Professional Documents
Culture Documents
Limited
METHOD STATEMENT
for
Construction of Road & Utilities for Realigned TAMA
From SWCC Corridor to Maajiz Road.
PIC I T-7062
Contractor:
SAMA CONSTRUCTION FOR TRADING & CONTRACTING COMPANY
Revision History:
1|Page
SAMA Construction for Trading & Contracting
Limited
Project No. PIC I -T-7062
Documents Type:
Method Revision No.: 01 Revision Date:
Statement
Documents Title: Method of Statement for Construction of Bridge-042
2|Page
SAMA Construction for Trading & Contracting
Limited
Project No. PIC I -T-7062
Documents Type:
Method Revision No.: 01 Revision Date:
Statement
Documents Title: Method of Statement for Construction of Bridge-042
Objective:
Design and detailing are in accordance with AASHTO, LRFD Bridge Design
specification (2014) with interim revisions (2015, 2016), and with the exception
stipulated by the Ministry of Transport of the Kingdom of Saudi Arabia.
Construction shall be accordance with AASHTO, LFRD Bridge Construction
Specifications (3rd Edition) (2010) with current interims and with MOT General and
Special Specifications.
3|Page
SAMA Construction for Trading & Contracting
Limited
Project No. PIC I -T-7062
Documents Type:
Method Revision No.: 01 Revision Date:
Statement
Documents Title: Method of Statement for Construction of Bridge-042
List of Contents
Section Description
1 Scope Of Work
3 Responsibilities
5 Methodology
8 Attachment
4|Page
SAMA Construction for Trading & Contracting
Limited
Project No. PIC I -T-7062
Documents Type:
Method Revision No.: 01 Revision Date:
Statement
Documents Title: Method of Statement for Construction of Bridge-042
1. Scope of work
This method statement relates to the construction of Bridge including
Earth Work (Manual Excavation), Concrete Work for foundations,
Abutments, Box Girder, Deck Slab, Wing Wall, and Approach Slab, New
Jersey Barrier with Rebar and Commissioning and Testing at Aramco
Corridor.
3. Responsibilities :
These Site activities will be carried out by SAMA team, headed by Project
Manager in Coordination with Construction Manager, QA/QC Manager, Safety
Manager and Site skilled worker Team at Aramco Corridor.
6|Page
SAMA Construction for Trading & Contracting
Limited
Project No. PIC I -T-7062
Documents Type:
Method Revision No.: 01 Revision Date:
Statement
Documents Title: Method of Statement for Construction of Bridge-042
Construction Manager shall ensure that all activities are executed in accordance to
the relevant project specification, RC Standard drawings, IFC Drawings in
compliance with Quality and Safety requirements. All the operations or risk
assessed, and necessary control measures have been implemented to carry out the
tasks in a safe manner. He shall strictly implement and monitor the work
methodology in a schedule time. He will handle any issues that would arise during
execution of the job. He will liaise with and report to the project Manager for
controlling site activities.
Civil, Electrical and Mechanical Engineers shall be responsible for the overall direction,
monitoring, coordination and control of all the construction activities under their
respective scope. They are also responsible for site supervision directly involved in
planning and execution of site activities. They are responsible for the preparation of
safety action plan and Risk Assessment. Submit safe work plan for the
application of work permits if required. They should raise request for inspection to
SAMA Qc department at appropriate stage of work.
Safety Manager shall review all safety documents prior to start work ,Method
statement, Risk Assessment, JSA, JHA , safe working plan and RC and ARAMCO work
permits. He shall conduct site inspection regularly and recommend appropriate
corrective measures. He shall Co-ordinate to the Project Manager/Construction
Manager and Provide safety Guidance and advice from Commencement of
activities until Completion. He will also raise all safety relates issues observed at the
7|Page
SAMA Construction for Trading & Contracting
Limited
Project No. PIC I -T-7062
Documents Type:
Method Revision No.: 01 Revision Date:
Statement
Documents Title: Method of Statement for Construction of Bridge-042
work site to CM for compliance. He will ensure that all safety rules & regulations
are following all the time and ensure that RC/Aramco Safety Management system
are effectively comply.
9|Page
Methodology:
d. Base on the design information provided by bridge designer, i.e foundation sizes,
anticipated structural loads and finished grade levels. Also based on the
stratigraphy encountered, GWT and overall site conditions, the bridge
abutments can be supported on shallow foundations. Accordingly, we have
considered the bridge foundations to be supported on Mat/ Raft for the given
sizes.
10 | P a g e
A footing of 5m x 5m or greater is generally considered as mat/raft foundation. A
structure supported on a mat foundation can withstand greater settlements
than one supported on spread footings as mat foundation tend to bridge over
heterogeneity of the soil and the average settlement does not approach the
extreme values of spread footings. Therefore, the LRFD value for mat foundation
can be greater than that for footings. For mat foundations on sand or gravel,
Terzaghi & Peck suggest an increase in LRFD value than those for footings.
5.3 Earthworks
Will be carried out according to Specifi cati on 02200 .
B. Utilities Scanning
Will be carried out according to RC/ARAMCO
Standard & Procedure for ‘Manual Excavation Vicinity of
Underground Utilities Aramco Pipeline. Some part (if needed) of
area needs sheet piling to secure Aramco existing Aramco Pipe.
ARAMCO Land Use (LUP) Permit is required. SAMA will coordinate
all Utilities authorities of ARAMCO before start any work.
C. Dewatering
12 | P a g e
Reference specification section 02200 - earthwork.
1. Prior to foundation excavation, the EPC contractor (SAMA) shall install
a continuous groundwater pumping system to maintain the
groundwater level at least 500 mm below the bottom of excavation.
4. If the dewatering does not comply with these notes and groundwater
drips through the subgrade or otherwise enters the excavation, then
the EPC contractor (SAMA) shall perform the following
5. Works at his own time and expense.
6. Re-design and re-construct the continuous groundwater pumping
system to lower the groundwater level to at least 500 mm below the
bottom of excavation.
7. Over-excavate an additional 200 to 300 mm of material if needed.
8. Proof-roll the newly exposed subgrade to detect all loose and soft
spots. Where loose and/or soft spots are encountered, undercut and
replaced with roller-compacted crushed stone (20 mm size) placed in
100 mm maximum thick lifts. Fully wrap the crushed stone layers with
geotextile fabric (e.g., mirafi 140N) to prevent the intrusion of fines.
9. Following the proof-rolling, undercutting, and replacing, thoroughly
and uniformly compact, the entire subgrade to density the underlying
layers to create a solid platform for filling, operations and foundation
construction.
13 | P a g e
property including but not limiting to; existing streets, sidewalks, site
structures, buildings, and utilities.
2. To prevent damage and instability after formwork removal, the contractor
shall design and install temporary shoring, bracing, and supports to resist all
dead, construction, and live loads, including backfilling and tamping
operations. All shoring, bracing, and supports for concrete elements shall
remain in place until the concrete has attained at least 75 percent of its
specified 28 day ultimate compressive strength verified through ASTM C39
testing of concrete cylinder specimens.
3. All temporary shoring, bracing, and supports shall remain securely in place
until the new primary structural components have been installed, cured, and
connected.
d. Strip all existing top soil, fill, organic, loose, disturbed, and otherwise unsuitable
materials.
e. Following striping, over-excavate any remaining loose soil. Note that this over-
excavation is a minimum and is not to be construed as limiting in any way the
amount of over-excavation necessary to remove all existing top soil, fill, and
organic, loose, disturbed, and otherwise unsuitable materials and reach
underlying competent soil bearing strata.
h. Place select (structural) fill in lifts having a maximum loose thickness of 200 mm
(for machine compaction; 100 mm for hand-operated compaction). Each lift
shall be compacted to a minimum of 95 percent of its maximum modified
proctor dry density as determined by the nuclear density method (ASTM
D6938). All fill shall be select (structural) fill complying with type 1 as defined in
specification section 02200-2.1.
l. Compaction test (FDT) will be carried out for the backfilling to obtain a
minimum of 95% of the maximum dry density for the materials. Test shall be
conducted in each layer.
n. Backfilling shall continue uniform around the shaft to ensure the stability
during backfilling over the effective length of pit.it must be inspected by RC
Engineer/Aramco Engineer.
15 | P a g e
5.4 CONCRETE WORKS
All concrete work will be carried out according to Specifi cati on 0330 0
for Concrete Works.
b. Reinforcing steel all reinforcing steel to be high strength, high bond bars
conforming to the requirement of AASHTO M31 GRADE-60.
c. Cement used in concrete permanently exposed to earth or rock shall be as per
royal commission general design criteria and technical guidelines, 4th edition
(RCGDCTG-4ED)
d. Cement used in reinforced and pre stressed concrete in structural element
other than those exposed to earth shall be ASTM type - 1.
e. All embedded steel items in concrete such as bolts, opening cover, etc. shall be
stainless steel.
f. All bars details, hooks, splices and bending schedules shall be in accordance with
AASHTO LFRD bridge design specification (2014) with interim revisions (2015) &
(2016) and ACI detailing manual (ACI-315) with the latest addendum.
16 | P a g e
g. Minimum cement content and maximum water cement ratio for all foundations
concrete shall be as per soil report recommendations.
h. All exposed concrete edges shall be chamfered 20mm.
i. Concrete cover unless shown otherwise the minimum concrete cover from
surface to the face of the nearest reinforcing bar shall be as follows:
a. Superstructures
i) Deck slab -30 mm
ii) Pre stressing steel and main reinforcement-50 mm
iii) Stirrups & ties-50 mm
b. Substructures / foundations
i) Unformed surface cast against earth.................. 75 mm
ii) Formed surface exposed to earth ........................ 75 mm
iii) Formed surface exposed to weather.................... 50 mm
For assuring the area must be compacted with Survey Verification prior to
Blinding and Waterproofing. Footing Reinforcement must be as per approved
Shop Drawings and RC Standard. Formwork must be inspected by RC Engineer
prior to Concreting. Refer Shop Drawings Attached for more Information.
a. Approved granular material that will produce a dense, well compacted back fill
shall be used for back filling at abutments and retaining walls. The fill shall be
compacted at optimum moisture content to 95% of the maximum dry density as
determined by modified proctor test (ASTM D-1557)
b. The backfill against the abutments shall be completed before installing of the
girders on the abutments.
e. The footing excavation base shall be compacted to at least 95% of the maximum
dry density as determined by modified proctor test (ASTM D-1557)
f. As per M.O.T highway design manual, the foundation depth on rock shall be as
required from design considerations but not less than 1.5m embedment into
weak rock and not less than 0.5m into sound rock.
g. All concrete surfaces in contact with soil shall be waterproofed as per
geotechnical report recommendations and project specifications.
18 | P a g e
h. Surface water shall be deviated from foundation excavation site.
i. Footings shall be placed on natural soil and all fill/loose layers shall be removed
if encountered.
j. Excavation supports and protection systems capable of safely resisting soil and
groundwater pressure, shall be designed, provided, installed, monitored and
maintained where needed for supporting the sides of the excavation in a
manner accepted to the engineer at the contractor's sole risk and responsibility.
The contractor is also held responsible for removing the excavation supports and
protection systems when they are no longer needed without disturbing the
underlying soils or causing any damage to the adjacent structures, utilities,
pavements or other facilities.
k. The natural soil at the recommended excavation level shall be thoroughly
inspected by the engineer to ensure that all the loose layers are totally removed.
Any soft spots, silty or clayey pockets or other inferior materials encountered at
the excavation levels shall be totally removed.
l. The natural soil at the recommended excavation levels should be compacted by
heavy vibratory compactor not less than 12 ton capacity. The compaction
procedure should be repeated at least three times.
m. Angle of internal friction for backfill materials behind retaining walls shall be 35°
coefficient of lateral earth pressure is assumed to be 0.27.
n. coefficient of base sliding friction is assumed to be 0.45
o. According to geotechnical report (rev.03) ground water was encountered in all
of the drilled boreholes at approximate depth ranging from +2.009 to 7.803m
below the existing ground surface. it should be mentioned that the water level is
unstable and is subjected to seasonal variations. However, no cavities were
encountered in any of the boreholes to the drilled depths.
p. According to geotechnical report no. 2019/122, dated 20 December 2020,
rev.03, titled geotechnical investigation for construction of roads & utilities for
realigned tama from SWCC corridor to maajiz road project no. pic-i-t-7062
Yanbu, kingdom of Saudi Arabia, the recommended net allowable bearing
pressure is (325 KPA) and the modulus of soil subgrade reaction is (19500
kpa/m) for all foundations.
q. During the curing process of the large volume of concrete (mass concrete)
elements such as footings, abutments etc. rather large temperature difference
(due to cement hydration) can be developed between the concrete surface of
such structural element and its core. the concrete is then subject to high thermal
stresses which can result in cracking and loss of structural.
19 | P a g e
r. During construction, a drainage system with possibly pumping facilities should
be provided on site to avoid flooding during rainfall season and surface run-off
waters.
s. All forms and false work shall be approved by the engineer.
t. Corrosion protection of concrete surfaces shall follow royal commission
guideline drawings no. RC-S-13 (sheets 1 and 2).
For assuring the area must be survey level verification prior to installation of
reinforcement and formwork and must be as per approved shop drawings and
RC standard. Reinforcement formwork must be inspected by RC engineer prior
to concreting. Refer shop drawings attached for more information. Abutment is
divided in to two parts “A1” & “A2”.
a. The backfill against the abutments shall be completed prior to installing of the
girders on the abutments.
b. The top faces of piers and abutment bearing shelves, other than the bearing
seats, shall have a minimum slope of 5 percent toward their edges.
c. During the curing process of the large volume of concrete (mass concrete)
elements such as footings, abutments etc. rather large temperature difference
(due to cement hydration) can be developed between the concrete surface of
such structural element and its core. The concrete is then subject to high
thermal stresses which can result in cracking and loss of structural integrity,
therefor. The contractor shall take adequate precautions for
controlling/Reducing such temperature gradient subject to RC Engineers
approval.
d. During construction. A drainage system with possibly pumping facilities should
be provided on site to avoid flooding during rainfall season and surface run-off
waters.
e. All forms and false work shall be approved by the engineer.
f. Corrosion protection of concrete surfaces shall follow royal commission
guideline drawings no. RC-S-13 (sheets 1 and 2).
20 | P a g e
For assuring the area must be survey level verification prior to installation of
reinforcement with formwork must be as per approved shop drawings and RC
standard. Formwork must be inspected by RC engineer prior to concreting.
Refer shop drawings attached for more information.
A. Top surface of the top flange of precast pre stressed girder shall be cleaned &
intentionally roughened to a full amplitude of 6.0mm.
B. Box Girder is a section of bridge in which the main beams comprise girder in the
shape of hollow box .The Box normally comprises pre stressed concrete with
epoxy coated structure steel.
For assuring the area must be survey level verification prior to installation of
reinforcement and formwork and must be as per approved shop drawings and
RC standard. Reinforcement, formwork must be inspected by RC engineer prior
to concreting. Refer shop drawings attached for more information.
A. The top surface of bridge deck shall be protected by waterproofing membrane in
accordance with MOT general specifications.
B. At the bridge deck expansion joint locations, the following concrete surfaces
shall be water Proofed using two coats of bituminous paint. Vertical faces of
bridge deck & girder ends. Top surface of abutment bearing shelves. Vertical
front faces of abutment back walls.
21 | P a g e
C. During construction, a drainage system with possibly pumping facilities should
be provided on Site to avoid flooding during rainfall season and surface run-off
waters.
D. All forms and false work shall be approved by the engineer.
E. Corrosion protection of concrete surfaces shall follow royal commission
guideline drawings no. RC-S-13 (sheets 1 and 2).
F. Scaffolding design must have approved prior to installation based on the load of
structure.
G. Scaffolding is properly installed for deck slab with the help of wood and steel
Materials approved materials.
H. Scaffolding must be stiffer to bear the load of structural concrete hence it must
be properly installed by skilled workers in the supervision of CM/PM.
I. RC Engineer must have to check and approved the scaffolding prior to structural
concrete pouring.
For assuring the area must be Survey level Verification prior to Installation of
Reinforcement and Formwork and must be as per approved Shop Drawings and
RC Standard. Reinforcement, Formwork must be inspected by RC Engineer
prior to Concreting. Refer Shop Drawings Attached for more Information. Wing
wall footing must install to bear the load properly to wing wall. All concrete
22 | P a g e
surfaces in contact with soil shall be waterproofed as per geotechnical report
recommendations and project specifications.
For assuring the area must be Survey level Verification prior to Installation of
Reinforcement and Formwork and must be as per approved Shop Drawings and RC
Standard. Reinforcement, Formwork must be inspected by RC Engineer prior to
Concreting. Refer Shop Drawings Attached for more Information. Approach slab
must install 5 meter width as per approved shop drawing. Concrete must be
35N/mm² micro silica.
For assuring the area must be Survey level Verification prior to Installation of
Reinforcement and Formwork and must be as per approved Shop Drawings and RC
Standard. Reinforcement, Formwork must be inspected by RC Engineer prior to
Concreting. Refer Shop Drawings Attached for more Information.it should be
installed all around the bridge. Refer Shop drawings for details. Concrete must be
35N/mm² micro silica.
UPVC Pipes of Drainage 150mmØ Scupper shall be used with Jersey barrier for
drainage purpose. Depressed 300mm area radius half circle around each drainage
pipe provide heavy duty road gully. Bridge 4 Place at the Corner adjacent to Jersey
barrier UPVC Pipe scupper 150mm-200mm shall be used and free Discharge at
bottom .Refer Drawing 7062-SE-A1-116 for more details.
For assuring the area must be Survey level Verification prior to Installation of
Guard Rail as per approved Shop Drawings and RC Standard. Refer Civil Drawings
and slope as per Road Drawings.
23 | P a g e
5.18 Finishing and Painting and Décor Work for Bridge
For assuring the area must be painted and decor as per approved shop drawings
and RC standard. Protective coating using saline treatment and paint (or other
proven treatment) shall be applied to the exposed concrete surface of the bridge
in accordance with the project data specifications subject to the engineer's
approval.
Load Test shall be conducted for durability and long-life rate as the most
important characteristics of Bridge Materials or System.
Bridge shall be tested for durability and long-life rate as the most important
characteristics of Bridge Materials or System.
Nondestructive load testing is an effective approach to measure the structural
response of a bridge under various loading condition and to determine its structural
integrity. This load test Program integrates optical surveying system, a sensor
network embedded in bridge decks, and surface deflection.
The area will be secured and will install warning signs, symbols prior to start work.
Safety Officers will check / inspect the working area before start the work.
26 | P a g e
SAMA Construction for Trading & Contracting
Limited
Project No. PIC I -T-7062
Documents Type:
Method Revision No.: 00 Revision Date:
Statement
Documents Title: Method of Statement for Construction of Bridge-042
8 Attachments:
27 | P a g e