills and local
2. Formation & orientation OF ARBs. Initial meetings with community members to form 115
beneficiaries will be organised. Project staff will orient the beneficiaries about the need and
Page | 13
benefits of forming a Sustainable Livelihood Enhancement for ARB’s. The agenda of the
Meetings will be to motivate beneficiaries from the target communities to organise for better
livelihood opportunities. The meetings will facilitate group formation and selection of key
3. Training on group dynamics to ARBs. Once the groups are formed, the project will begin
with training on the group dynamics and various techniques involved in managing the group. It
will organise trainings to all 115 beneficiaries. Roles and responsibilities of the groups will be
discussed and finalised during these trainings. Rules and monthly subscriptions by the members
will be decided during the trainings. These trainings will be organised at Project site at Buluan
4. Training on leadership development: The training is crucial and identified as one of the
gaps in several studies conducted in community. The trainings will impart skills in leadership
development and management of the group. The trainings will be provided to key members of
5. Training on accounts and bookkeeping. Accounting and bookkeeping in the groups has
always been a challenge due to lack of education and literacy amongst the group members. The
project will impart training on basic bookkeeping procedure to selected members of the
BACOMCO. It will ensure that the groups will have at least one literate person and support her
6. Refresher trainings to ARBs: The refresher trainings will aim to identify the gaps/challenges
in group dynamics, leadership and bookkeeping and address the same in participatory manner.
These trainings will be organised after completion of one year of group formation. The project
will adopt peer support approach viz. engaging successful ARBs to resolve the challenges of
other SHGs. Further the refresher trainings will provide additional inputs to the key members of
the group.
Page | 14
7. ARBs exposure visits to other NGOs: Exposure visits to other successful ARBs will be
organised to newly formed ARBs. It will be useful for the members of new groups to understand
8. Procurement of Quality seeds for paddy cultivation: Quality seeds units will be procured
9. Training on ARBs cultivation: Build technical skills in agriculture cultivation. The project
will engage external experts to organise the training and build the technical capacity of the
members.
10. Training on Organic Vegetable Cultivation: Trainings to be provided to 115 ARBs poor
farmers on organic vegetable cultivation with the support of Horticultural department. Training
to be provided to farmers.
11. Capital Support to Vegetable Cultivation : Capital support to be given 1500 farmers ( 115
ARBs) for purchase of seeds, tools , machinery and working capital support in collective
approach.
12. Training on Kitchen Garden : Training to be give to 115 ARBs on kitchen garden to
enhance their household level income in association with agricultural and horticultural
department.
13. Procurement of Vegetable seeds for Kitchen Garden : In order to increase the income
level of daily vegetable cultivation women, the project proposes to distribute small vegetable
kits. 115 vegetable kits will be procured and distributed to ARBs. The project will ensure that
the supplier provides proper demonstration to the beneficiaries to understand its usage.
14. Promotion of alternative livelihood opportunities: The project will use baseline and PRA
information to identify the existing alternate livelihood opportunities as well as vocational skill
building requirements. Few alternate livelihood opportunities such as dairy farm, goat rearing,
poultry farm, Community fair shops, leaf plate making, and other micro enterprises could be
Page | 15
explored. However, the project will emphasise on the demand from the target groups with regard
to alternate livelihoods and support accordingly. Capital support to be given to the Executive
committees for purchase of cows, goats, establish community fair shops, leaf plate enterprise in
15. Vocational skill building on alternative livelihood opportunities: The project proposes to
organise skill building trainings, if needed, once the alternate livelihood opportunities are
identified and finalised by the groups. Specially the training to be organised dairy farm, goat
rearing, poultry farm, Community fair shops and leaf plate making.
schemes available for ARBs. The project will involve officials from agricultural, horticultural
ensure accurate information about the entitlements. Two such workshops (one day each) are
17. Seminar on Right to Information (RTI) Act. Right to Information Act is enforced by the
Government of Philippines, which provides the right to access any information from the
government authorities / department. The tool has been effective for an ordinary citizen to access
crucial information from the government. As part of women empowerment, the project will
organise a one day seminar for key ARBs to raise awareness on the Act and its usage.
18. Networking with financial institutions: To establish and increase micro-credit linkages for
ARBs. Apart from financial institutions, the project will coordinate with BACOMCO to get
information regarding the schemes and entitlements for women from the target communities.
19. Training on organisation development and management: The training will provide basic
understanding about the organisational dynamics, development and management. One training
(3 days duration) will be organised for all the office bearers as well as key members of the
Page | 16
society. External technical experts will be hired to conduct the training.
the financial management of the society. One training is planned and the duration of the training
will be two days. Training will include key people responsible for finance/accounts
management.
21. Networking for building marketing linkages. The main purpose of the society is to create
better marketing opportunities for the ARBs. The society will also make efforts to explore other
market avenues for selling ARBs related products. DAR will provide on-going technical support
has commenced and will send three-monthly reports to donor agency up until six months after
its termination. In addition, the project will establish a project monitoring plan based on the
project log frame for internal monitoring and evaluation purpose. The monthly activity plans
will be developed from the project monitoring plan. DAR will develop appropriate reporting
formats for collection of project information on a monthly basis. Monthly project review
meetings will be organised to review the progress and these meetings will be facilitated by the
Project Manager. Proceedings of each monthly review will be recorded and kept for future
reference. The Chief for Program Beneficiaries Development Division will undertake period
monitoring visits to the project area to interact with project beneficiaries, project staff and other
stakeholders on the progress. Besides, the project will form an executive committee consisting
Executive Director of DAR which is the Chief For Project Beneficiaries Development
Division
Page | 17
President of the Agrarian Reform Beneficiaries
The executive committee will act as a nodal body for project monitoring and implementation.
Towards end of the project an external evaluation is planned by external resource person. The
Evaluation will assess the impact of the project within the project framework. It will also
Identify the gaps and provide recommendations to be considered for similar future projects. In
case, donor agency commits to undertake the external evaluation of the project, then the
project will reconsider the budget for the evaluation activity. However, DAR will appreciate
activities are identified considering the existing socio-cultural practices of the target
beneficiaries. The skill building measures are planned to improve the effectiveness of existing
livelihood practices. The project will not impose any practice that is locally unviable. The
behavioural and attitudinal changes brought in by the project among the beneficiaries will
empower them to actively participate in decision making processes at the community level. The
socio-cultural changes brought in by the project, in terms of livelihood practices, will have
lasting impact on the target beneficiaries even beyond the project period. The project will
significantly affect the lives ARB’s in their income generation activities, livelihood security and
through tools and capacity building support. It is expected that the beneficiaries will continue the
Further, the groups will continue to access resources from financial and government agencies
through the linkages created under the project. DAR plans to continue the project from income
generated from the BACOMCO and the external support received from government programmes
and other agencies. DAR will continue to play an active role to facilitate the them to strengthen
Page | 18
strong links with government schemes and projects so as to generate the required assistance.
Internal income will be generated in form of membership fees, donations and revenue generated
from community based institutions. The project will promote BACOMCO with objective of
sharing information, conducting training, providing financial and non-financial services to its
members. The ARB, on the completion of the project, plans to rise own funds through
membership development fees, nominal fees charged for its services to the groups, benefit
events, grants from the government and donors. The revenue generated will cover the ARB’s
operating expenses as well as minimal support to the groups created under the project.
Page | 19