Gantt 2
Gantt 2
Mode S M T W T F
1 Project Initiation 5 days Mon 5/31/21 Fri 6/4/21 100%
2 Project Charter 3 days Thu 6/3/21 Mon 6/7/21 100%
3 System Development 29 days Thu 6/3/21 Tue 7/13/21 35%
4 Phase 1 Black Box Testing 2 days Mon 6/14/21 Tue 6/15/21 100%
8 Phase 2 Black Box Testing 2 days Mon 6/21/21 Tue 6/22/21 0%
12 Phase 3 Black Box Testing 2 days Mon 6/28/21 Tue 6/29/21 0%
16 Phase 4 Black Box Testing 2 days Mon 7/5/21 Tue 7/6/21 0%
21 Phase 5 Black Box Testing 2 days Sat 7/10/21 Sun 7/11/21 0%
26 Project Punchlist 2 days Thu 7/15/21 Fri 7/16/21 0%
27 Project Report 3 days Thu 7/15/21 Mon 7/19/21 0%
28 Post Mortem Tue 7/20/21 0%