Professional Documents
Culture Documents
Design discharge (power) 5.00 m3/s Manning ''n' for concrete 0.015
Flood discharge (peak) 400 m3/s Manning ''n' for steel 0.013
River width at weir 40.0 m Manning ''n' for river 0.030
River bed EL. at weir 1465 m.a.s.l Hazen - Williams Coefficient 120
Peaking time for forebay 0.1 hrs Depth of forebay (at start) 8.00 m
Proposed width (shorter dim) 20.0 m
Channel side slope (1v : zh) 0 0=Rect. Channel Propose bed width of tailrace 2.50 m
Page 1 of 135
Length of tailrace 150 m NSL at tailrace end 1298.00 m.a.s.l
INPUT SHEET - 2
Page 2 of 135
Site Geology - Max.wall thickness of penstock 11.0 mm
Page 3 of 135
DESIGN SUMMARY
CONN. CHANNEL #VALUE! 1.44 100.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
POWER CHANNEL 2.50 2.24 5000.00 5.007 #VALUE! #VALUE! #VALUE! #VALUE!
Page 4 of 135
* 20 days shutdown period has been considered for annual energy output computations by Flow Duration Method
DESIGN CHECKS
Page 5 of 135
Page 6 of 135
ANNUAL ENRGY
(days) (%) (days) (m3/s) (m) (m3/s) (%) (GWh) (m3/s) (%) (GWh) (m3/s) (%) (GWh) (GWh)
0 0.0% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
5 1.4% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
10 2.7% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
15 4.1% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
20 5.5% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
25 6.8% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
Page 7 of 135
ANNUAL ENRGY
(days) (%) (days) (m3/s) (m) (m3/s) (%) (GWh) (m3/s) (%) (GWh) (m3/s) (%) (GWh) (GWh)
30 8.2% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
35 9.6% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
40 11.0% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
45 12.3% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
50 13.7% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
55 15.1% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
60 16.4% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
65 17.8% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
70 19.2% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
75 20.5% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
80 21.9% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
85 23.3% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
90 24.7% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
95 26.0% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
100 27.4% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
105 28.8% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
110 30.1% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
115 31.5% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
120 32.9% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
125 34.2% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
Page 8 of 135
ANNUAL ENRGY
(days) (%) (days) (m3/s) (m) (m3/s) (%) (GWh) (m3/s) (%) (GWh) (m3/s) (%) (GWh) (GWh)
130 35.6% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
135 37.0% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
140 38.4% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
145 39.7% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
150 41.1% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
155 42.5% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
160 43.8% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
165 45.2% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
170 46.6% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
175 47.9% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
180 49.3% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
185 50.7% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
190 52.1% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
195 53.4% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
200 54.8% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
205 56.2% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
210 57.5% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
215 58.9% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
220 60.3% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
225 61.6% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
Page 9 of 135
ANNUAL ENRGY
(days) (%) (days) (m3/s) (m) (m3/s) (%) (GWh) (m3/s) (%) (GWh) (m3/s) (%) (GWh) (GWh)
230 63.0% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
235 64.4% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
240 65.8% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
245 67.1% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
250 68.5% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
255 69.9% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
260 71.2% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
265 72.6% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
270 74.0% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
275 75.3% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
280 76.7% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
285 78.1% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
290 79.5% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
295 80.8% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
300 82.2% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
305 83.6% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
310 84.9% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
315 86.3% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
320 87.7% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
325 89.0% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
Page 10 of 135
ANNUAL ENRGY
(days) (%) (days) (m3/s) (m) (m3/s) (%) (GWh) (m3/s) (%) (GWh) (m3/s) (%) (GWh) (GWh)
330 90.4% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
335 91.8% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
340 93.2% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
345 94.5% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
350 95.9% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
355 97.3% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
360 98.6% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
365 100.0% 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
Actual Energy
Plant Factor = #VALUE! =
Theoretical Energy
Page 11 of 135
GROSS CAPACITY AND ENERGY OUTPUT CALCULATIONS
Month Days 10-daily Headrace Sandtrap Turbine Tailwater Headwater Tailwater Gross Head Net Power Energy
avg. inflows flows at flushing flows flows elevation elevation head losses head capacity output
at weir site intake flows "N100"
(m3/s) (m3/s) (m3/s) (m3/s) (m3/s) (masl) (masl) (m) (m) (m) (MW) (GWh)
0.9
10.0
0.8
Power (MW)
0.7
8.0
0.6
6.0 0.5
0.4
4.0
0.3
0.2
2.0
0.1
0.0 0.0
AY L T
JA
N
FE
B AR AP
R
JU
N JU AU
G
SE
P
OC NO
V
DE
C
M M
Average Year (10-Daily Intervals)
Power 'Qd' (MW) Monthly Flows (cumecs) Cum. Energy 'Qd' (GWh)
TYROLEAN WEIR
INPUT
- BASIC DATA
- FLOOD DISCHARGE
Where:
Discharge coefficient C = #VALUE! Ref: DOSD, SI Units
Page 14 of 135
TYROLEAN WEIR
Depth Discharge
Weir - Rating Curve 0.0 0.00
1.0
0.9 #VALUE! #VALUE!
0.8 #VALUE! #VALUE!
0.7 #VALUE! #VALUE!
0.6
#VALUE! #VALUE!
0.5
#VALUE! #VALUE!
0.4
#VALUE! #VALUE!
0.3
#VALUE! #VALUE!
0.2
0.1 #VALUE! #VALUE!
- TRASHRACK
2
Initial water height h= kho Ref: GTZ, Intakes
3
Depth at upstream edge of rack h = #VALUE! m
a
Coefficient c=0 . 6 cos 3/2 β
d
Coefficient c = 0.28
2
Discharge to be diverted Q A= cμ bLI √ 2 gh Ref: GTZ, Intakes
3
µ= 0.84
Let width of trashrack along river b = 10.0 m (designed)
Assuming 20% blockage due to stones b = 8.0 m
Width along trashrack (with blockage) b (m) = 6.0 8.0 10.0 12.0
Length of trashrack L (m) = #VALUE! ### ### ###
- GEOMETRY OF WEIR
Page 15 of 135
TYROLEAN WEIR
DESIGN LEVELS
Top EL: of u/s stone apron ELTUS = 1465.00 m a.s.l.
Bed EL: of u/s stone apron ELBUS = 1464.00 m a.s.l.
Crest EL: of trashrack section CLTS = 1465.30 m a.s.l.
Crest EL: of overflow section CLOS = 1465.80 m a.s.l.
Top EL: of u/s side wall TLUW = #VALUE! m a.s.l. F.B. = 0.50
Top EL: of d/s side wall TLDW = #VALUE! m a.s.l.
The length of stilling basin may be reduced due to economic considerations, keeping in
view the fact that the boulders carried by the river/nullah during flood season will deposit in
the stilling basin providing an armouring layer. A cutt-off wall to bed rock of suitable depth
should also be provided for added protection against undermining by scour.
Page 16 of 135
TYROLEAN WEIR
Elevation (m asl)
Longitudinal Section
1467.0
1466.0
1465.8
1465.0
X-Section
1465.9
1465.8
5.0 ### 45.0 1465.8 34.5 1465.8
1465.7 5.0 1465.8 45.0 #VALUE! 34.5 #VALUE!
1465.1 ###
1465.0
0.0 5.0 10.0 15.0 Distance
20.0 (m)
25.0 30.0 35.0 40.0 45.0 50.0
Page 17 of 135
TYROLEAN WEIR
2/ 3
Bt
Mannings Formula (rect. channels) Q A =Btk S I 1/ 2 ( B+2 t )
6.00 = #VALUE!
Depth Discharge
0.0 #VALUE!
1.2
Embedded Channel - Rating Curve 0.1 #VALUE!
0.2 #VALUE!
1.0
0.3 #VALUE!
0.8 0.4 #VALUE!
FRICTION LOSS 2
2V L
Friction headloss (Manning) h f =n 4 / 3
R
Velocity in embedded channel V = #VALUE! m/s
Hydraulic radius R = #VALUE! m
Page 18 of 135
TYROLEAN WEIR
- STILLING BASIN
Energy Dissipaters
Stilling
Froude No. Chute Baffle
Basin type End Sill
Blocks Blocks
Not Not
1.7 ≥ F ≤ 2.5 Type I Required Required
Not Required
w=D1 (max.)
Height from
s=2.5w
graph
h=2D1 Not
2.5 ≥ F ≤ 4.5 Type IV Required
upper
surface
Slope 2:1
sloped at 5º
D/S
Page 19 of 135
TYROLEAN WEIR
Dentated Sill
Not h=0.2D2
F > 4.5, v > 60 ft/s Type II h=w=s=D1
Required
w=0.15D2
s=0.15D2
(m a.s.l.) (m3/s)
1,472 1464.0 0.0
1464.5 15.7
1,470
1465.0 49.0
1,468 1465.5 94.8
1466.0 150.7
1,466
1467.0 287.6
1,464 1467.5 366.6
1
Manning's Equation Q= A R 2/3 S1/2
n
Page 20 of 135
TYROLEAN WEIR
D1
Ratio of conjugate depths =0 . 5 ( √ 1+8 F 2R 2 −1 ) Ref: C. Nalluri
D2
D2
Alternatively =0 . 5 ( √ 1+8 F 2R 1 −1 )
D1
Depth before the jump D1 = #VALUE! m
Flow velocity - before the jump V1 = #VALUE! m/s
Froude Number - before the jump FR1 = #VALUE! dimensionless
3
Energy loss through the jump ( D2 −D1 ) Ref: C. Nalluri
E L=
4 D2 D1
" " " " EL = #VALUE!
Alternatively
D2
Length of stilling basin LB =4 . 5 Ref: L.W. Mays
F 0R .38
" " " " LB = #VALUE! m
Alternatively
1. 5
Length of stilling basin LB=KD 1 F 1 Ref: Paterka
Stilling basin with a sloping end sill and one or two rows of baffle blocks 2
Page 21 of 135
TYROLEAN WEIR
CREEP LENGTH
Page 22 of 135
TYROLEAN WEIR
1
Total creep length (by Lane) ∑ Lcr =∑ Lv + 3 ∑ Lh
Where:
Total creep length in vertical direction ΣLv = 12.50 m
UPLIFT FORCE
Lx
The uplift force at any point 'x'
Where:
u x=h− H x + ( C )
Uplift pressure head = ux m
The u/s water depth = h m
El. at point 'x' relative to river bed = Hx m
Creep length upto point 'x' = Lx m
FLOOR THICKNESS
h
The thickness of d/s floor t=1 .33 ( ) G−1
The thickness of d/s floor at; h G-1 t (m)
1 At toe of glacis = #VALUE! 1.4 ###
2 At center of stilling basin = #VALUE! 1.4 ###
3 At end of stilling basin = #VALUE! 1.4 ###
W
Factor of safety against uplift FSu =
Fu
Page 23 of 135
TYROLEAN WEIR
W
FSu =
Fu
Factor of safety against uplift FSu = #VALUE!
γF
Critical hydraulic gradient I crit .=( 1−n )
( γW
−1
) Ref: GTZ, Intakes
Δh
Existing gradient at critical point 'f' I exist .=
n S Δn S
ΔnS ≈ 0.17 m
Page 24 of 135
TYROLEAN WEIR
0 0
0 -0.80 0 -0.80
0 ### -0.80 -0.80
#VALUE! ###
#VALUE! ### ###
#VALUE! ### ###
#VALUE! ###
#VALUE! ###
0.25 0.00
0 0
Page 25 of 135
TYROLEAN WEIR
VERTICAL FORCES
Weight of structure G = W1 + W2 +W3
" " " " " = #VALUE! kN
Water surcharge WV
HORIZONTAL FORCES
Force due to headwater WH1e =
" " " " WH1e = #VALUE! kN
vG = #VALUE!
Page 26 of 135
TYROLEAN WEIR
- CONCRETE VOLUME
1 2
Concrete quantity in end sill Ces =Ls [ d +t d + d ( d t )
2 es sb 2 es es es sb 2 ]
Concrete quantity in end sill Ces = 35.00 m3
1
Concrete quantity in stilling basin
[
C sb =Ls L B t sb 2 + LB ( t sb 1−t sb 2 )
2 ]
Concrete quantity in stilling basin Csb = #VALUE! m3
A r = ( b + zy ) y
Page 27 of 135
TYROLEAN WEIR
Flow area A r = ( b + zy ) y
Wetted perimeter P r =b +2 y √ 1 + z 2
Flow velocity 1
V = S 1/2 R2/ 3
n
Flow velocity V = 6.69 m/s
Discharge capacity Qr = 200.0 m3/s
q2
Approach velocity head ha =
2 g ( P+ H o )2
Approach velocity head ha = #VALUE! m
and ha / Hmax = #VALUE!
Page 28 of 135
TYROLEAN WEIR
Parameters of the crest geometry are determined from the above figure.
K = #VALUE! n = ###
Xc / Hmax = #VALUE! Yc/Hmax = ###
R1 / Hmax = #VALUE! R2/Hmax = ###
Slope of weir d/s of crest Sd/s = 2.00 H/V
The origin of X - Y axis is at the crest of spillway and Xc is distance from the u/s face to crest.
Page 29 of 135
TYROLEAN WEIR
n
Y X
Ho
=− K
Ho ( )
X = #VALUE! ###
Y = #VALUE! ###
n
Xt
Y-coordinate of tangent point Y t =−H max K
( )
H max
" " " " " Yt = #VALUE! m
X Y
Hydraulic Profile
1.00 #VALUE! #VALUE!
0.90 #VALUE! #VALUE!
0.80 #VALUE! #VALUE!
0.70 0.00 0.00
0.60 #VALUE! #VALUE!
0.50 #VALUE! #VALUE!
0.40 #VALUE! #VALUE!
0.30 #VALUE! #VALUE!
0.20 #VALUE! #VALUE!
0.10 #VALUE! #VALUE!
0.00 #VALUE! #VALUE!
0.00 0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80 0.90 1.00 #VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
Page 30 of 135
TYROLEAN WEIR
Page 31 of 135
TYROLEAN WEIR
f: DOSD, SI Units
Page 32 of 135
TYROLEAN WEIR
Page 33 of 135
TYROLEAN WEIR
m)
s ratios become
Page 34 of 135
TYROLEAN WEIR
Page 35 of 135
TYROLEAN WEIR
gravel, sand
Page 36 of 135
TYROLEAN WEIR
Page 37 of 135
TYROLEAN WEIR
Page 38 of 135
sc-01
Page 39
sc-02
Page 40
sc-03
Page 41
sc-04
Page 42
CONNECTING CHANNEL
INPUT
- BASIC DATA
12
0 ###
10
0 ###
8 #VALUE! ###
#VALUE! ###
6
0 ###
4 #VALUE! ###
2
0
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1
SCOURING SLOPE
To avoid accumulation of particles in the connencting channel a suitable scouring slope
should be estimated as follows.
Page 43 of 135
CONNECTING CHANNEL
1
Mannings equation V = S 1/2 R2/3 Ref: C.V. Davis
n
Area=( b+ zy ) y
Flow area A
" " " " " = #VALUE! m2
Perimeter=b+2 y √1+ z 2
Wetted perimeter P
" " " " " = #VALUE! m
Topwidth=b +2 zy
Top width T
" " " " " = #VALUE! m
A
Hydraulic depth D D=
" " " " " = #VALUE! m
T
Hrdraulic radius R
A
R=
" " " " " = #VALUE! m P
Flow velocity V
" " " " " = #VALUE! m/s #VALUE!
Discharge capacity Q Q= AV
" " " " " = #VALUE! m /s3
Q
Unit discharge q q=
" " " " " = #VALUE! m3/s/m b
1/3
q2
Criticaldepth=
g ( ) Ref: L.W. Mays
Page 44 of 135
CONNECTING CHANNEL
2 1/3
Criticaldepth= ( qg )
Critical depth yc
Critical depth " = #VALUE! m
V
F r=
√ gD
Froude number Fr
" " " " " = #VALUE!
- HEADLOSSES
FRICTION LOSS
2
V L
Friction headloss (Manning) h f =n2
R4 / 3
Friction headloss (Manning) hf = #VALUE! m
BEND LOSS
The channel bends should have a centerline radius of 3T to 5T or more, where ‘T’ is the
water surface width of the design flow. If the radius must be reduced, the head loss at
channel bends can be estimated as;
2
v
Headloss at bends h L=K
Where:
2g
K = 2 x (B / Rc), Rc = center-line radius, B = channel width
- RATING CURVE
Elevation Flow
#VALUE! #VALUE!
#VALUE! #VALUE!
4.0
2.0
Page 45 of 135
0.0
Flow (cumecs)
0.00 2.00 4.00 6.00 8.00 10.00 12.00
W at e
12.0
Rating Curve (Connecting Channel)
10.0
CONNECTING CHANNEL
8.0
6.0
Longitudinal Profile
12.0 0 #VALUE! #VALUE! #VALUE!
100.0 #VALUE! #VALUE! #VALUE!
10.0
8.0
6.0
4.0
2.0
0.0
0 20 40
Distance (m)60 80 100 120
- SURGE CALCULATIONS
Q 1 −Q0
Increase in water level (m) Δy=
( v + √ gy ) b
Increase in water level Δy = #VALUE! m (very rare)
2
v2 v2 v2
SUDDEN CLOSURE OF OUTLET GATE
(if outlet gate has been provided)
Δy max = +
2g √( 2g
+2)2g
D Ref: W.P. Creager
0 .5 v 2 D
Δy max =
2g
+v
g √ Page 46 of 135
CONNECTING CHANNEL
0 .5 v 2 D
GRADUAL CLOSURE OF OUTLET GATE
(if outlet gate has been provided)
Where:
Δy max =
2g
+v
g √
A
Hydraulic depth D = #VALUE! m D=
T
Maximum height of surge wave Δymax = #VALUE! m
As only one gate has been provided at the inlet of connecting channel, therefore
Check Δymax < F.B. = #VALUE! ۩
- SUPER-ELEVATION
2
v T
Rise in water surface above flow depth Δy= Ref: V.T. Chow
Where: 2 gr
Radius of bend / curve r = #VALUE! m r=5 T
- CONCRETE VOLUME
1
Concrete quantity in side walls
(
C S = wt hc + h c ( w b −wt ) 2 L
2 )
Concrete quantity in side walls CS = 71.92 m3
Page 47 of 135
CONNECTING CHANNEL
12
0.0 ### ### #VALUE!
10 0.0 ### ### #VALUE!
0
0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7
Page 48 of 135
SANDTRAP
DESIGN OF SANDTRAP
INPUT
- BASIC DATA
FLOW VELOCITY
SETTLING VELOCITY
Page 49 of 135
SANDTRAP
100
Alternatively: v s' = ( √ 1+1 . 57∗102 d 3 −1 ) mm/s
9d
(for T 20 & grain to water density ratio of 2.65)
o
Ref: ESHA Guide
Alternatively:
H
Transit time t=
v s ' −αv d
Transit time t = 172.25 sec
Qt d
Width of chamber B=
LH L
where t d=
Q vd
B=
vd H
Page 50 of 135
SANDTRAP
L
t d=
Therefore width of chamber Q vd
B=
vd H
CRITICAL VELOCITY
1 HB 0 .03 ( ρ−1 ) ρ
Critical velocity v cr = (
n 2H +B )√ 1000
m/s
Ref: ESHA Guide
Critical velocity vcr = 0.278 m/s
Page 51 of 135
SANDTRAP
- TRAP EFFICIENCY
−Lv s '
Constant e = 2.718
60%
40% 34%
20% 11%
0%
0.5 mm 0.25 mmParticle
0.2Size
mm(mm) 0.1 mm 0.05 mm
- FINAL DIMENSIONS
B−W fc
Total height of chamber H TS =f . b .+t t + H+ +W fc +t b
2
Total height of chamber (at start) HTS = 7.20 m
Total height at deepest point (at end) HTE = 8.64 m
Page 52 of 135
SANDTRAP
- TRASHRACK
bra b
n
Number of rack bars bt
" " " n = 44.1 no.
Page 53 of 135
SANDTRAP
- HEADLOSSES
FRICTION LOSS
2
V L
2
Friction headloss (Manning)
h f =n 4 / 3
R
2
W fc + B B−W fc
Flow area (per chamber) A =BH +W fc ( 2
+)( 2 )
Flow area (per chamber) A = 17.10 m2
2
ENTRANCE LOSS v Ref: Mosonyi
h L=K
2g
Page 54 of 135
SANDTRAP
2
v
h L=K K= 0.10
2g
Entrance headloss hLE = #VALUE! m
TRASHRACK LOSS
Page 55 of 135
SANDTRAP
- LONGITUDINAL SECTION
Longitudinal
2.0 Section
### 2.0 #VALUE! #VALUE! #VALUE! #VALUE!
12.0
2.5 ### 2.7 #VALUE! #VALUE! #VALUE! #VALUE!
#VALUE! ###
Elevation (m asl)
X - Section
12.0
8.0
SANDTRAP
Elevation (m asl)
X - Section
12.0
2 ### 9.90 #VALUE! 5.90 #VALUE!
- TRANSITION LENGTH
Page 57 of 135
SANDTRAP
Page 58 of 135
SANDTRAP
D+ K
Minimum thickness of steel sheet t min= (K = 500 & D in mm)
400 Ref: Warnick
Minimum thickness of steel sheet tmin = 3.75 mm
Corrosion allowance ca = 1.00 mm
A s=
π d i +2 (
1000 ) −
πd 2i
4 4
X-sectional area of steel As = 0.019 m2
Page 59 of 135
SANDTRAP
C B =( b+ 2 wb +2 ws ) t s L
Concrete quantity in bottom slab CB = 45.60 m3
1
(
C S = wt hc + h c ( w b −wt ) 2 L
2 )
Concrete quantity in side walls CS = 42.00 m3
Cts =( b+2 wt ) t t L
Concrete quantity in top slab Cts = 0.00 m3
Page 60 of 135
0
0.0 0.2 0.4 0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0
8
6
SANDTRAP
0
0.0 0.2 0.4 0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0
- SPILLING ARRANGEMENT
A side channel spillway arrangement is recommended for spilling the excess flows diverted
from the Tyrolean weir during high flow (Summer) season. In the absence of such spilling
arrangement the excess flows will be carried by the Power Channel all the way to the Forebay
causing some spillage along the Power Channel which is least desirable.
3/2
Discharge over ogee crest Q=CLS H Ref: C.V. Davis
" " " " Qs = 4.52 m /s
3
Check Q s ≥ QD = FAIL ۩
SPILL CHANNEL
Length of spill channel (Δx) LSP = 80.0 m
Bed width of spill channel b = #VALUE! m
Depth of water in spill channel y = 0.88 m Ref: C.V. Davis
Total depth of spill channel hc = #VALUE! m
Free board in spill channel F.B. = #VALUE! m fb s≥0. 4 y c
12
10
0 ###
8
0 ###
6 #VALUE! ###
4 #VALUE! ###
2 0 ###
#VALUE! ###
0
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1
Page 61 of 135
6
2 SANDTRAP
0
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1
2/3
1 by
Manning's Equation Q= byS1s /2
n b+2 y ( )
Flow velocity in spill channel vS = #VALUE! m/s
Qs
Unit discharge of spill channel qs = #VALUE! m3/s/m q s=
ws
1/ 3
q 2s
Critical depth in spill channel
yc=( ) g
" " " " " yc = #VALUE! m
Elevation Flow
#VALUE! #VALUE!
#VALUE! #VALUE!
C B =( b+ 2 wb +2 ws ) t s L
Page 62 of 135
SANDTRAP
1
(
C S = wt hc + h c ( w b −wt ) 2 L
2 )
Concrete quantity in side walls CS = #VALUE! m3
Cts =( b+2 wt ) t t L
Concrete quantity in top slab Cts = 0.00 m3
0
0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7
Page 63 of 135
POWER CHANNEL
INPUT
- BASIC DATA
12.0
0 ###
10.0 0 ###
2.5 ###
8.0
2.5 ###
6.0 0 ###
2.5 ###
4.0
2.0
0.0
0 0.5 1 1.5 2 2.5 3
1
Mannings equation V = S 1/2 R2/3 Ref: C.V. Davis
n
Area=( b+zy ) y
Flow area A
" " " " " = 4.343 m2
Perimeter=b+2 y √ 1+ z 2
Page 64 of 135
POWER CHANNEL
Wetted perimeter P
" " " " " = 5.97 m
Topwidth=b +2 zy
Top width T
" " " " " = 2.50 m
A
Hydraulic depth D D=
T
" " " " " = 1.74 m
A
Hrdraulic radius R R=
" " " " " = 0.73 m
P
Flow velocity V
" " " " " = 1.15 m/s 1.15
Discharge capacity Q
" " " " " = 5.00 m3/s
Check Q ≥ Qd = O.K. ۩
Q
Unit discharge q q=
" " " " " = 2.00 m3/s/m b
2 1/3
q
Criticaldepth=
g ( ) Ref: L.W. Mays
Critical depth yc
" " " " " = 0.74 m
Fr
V
Froude number F r=
" " " " " = 0.28 √ gD
Page 65 of 135
POWER CHANNEL
- HEADLOSSES
2
v Ref: Mosonyi
ENTRANCE LOSS h L=K
2g K= 0.10
FRICTION LOSS 2
V L2
Friction headloss (Manning) h f =n 4 /3
R
Friction headloss (Manning) hf = 5.00 m
BEND LOSS
The channel bends should have a centerline radius of 3T to 5T or more, where ‘T’ is the
water surface width of the design flow. If the radius must be reduced, the head loss at
channel bends can be estimated as;
2
v
Headloss at bends h L=K
2g
Where:
K = 2 x (B / Rc), Rc = center-line radius, B = channel width
- RATING CURVE
W at e r Ele vati o n (m asl)
Elevation Flow
#VALUE! #VALUE!
#VALUE! #VALUE!
1 2.0
Rating Curve #VALUE! #VALUE!
#VALUE! #VALUE!
1 0.0
#VALUE! #VALUE!
8.0
#VALUE! #VALUE!
6.0
#VALUE! #VALUE!
4.0
2.0
0.0
Flow (cumecs) Page 66 of 135
0.00 2.00 4.00 6.00 8.00 10.00 12.00
Rating Curve
W at
1 2.0
1 0.0
4.0
#VALUE! #VALUE!
2.0
#VALUE! #VALUE!
0.0
Flow (cumecs) #VALUE! #VALUE!
0.00 2.00 4.00 6.00 8.00 10.00 12.00
#VALUE! #VALUE!
12.0
Longitudinal Profile
0 #VALUE! #VALUE! #VALUE!
10.0 5000.0 #VALUE! #VALUE! #VALUE!
8.0
6.0
4.0
2.0
0.0
0 1000 Distance
2000 (m)
3000 4000 5000 6000
- SURGE CALCULATIONS
Q1 −Q 0
Increase in water level (m) Δy=
( v + √ gy ) b
Increase in water level Δymax = 0.38 m (very rare)
2
v2 v2 v2
SUDDEN CLOSURE OF OUTLET GATE Δy max =
2g
+
√( )
2g
+2
2g
D Ref: W.P. Creager
0 .5 v 2 D
GRADUAL CLOSURE OF OUTLET GATE
Where:
Δy max =
2g
+v
g √ A
Hydraulic depth D = 1.74 m D=
T
Page 67 of 135
POWER CHANNEL
A
D=
T
Maximum height of surge wave Δymax = 0.52 m
- SUPER-ELEVATION
2
v T
Rise in water surface above flow depth Δy= Ref: L.W. Mays
Where: 2 gr
Radius of bend / curve r = 12.5 m r=5 T
The channel bends should have a centerline radius of 3T to 5T or more, where ‘T’ is the
water surface width of the design flow.
- CONCRETE VOLUME
(Not applicable to stone masonry channels)
C B =( b+ 2 wb +2 ws ) t s L
Concrete quantity in bottom slab CB = 7800.00 m3
Page 68 of 135
POWER CHANNEL
12
10
0.0 ### 3.2 #VALUE! 0.7 #VALUE!
8 0.0 ### 3.2 #VALUE! 3.2 #VALUE!
0
0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5
Page 69 of 135
HEADRACE PIPE
INPUT
- BASIC DATA
f = 1.25
z
a = 4.141
h = -0.107
θ y
2.50
1
V = S 1/2 R2/3
n
Page 70 of 135
HEADRACE PIPE
1
Mannings equation V = S 1/2 R2/3
n
Flow velocity V
" " " " " = 1.84 m/s O.K.
- HEADLOSSES
FRICTION LOSS
1
Mannings equation V = S 1/ 2 R2/ 3
n 2
V L
Friction headloss (Manning) h f =n2
R4 / 3
Friction headloss (Manning) hf = 5.00 m
2
BEND LOSS v Ref: Mosonyi
h L=K K= 0.15
2g
No. of bends nB = 50 no.
Headloss in bends hLB = 1.29 m
- RATING CURVE
Page 71 of 135
HEADRACE PIPE
Longitudinal Profile
12.0
0 #VALUE! #VALUE! #VALUE!
10.0 5000.0 #VALUE! #VALUE! #VALUE!
8.0
6.0
4.0
2.0
0.0
0 1000 Distance
2000 (m)
3000 4000 5000 6000
- STEEL QUANTITY
D+ K
Minimum thickness of steel sheet t min= (K = 500 & D in mm)
400 Ref: Warnick
Minimum thickness of steel sheet tmin = 7.50 mm
Corrosion allowance ca = 1.00 mm
Page 72 of 135
HEADRACE PIPE
A s=
π d i +2(1000 ) −
πd 2i
4 4
X-sectional area of steel As = 0.095 m2
Page 73 of 135
HEADRACE PIPE
INPUT
- BASIC DATA
2
Alternatively Q o = C √ 2 g D ( H 3/2 3/2
2 −H 1 )
3
Max. possible discharge (conduit flow) QCmax = #VALUE! m3/s
2.50
Page 74 of 135
2.50
HEADRACE PIPE
x2 y2
Elliptical entrance curve (bellmouth) + =1
( 0 . 5 D )2 ( 0 . 15 D )2
2 2 Ref: DOSD
Elliptical entrance curve (square & rect.) x y
+ =1
D ( 0 . 33 D )2
2
For circular pipes D is the diameter while maximum values of 'x' & 'y' are given in plan view as;
Maximum 'x' = 0.65D from pipe centerline and Maximum 'y' = 0.5D from entrance face
However the existing practice in the region is to adopt the bellmouth diameter as 1.5D, therefore
x2
Therefore: y=
√( 1− 2 ( 0 .25 D )
( D) )
2
Elevation (m asl)
x y (low) y (up)
2.500 0.000 0.000 #VALUE! #VALUE!
Longitudinal
2.250 Section
0.272 0.250 #VALUE! #VALUE!
12.0
2.000 0.375 0.500 #VALUE! #VALUE!
10.0
1.750 0.446 0.750 #VALUE! #VALUE!
8.0 1.500 0.500 1.000 #VALUE! #VALUE!
- FRICTION FACTOR
DV
Reynolds number Re = Ref: Davis
where: ν
Kinematic viscosity of water at 20oC ν = 1.0E-06 m2/s
64
For laminar flow f= for laminar flow
Re
1 e/ D 2. 51
For turbulent flow
(Colebrook - White equation) √f
=−2 log 10 +
(
3 . 7 Re √f )
Page 75 of 135
HEADRACE PIPE
1 e/ D 2. 51
√f
=−2 log 10 +
3 . 7 Re √f( )
1 R √f
For hydraulically smooth pipe
√f
=2 log 10 e
2 . 51 ( ) Ref: Von Karman
where:
√f
=2 log 10 3 . 7
e ( )
Roughness height (welded steel) e = 0.600 mm
Ratio e/D = 0.00024
1 = 1.06
Friction factor (Moody) f = 0.01655
- SUBMERGENCE REQUIREMENTS
Ref: ESHA Guide
V
Minimum submergence (by Knauss)
(
S min =D 1+2 .3
√ gD ) 3.68 m
" " " " (by Rohan) S min 1.474V 0.48 D 0.76 2.98 m
Smin
- HEADLOSSES
FRICTION LOSS
1
Mannings equation V = S 1/ 2 R2/ 3
n 2
V L
Headloss (Manning) h f =n2
R4 / 3
Headloss (Manning) hf = 1.64 m
hf
Hazen-Williams equation Q=C u CD 2 . 63 S 0. 54 where S= & Cu=0.278
L
1/0. 54
Q L
Headloss (Hazen-Williams) h f =10. 654
C () D4 . 87
Headloss (Hazen-Williams) hf = 1.71 m
2
L V
Darcy-Weisbach equation h f =f
D 2g
Page 76 of 135
HEADRACE PIPE
2
L V
h f =f
D 2g
Headloss (Darcy-Weisbach) hf = 1.75 m
hf e/ D 2. 51 ν
Average velocity of flow
(Colebrook - White equation)
V =−2 2 gD
√ L
log
( √ )
3 .7
+
D 2 gD
hf
L
1 = 2.39
Friction loss (Colebrook-White) hf = 8.70 m
Headloss Flow
0.00 0.00
0.02 0.50
Friction Headloss Vs Discharge 0.07 1.00
1.80
1.60 0.15 1.50
1.40
0.26 2.00
1.20
0.41 2.50
1.00
0.80
0.59 3.00
2
BEND LOSS v Ref: Mosonyi
h L=K
2g K= 0.15
No. of bends nB = 50 no.
Headloss in bends hLB = 0.40 m
Page 77 of 135
HEADRACE PIPE
- LONGITUDINAL SECTION
Longitudinal Profile
12.0
0 #VALUE! #VALUE! #VALUE!
10.0
5000.0 #VALUE! #VALUE! #VALUE!
8.0
6.0
4.0
2.0
0.0
0 1000
Distance (m)
2000 3000 4000 5000 6000
- WALL THICKNESS
Pw D
Wall thickness required t s= Ref: ESHA Guide
2 σ f kf
Hydrostatic pressure Pw = #VALUE! kN/mm2
Weld efficiency kf = 0.90
Allowable tensile stress σf = 1400 kN/mm2
Corrosion allowance cs = 2.0 mm
D+ K
Minimum thickness of steel sheet t min= (K = 500 & D in mm)
400 Ref: Warnick
Page 78 of 135
HEADRACE PIPE
0 . 1 H max D
Hoop stress σ H= Ref: DPR-Bilgaon
2 te
Hoop stress σH = #VALUE! kgf/cm2
- STEEL QUANTITY
2
ts
A s=
(
π d i +2
1000 ) −
πd 2i
Ref: Davis
As
4 4
X-sectional area of steel = 0.095 m 2
Page 79 of 135
FOREBAY
DESIGN OF FOREBAY
INPUT
- BASIC DATA
- INFLOWS
- OUTFLOWS
- PEAKING TIME
- FOREBAY DIMENSIONS
Page 80 of 135
FOREBAY
W F −D H
Transition length LT = Ref: L.W. Mays
2 tan β
Transition length - horizontal (required) LHT = 32.7 m
Transition length (provided) LHT = 33.0 m
Page 81 of 135
FOREBAY
- HEADLOSSES
FRICTION LOSS
V2L
2
Friction headloss (Manning) h f =n 4 /3
R
Flow area A = 130.00 m2
Wetted perimeter P = 33.00 m
Hydraulic radius R = 3.94 m
Flow velocity V = 0.038 m/s
Page 82 of 135
FOREBAY
- LONGITUDINAL SECTION
(Wall top level will be constant throughout the entire length of forebay including u/s transition)
Wall top level ELWT = #VALUE! m asl
Bed level of forebay at start B.L s = #VALUE! m asl
8.0
6.0
4.0
2.0
Normally a volume of QP x 120 m3 (or two minutes at maximum plant flow) will be
satisfactory for mechanical governors. For digital governors the control volume can
be further reduced
Page 83 of 135
FOREBAY
Initial Final
Forebay Forebay
Time forebay forebay Spill
inflow outflow
volume volume
- TRASHRACK
Page 84 of 135
FOREBAY
- SPILL SECTION
3/2
Discharge over ogee crest Q=CLS H Ref: C.V. Davis
" " " " Q = 14.17 m /s
3
Page 85 of 135
FOREBAY
12
10 0 ###
8
0 ###
#VALUE! ###
6 #VALUE! ###
0 ###
4
#VALUE! ###
2
0
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1
2/3
1 w S dS
Manning's Equation Q= w S d S S 1/2
n S (
w S +2 d S )
Flow velocity in spill channel vS = #VALUE! m/s
Qs
Unit discharge of spill channel qs = #VALUE! m3/s/m q s=
ws
1/ 3
q 2s
Critical depth in spill channel
yc=
g ( )
" " " " " yc = #VALUE! m
W at e r Ele vati o n (m asl)
Page 86 of 135
1 2.0
Rating Curve (Spill Channel Option)
1 0.0
FOREBAY
1 2.0
Rating Curve (Spill Channel Option) #VALUE! #VALUE!
1 0.0
#VALUE! #VALUE!
#VALUE! #VALUE!
8.0
#VALUE! #VALUE!
6.0
#VALUE! #VALUE!
4.0
#VALUE! #VALUE!
2.0
#VALUE! #VALUE!
0.0
Flow (cumecs) #VALUE! #VALUE!
0.00 2.00 4.00 6.00 8.00 10.00 12.00
#VALUE! #VALUE!
C B =( b+ 2 wb +2 ws ) t s L
Concrete quantity in bottom slab CB = #VALUE! m3
12
10
0.0 ### ### #VALUE!
4 Page 87 of 135
2
12
10 FOREBAY
8
0.3 ### ### #VALUE!
6
0.4 ### ### #VALUE!
Ref: C. Nalluri
f = 0.87
z
a =θ 4.189
h = -0.500
y
2θ = 240.00
2.00
1
Mannings equation V = S 1/2 R2/3
n
Flow velocity V
" " " " " = #VALUE! m/s
Page 88 of 135
FOREBAY
D+ K
Minimum thickness of steel sheet t min= (K = 500 & D in mm)
400 Ref: Warnick
Minimum thickness of steel sheet tmin = 6.25 mm
Corrosion allowance ca = 1.00 mm
A s=
π d i +2 s(
1000 ) −
πd 2i
4 4
X-sectional area of steel As = 0.050 m 2
V
Froude Number F R= Ref: C.V. Davis
√ gD
Page 89 of 135
FOREBAY
V
F R=
√ gD
(Where V & D are velocity and depth of flow entering the jump)
D2
Ratio of conjugate depths =0 . 5 ( √ 1+8 F 2R 1 −1 ) Ref: L.W. Mays
D1
Depth before the jump D1 = 1.13 m
Depth after the jump D2 = #VALUE! m
- FLUSHING PIPE
Page 90 of 135
FOREBAY
V =Cd √ 2 ghe
Flow velocity (orifice flow) V = #VALUE! m/s
Discharge (orifice flow) Qo = #VALUE! m3/s
D+ K
Minimum thickness of steel sheet t min= (K = 500 & D in mm)
400 Ref: Warnick
Minimum thickness of steel sheet tmin = 3.25 mm
Corrosion allowance ca = 1.00 mm
A s=
π d i +2 (
1000 ) −
πd 2i
4 4
X-sectional area of steel As = 0.015 m 2
The use of the impact-type stilling basin is limited to installation where the velocity at the
entrance to the stilling basin does not greatly exceed 30 ft/s (9.1 m/s). For discharges
exceeding 10 m3/s, it may be more economical to consider multiple units side by side.
Page 91 of 135
FOREBAY
Page 92 of 135
FOREBAY
Alternatively:
Inside width of stilling basin (from graph) W = 6.00 ft = 1.83 m
Loss in energy (from graph) EL/E1 = 53 %
The dimensions of various components as shown in the above figure, are given below;
Page 93 of 135
PENSTOCK
DESIGN OF PENSTOCK
INPUT
- BASIC DATA
0 . 45
Q
Most economical penstock diameter D e=1. 12 Ref: Mosonyi
H 0 .12
" " " " De = #VALUE! m
0 . 43
P
Most economical penstock diameter De=0 .71 0. 65 Ref: GTZ
H
" " " " De = #VALUE! m
2 0.25
Q
Most economical penstock diameter D e=3. 55 ( )
2 gH
Ref: Guidelines, Roorkee
Sarkaria's equation
" " " " De = #VALUE! m
Page 94 of 135
PENSTOCK
0 .1875
n 2 Q2 L
Dia. for limiting headloss to 4% of H Dlim it =2. 69 (
H ) Ref: ESHA Guide
1.00
x2 y2
Elliptical entrance curve (bellmouth) + =1
( 0 . 5 D )2 ( 0 . 15 D )2
Ref: DOSD
Elliptical entrance curve (square & rect.) x2 y2
+ =1
D 2 ( 0 . 33 D )2
For circular pipes D is the diameter while maximum values of 'x' & 'y' are given in plan view as;
Maximum 'x' = 0.65D from pipe centerline and Maximum 'y' = 0.5D from entrance face
Page 95 of 135
PENSTOCK
However the existing practice in the region is to adopt the bellmouth diameter as 1.5D, therefore
x2
Therefore: y=
√( 1−
( D) )
2
( 0 .25 D )2
Elevation (m asl)
x y (low) y (up)
1.000 0.000 0.000 #VALUE! #VALUE!
0.900
Plan 0.109 0.100 #VALUE! #VALUE!
12.0
0.800 0.150 0.200 #VALUE! #VALUE!
10.0
0.700 0.179 0.300 #VALUE! #VALUE!
8.0 0.600 0.200 0.400 #VALUE! #VALUE!
GATE SIZE
Gate hight H = 1.00 m H =D
Gate width W = 0.79 m H=0 . 785 D
For a gate having H=D and W=0.785D, the flow velocity at the gate will be equal to the
velocity in penstock so no further flow acceleration is produced in this section.
- FRICTION FACTOR
DV
Reynolds number Re = Ref: Davis
where: ν
Kinematic viscosity of water at 20oC ν = 1.0E-06 m2/s
64
For laminar flow f= for laminar flow
Re
Page 96 of 135
PENSTOCK
64
f=
Re
1 e/ D 2. 51
For turbulent flow
(Colebrook - White equation) √f
=−2 log 10 +
3 . 7 Re √f( )
1 R √f
For hydraulically smooth pipe
√f
=2 log 10 e
2 . 51 ( ) Ref: Von Karman
where:
√f
=2 log 10 3 . 7
e ( )
Roughness height (welded steel) e = 0.600 mm
Ratio e/D = 0.00060
1 = 0.98
Friction factor (Moody) f = 0.01678
- SUBMERGENCE REQUIREMENTS
" " " " (by Rohan) S min 1.474V 0.48 D 0.76 3.58 m
Smin
- TRASHRACK
Page 97 of 135
PENSTOCK
- HEADLOSSES
FRICTION LOSS
1
Mannings equation V = S 1/ 2 R2/ 3
n 2
V L
h f =n2
R4 / 3
Page 98 of 135
PENSTOCK
V2L
Headloss (Manning) h f =n2
R4 / 3
Headloss (Manning) hf = 21.75 m
2 . 63 0. 54
hf
Hazen-Williams equation Q=C u CD S where S= & Cu=0.278
L
1/0. 54
Q L
Headloss (Hazen-Williams)
()
h f =10. 654
C D4 . 87
1. 85
6 . 87 L V
Alternatively Headloss (Hazen-Williams) h=
D
f (C )
1 . 165
2
L V
Darcy-Weisbach equation h f =f
D 2g
Headloss (Darcy-Weisbach) hf = 17.33 m
hf e/ D 2. 51 ν
Average velocity of flow
(Colebrook - White equation)
V =−2 2 gD
√ L
log
( √ )
3 .7
+
D 2gD
hf
L
1 = 1.00
Headloss (Colebrook-White) hf = 18.03 m
Headloss Flow
0.00 0.00
0.22 0.50
Friction Headloss Vs Discharge 0.87 1.00
25.00
1.96 1.50
20.00
3.48 2.00
TRASHRACK LOSS
2
t 4 /3 v bars Ref: Davis:
hl ,ra = K
b () 2g
sin α
Page 99 of 135
PENSTOCK
4 /3 v2
t
hl ,ra = K ()
b
bars
2g
sin α "Hydraulics Handbook"
2
v
BEND LOSS h L=K Ref: Mosonyi
2g K= 0.20
No. of bends = 10 no.
Headloss in bends hLB = 4.13 m
- PENSTOCK SECTIONS
12
Longitudinal Profile
Invert top
10
0 #VALUE! #VALUE!
8
100 #VALUE! #VALUE!
6 200 #VALUE! #VALUE!
230 #VALUE! #VALUE!
4
500 #VALUE! #VALUE!
2
0
Distance (m)
0 100 200 300 400 500 600
- AERATION PIPE
3
t
Collapsing depression Pc =882500 s
D ( ) (ts & D in mm)
Q
Diameter of aeration pipe d=7 . 47
√ √ PC
for Pc ≤ 0.49
ALTERNATIVELY
QT
Air vent area should be greater of these two values A V =0 .20 A P or AV=
Where: 25. 0
Cross-section area of penstock AP = 0.79 m2
Rated turbine flow QT = 5.00 m3/s
The air vent should exhaust to a safe location unoccupied by the project staff or general public.
CRACK OPENING
The penstock should be filled slowly to avoid excessive and dangerous "blow-back". The
recommended practice is to control filling rate via the head gate. The head gate should not be
opened more than 50 mm until the penstock is completely full. This is sometimes referred
to as "cracking" the gate.
- MANIFOLD / BIFURCATION
Check vb ≥ V = O.K. ۩
2
t
X-sectional area of steel A s=
(
π d i +2 s
1000 ) −
πd 2i
Ref: Davis
4 4
X-sectional area of steel As = 0.023 m2
- SURGE CALCULATIONS
10−3 k
Pressure wave speed
=
ρ
)
2.1E+09 N/m2
Ref: ESHA Guide
N N2
Allievi Formula for max. overpressure
ΔP=P w ( √
2
±
2
4
+N ) Ref: ESHA Guide
LV
Where: N=
(
gP w T v )
N = #VALUE!
If water acceleration constant is less than 3 seconds than surge tank is not required
VL
Water acceleration constant t h= Ref: ESHA Guide
gH
" " " " " th = #VALUE! sec
ALTERNATIVELY
ΣL i V i
A surge tank may be required when L/ H >4 to 8 or >7 to 13
H
Check L/H<5 = #VALUE! ۩
ALTERNATIVELY
A surge tank may be required when L≥ L max . Ref: IIT, Roorkee
Where:
Tv
Maximum length of penstock Lmax =3. 14 H n
V
Maximum length of penstock Lmax = #VALUE! m
- WALL THICKNESS
PENSTOCK MATERIAL
ASTM A516-70 steel having yield stress of 38000 psi (262010 kN/m2) and tensile stress
of 80000 psi (55880 kN/m2) has been used for penstock design.
Joint efficiency (E) has been taken as 100%( i.e. 100% radiographic inspection).
Following conditions have been considered.
Pw D
Wall thickness required t s= Ref: ESHA Guide
2 σ f kf
Hydrostatic pressure Pw = #VALUE! kN/mm2
D+ K
Minimum thickness of steel sheet t min= (K = 508 & D in mm)
400 Ref: Warnick
" " " " " tmin = 3.77 mm
ALTERNATIVELY
Minimum thickness of steel sheet t min=2 . 5 D+1. 2 (D in meter)
" " " " " tmin = 3.70 mm Ref: ASME
ALTERNATIVELY
Minimum thickness of steel sheet t min=D /288 (D in mm)
" " " " " tmin = 3.47 mm
The larger value of minimum shell thickness governs for design purpose
2 VL
For given closure time H surge =
g Tv
Maximum surge head Hsurge = 108.16 m
(For given closure time)
0 . 1 H max D
σ H=
2te
Page 106 of 135
PENSTOCK
0 . 1 H max D
Hoop stress σ H= Ref: DPR-Bilgaon
2te
Hoop stress σH = #VALUE! kgf/cm2
( D+ 0. 0147 )4 −D4
Maximum length between supports
Ls =
√
3
w p+w
6.6 m
0 .82
Concrete volume in footings V f =3. 5 ( LD 2 ) Ref: IIT, Roorkee
INPUT
- MAIN DIMENSIONS
For high tailwater levels at flood It may be necesssary to provide separate erection and
unloading bays adding considerably to the repair bay floor area.
L = 41 m
W = 13 m
MAIN DIMENSIONS
H = 9 m
Ds = 4 m
INPUT
- BASIC DATA
1300
0 1299.8
1299.5
0 1297.7
1299 2.5 1297.7
1298.5 2.5 1299.8
0 1299.3
1298
2.50 1299.3
1297.5
1297
1296.5
0 0.5 1 1.5 2 2.5 3
1
Mannings equation V = S 1/2 R2/3 Ref: C.V. Davis
n
Area=( b+zy ) y
Flow area A
" " " " " = 4.00 m2
Perimeter=b+2 y √1+ z 2
Wetted perimeter P
Topwidth=b +2 zy
Top width T
" " " " " = 2.50 m
A
Hydraulic depth D D=
" " " " " = 1.60 m
T
A
Hrdraulic radius R R=
" " " " " = 0.70 m P
Flow velocity V
" " " " " = 1.25 m/s 1.25
Discharge capacity Q
" " " " " = 5.00 m3/s
Check Q ≥ QD = O.K. ۩
Q
Unit discharge q q=
" " " " " = 2.00 m3/s/m b
2 1/3
q
Criticaldepth=
g ( ) Ref: L.W. Mays
Critical depth yc
" " " " " = 0.74 m
V
Froude number Fr F r=
" " " " " = 0.32 √ gD
2
2V L
Friction headloss (Manning) h f =n 4 / 3
R
Friction headloss (Manning) hf = 0.15 m
- RATING CURVE
Elevation Flow
1297.7 0.00
1297.9 0.26
1298.1 0.77
1300.0
Rating Curve
1299.5
1299.0
Page 112 of 135
1298.5
1298.0
W at e r Ele vati o n (m a
TAILRACE
1300.0
Rating Curve
1298.3 1.40
1299.5
1298.5 2.10
1299.0
1298.7 2.86
1298.5
1299.0 3.65
1298.0
1299.2 4.48
1297.5
1299.4 5.32
1297.0
1299.6 6.19
1296.5
Flow (cumecs) 1299.8 7.06
0.00 1.00 2 .00 3.00 4.00 5.00 6.00 7.00 8.00
1300.0
Longitudinal Profile 0 1297.7 1299.3 1299.8
1299.5 150.0 1297.5 1299.1 1299.6
1299.3 1299.1
1299.0
1298.5
1298.0
1297.5
1297.0
1296.5
- SURGE CALCULATIONS
Q1 −Q 0
Increase in water level Δy = 0.44 m Δy=
( v + √ gy ) b
Check Δymax < F.B. = O.K. ۩
- CONCRETE VOLUME
C B =( b+ 2 wb +2 ws ) t s L
Concrete quantity in bottom slab CB = 55.50 m3
1
(
C S = wt hc + h c ( w b −wt ) 2 L
2 )
Concrete quantity in side walls CS = 165.00 m3
Cts =( b+2 wt ) t t L
Concrete quantity in top slab Cts = 0.00 m3
1300.5
1300
1299.5
0.0 1297.4 3.1 1297.7
1299
0.0 1297.7 3.1 1299.9
1298.5
0.3 1297.7 3.3 1299.9
1298
0.4 1299.9 3.4 1297.7
1297.5
0.6 1299.9 3.7 1297.7
1297
0.6 1297.7 3.7 1297.4
1296.5
3.1 1297.7 0.0 1297.4
1296
0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0
MECHANICAL EQUIPMENT
INPUT
- BASIC DATA
If turbine operates at head H1 other than the rated head Hd, the flow admitted by
the turbine will be:
H1
Qmin =
√ Hn
#VALUE! m3/s
Ref: ESHA Guide
- SPECIFIC SPEED
n √Q
Specific speed of turbine nQE = Ref: ESHA Guide
Where: E3 /4
Rotational speed of turbine n = 5.00 t/s (w.r.to generator speed
" " " " " n = 300.0 rpm i.e. direct coupling)
In pelton turbines the specific speed increases with the square root of the number of jets
- RUNNER DIAMETER
PELTON TURBINES
Q 1
Bucket width
=
√ n jet √ H n
#VALUE! m
Ref: ESHA Guide
Q 1
Nozzle diameter
If this ckech fails than lower the rotational speed or increase the no. of nozzles
2
De
Nozzle discharge Q jet =K v π √ 2 gH
Where;
4 Cp / De Kv
Kv is a function of relative gate opening "a = Cp / De" 0.00 0.00
0.20 0.28
Opening of nozzle Cp = 0.10 m 0.40 0.50
0.60 0.65
Relative opening a = #VALUE! m 0.80 0.73
Coefficient Kv = #VALUE! 1.00 0.77
1.20 0.78
Nozzle discharge Qjet = #VALUE! m /s 3 2.00 0.78
FRANCIS TURBINES
0 . 095
Inlet diameter (smaller)
(
D 1 = 0. 4+
nQE
D3
)
" " " " " D1 = #VALUE! m
D3
Inlet diameter (larger) D2=
0. 96 +0 .3781 nQE
For nQE < 0.164, we can consider D1 = D2
KAPLAN TURBINES
0 .0951
Runner hub diameter
(
Di= 0 . 25+
nQE
De
)
" " " " " Di = #VALUE! m
FRANCIS TURBINES
2
V
Cavitation coefficient (Thoma's coeff.) σ =1 .2715 n 1. 41
QE +
2 gH n
" " " " " σ = #VALUE!
Patm −P v V 2
Turbine setting w.r.t. tailwater level H S= + −σH n
ρg 2g
" " " " " HS = #VALUE! m
KAPLAN TURBINES
2
Cavitation coefficient (Thoma's coeff.) V
σ =1 .5241 n1QE. 46 +
2 gH n
" " " " " σ = #VALUE!
Patm −P v V 2
Turbine setting w.r.t. tailwater level H S= + −σH n
ρg 2g
" " " " " HS = #VALUE! m
D2 D
Diameter of nozzle (for max. energy)
=
√
C N 8 fL
0.12 m
Ref: J. Alen
"Civil Engg. Ref. Book"
- GOVERNING CONDITIONS
LV o
Water starting time T w= Ref: C.C. Warnick
gH o
COST ESTIMATES
INPUT
- ABSTRACT OF COST
WEIR #VALUE!
Bulk excavation m3 #VALUE! 140 #VALUE!
Structural excavation m 3
#VALUE! 270 #VALUE!
Fill / backfill m 3
#VALUE! 150 #VALUE!
POWERHOUSE #VALUE!
Bulk excavation m 3
831 140 116278
Structural excavation m 3
4153 270 1121250
Fill / backfill m 3
2492 150 373750
Total #VALUE!
ECONOMIC ANALYSIS
INPUT
Energy Reduction GWh ### ### ### ### ### ### ### ###
Ann. En. (incl.Red.) GWh ### ### ### ### ### ### ### ###
Accum. Factor - 1.10 1.10 1.10 1.10 1.10 1.10 1.10 1.10
Present Value Cost Mill US $ 11.8 12.3 12.9 13.5 13.8 14.2 14.4 14.7
Annual Benefits Mill US $ 1.6 1.7 1.9 2.0 2.1 2.1 2.1 2.1
Annual O&M Cost Mill US $ 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2
Annual (B-O&M) Mill US $ 1.4 1.6 1.7 1.9 1.9 2.0 1.9 1.9
Present Value Bene Mill US $ 13.2 14.8 16.2 17.5 18.1 18.4 18.3 18.0
NPV (B-C) Mill US $ 1.5 2.5 3.4 4.0 4.3 4.2 3.9 3.3
Tarrif / kWh US $ / kWh 0.054 0.051 0.049 0.047 0.047 0.048 0.048 0.050
Cost / kW US $ / kW 3407 3077 2828 2658 2543 2481 2434 2424
NPV ( B - C ) M ill US $
5
14.00 5
13.50 4 Page 127 of 135
13.00 4
3
12.50
3
12.00
2
In te rn al R ate o f Re tu rn %
NPV ( B - C ) M ill US $
ECONOMIC ANALYSIS
5
14.00 5
13.50 4
13.00 4
3
12.50
3
12.00
2
11.50
2
11.00 1
10.50 1
10.00 0
2.50 3.00 Design
3.50 Discharge
4.00 m3/s 5.00
4.50 5.50 6.00 6.50 7.00 2.50 3.00 Design 4.00
3.50 Discharge
4.50m3/s
5.00 5.50 6.00 6.50 7.00
DESIGN UTILITIES
2 If turbine operates at head H1 other than the rated head Hd, the flow admitted by
the turbine will be:
H1
Rated head Hd =
Q 1 =Q d
65.00
√ Hd
m
Minimum operating head Hmin = 50.00 m
Rated turbine discharge Qd = 4.00 m3/s
Minimum River flow QRmin = 2.80 m3/s
1/2
Width of incised river W =2. 4 Q
Width of incised river W = 330.90 ft
d. Scour depth of rivers in gorges with inerodible banks and a deep alluvium bed
3/10
Q
Scour depth below water surface R=1. 32
( ) Cr
1 /2
Q
For gorge width W ≥2. 4
Cr ( )
d1 Scour depth below water surface R = 22.46 ft 6.85 m
3/5
Q
Scour depth below water surface R=2. 25
( )
WC r
1/2
Q
For gorge width W <2 . 4
Cr ( )
d2 Scour depth below water surface R = 20.05 ft 6.11 m
H 0 . 2 q0 . 57
Scour depth below stream bed R=3. 15
( D090.32 ) −d m
B/r "E"
0.000 1.27
0.166 1.48
0.200 1.84
0.250 2.20
0.333 2.57
0.500 3.00
1/3
Q Metric Units
R=0 . 473()
f
2 1/3
q Metric Units
R=1. 35 ( )
f
DON'T MODIFY