You are on page 1of 8

INTERPRETING WORKING DRAWINGS BY TYPES AND

RELATIONSHIPS

a. Building Symbols
✓ Architectural Graphic Symbols-

✓ Plumbing Symbols- industrial piping:


designed to carry liquids and gases used
in manufacturing processes; plumbing:
piping used in commercial and
residential applications, designed to
✓ Interior Walls
carry fresh water, liquid, solid wastes,
and gases.

✓ Material Symbols- used to represent TYPES OF BUILDING DRAWINGS


materials or contents on floor plans,
elevations, and detail drawings.
a. Proposal Drawing- first plan drawn, more of
sketch
b. Submission Drawings/Architectural Drawings-
submitted drawings are in the process to be
approved, rectified, rejected.
Purpose:
1. To develop design into a coherent
proposal
2. To communicate ideas and concept
3. To convince clients of the merits of
the design
4. To enable contractor to construct it
c. Working Drawing- a drawing or blueprint based
on explanation; approved and can be executed;
provides graphical & dimensional information;
contractors use this data to build their work or
for assemblage required; can be in the form:
architectural drawings, civil drawings, electrical
✓ Electrical Symbols- prepared by drawings, mechanical drawings, etc.; consist of
electrical drafters; symbols not two dimensional orthogonal projections,
standardized, hence requires legend in including section plans and elevations; can be
plan. drawn by hand, CAD (Computer-Aided
Drawing), BIM (Building Information Modelling,
used for 3D representation).
d. Completion Drawings- ito ‘yung drawings na
sinasubmit ng mga contractor; after the project
is finished, change, modifications, etc. sa
working drawing, dito pinapakita. For every
change, there should be record of approval.
SITE PLAN- shows contours, boundaries, roads, utilities, FOUNDATION AND FLOOR FRAMING PLANS
structures, etc.; shows location of the proposed
a. Foundation Plan- Plan view drawing, in section,
structure in outline; shows corner locations relative to
showing the location and size of footings, piers,
reference lines. This may include:
columns, foundation walls, supporting beams;
1. Buildings to be demolished/removed/modify based on floor plans, plot plans, elevation
etc. plans/drawings; before drawing foundation
2. Extent of earthworks, included, cutting, and plans, examine first floor plan for exterior walls,
filling, the provision of retaining walls, etc. elevation plans should also consider in drawing
3. General layout of external services, i.e., foundation plan for stepped footings, retaining
drainage, water, gas, electricity, telephone, walls, and problem related to grade of the land.
manhole covers, etc. ✓ TYPES OF FOUNDATION PLAN
4. Layout of external lighting ✓ A. SHALLOW FOUNDATION
5. Location of miscellaneous external component, 1. Individual Footing/Isolated
i.e., fire hydrants, signage, litter bins, etc. Footing
1.1. Pad Footing
FLOOR PLAN- views of building as though cutting planes
1.2. Stepped Footing
were made through the building horizontally; the
1.3. Sloped Footing
cutting plane is generally taken 5 feet, 0 inch (5’0”)
2. Combined Footing
above the floor being shown; scale drawings; shows
3. Spread Footing/ Strip
relationship between rooms, spaces, physical features
footing and wall footing (or
viewed above; don’t hold enough info for builders to
just spread footing)
actually construct structure; provides room layout &
4. Raft of Mat Foundations-
conceptual starting point.
parang net; support loads
✓ Space Planning- important in new from columns and walls;
structures; determine how to use space used to prevent differential
more efficiently. settlement.
✓ 7 STEPS TO FLOOR PLANNING
B. DEEP FOUNDATION
1. List requirements- needs and wants
of those who will be occupying the 5. Pile Foundation- type of
buildings. deep foundation; used to
2. Measure- make sure you have the transfer heavy loads from the
correct measurements. structure to a hard rock strata
3. Scale- floor plans should be drafted much deep below ground level;
in scales. used for construction wherein
4. Think about sightlines- purpose of soil is not suitable for heavy
space, think of it. loads
5. Render it- organize your plan.
6. Drilled Shaft or Caisson
6. Evaluate- review the wants & needs
Foundation- a type of deep
list; evaluate spatial arrangement;
foundation; similar to pile
analyzing circulation; usable space;
foundation; high capacity cast-
privacy; accessibility.
in-situ foundation; resists loads
7. Share- double check with each
from structure through shaft
other.
resistance, toe resistance,
✓ IMPORTANCE OF FLOOR PLANS
and/or combination of the two;
1. Shows relationships between rooms
construction through the use of
and spaces.
auger; isa sa mga ginamit na
2. Communicate how one can move
foundation because of swampy
through a property.
unpredicted soil sa CSPC—
3. Essential part in real state marketing,
Maam Mary.
home building, home design, interior
design, architectural projects. FRAMING PLANS- must specify the sizes and spacing of
4. Communicate the ideas more clearly. joists, girders, and columns used to support the floor;
5. Shows the potential of the layout shows anchoring joists and girders to the columns and
6. Demonstrate the scale and scope of a foundation walls or footings, when detail drawings are
project to a home builder or contractor, needed; provides structural information, i.e., joist
hence more accurate pricing. location, spacing of direction, floor heights, and stair
openings.
FLOOR FRAMING IN WOOD PLATFORM used by the ratings responsible for the utilities; most
requires spacing in walls for installation.
1. Subfloor
2. Blocking WORKING DRAWING CONTENT BY DRAWING TYPE
3. Framed opening
Architectural: site development plan, vicinity map,
4. Heading, rim, or band joist
elevations (i.e., right side, left side, rear, front), roof
5. Still plates
plan, ground floor, reflected ceiling plan, second floor
6. Girder or beam
reflected ceiling plan, schedules of doors and windows
7. Column and footing
8. Joist Structural: schedule of footing, schedule of column,
9. Poured concrete foundation wall detail of wall footing, details of columns and footings,
10. Footing foundation plan, second floor framing plan, roof
framing plan, detail of slab, detail of footing tie beam,
SLAB (Reinforced Concrete Slab)- crucial structural
typical detail of beams, detail of stair, detail of conic
element; provide flat surfaces (floor and ceiling in
gutter, detail @ truss ridge, detail of truss
buildings); classified into one-way slab & two-way slab.
Electrical: ground floor lighting layout; second floor
A. ONE-WAY SLAB- supported in two sides and the
lighting layout; ground floor power layout; second floor
ratio of long to short span is greater than two;
power layout; schedule of loads; details of service
supported by beams in two sides to carry loads
𝑙 entrance; schematic diagram, legend
along 1 direction; 𝑏 ≥ 2, 𝑤ℎ𝑒𝑟𝑒 𝑙 =
𝑙𝑜𝑛𝑔𝑠𝑝𝑎𝑛, 𝑏 = 𝑠ℎ𝑜𝑟𝑡𝑒𝑟 𝑠𝑝𝑎𝑛 Plumbing-legend, ground floor clean water layout,
B. TWO-WAY SLAB- supported on four sides and ground floor drain waste and vent layout, detail of floor
the ratio of long to short span is smaller than drain, detail of water meter, detail of septic vault,
𝑙 isometric diagram, detail of lavatory connection, detail
two; < 2; supported by beams at four side;
𝑏 of water closet, detail of catch basin
loads carried by the supports along w/ both
directions. COMMON CODE REQUIREMENTS

SECTIONS-Sectional views provide important info about RELATIONSHIP TO PLAN CHECK DOCUMENTS
the height, materials, fastening and support system, and
A. Plan check- review of plans, drawings, and
concealed features of structure.
documents by the building official for
Two types of Sections: compliance with the building codes; required
before construction permit is issued.
1. Longitudinal Section- are long sections B. Building Codes: a collection of rules and
through the longest length of the subject regulation adopted by authorities; used for
land, section along the road. safety; enforced by the local Government. A
2. Cross Section- sections across narrowest code is a set of rules and specifications for the
length of the subject or land works; across correct methods and materials used in a certain
the road. product, building or process.
DETAILS- Detail views are large scale drawings of 1. National Building Code of the Philippines
construction assemblies and installations that can’t be (NBCP): PD 1096- provides and sets
clearly shown in the section; enlarge drawings; show standards so you’ll live in a building cozy,
various parts in more details how they will be safe; for the general welfare of the public.
connected or placed. 2. National Structural Code of the
Philippines: a referral code of NBCP, not a
ELEVATIONS- orthographic projection; shows one side law.
of the house; to show finish appearance of a given side 3. Fire Code of the Philippines: RA 9514; year
and furnish vertical height dimension; provides 2018; sec. 2. Ensure public safety, promote
information on the area of all wall surfaces and wall economic development through
openings. suppression/prevention of all kinds of
Elevations: destructive fires; promote
professionalization of the fire service as a
1. Front profession.
2. Rear 4. Philippine Electrical Code- basis for
3. Left side safeguarding persons, buildings and its
4. Right side contents from hazards that may arise from
UTILITY PLANS- a floor plan that shows the layout of the use of electricity.
heating, electrical, plumbing, or other utility systems; 5. National Plumbing Code of the Philippines-
ensure the proper performance of plumbing
systems; plumbing codes help ensure the • 3 Large envelope w/ Folder, Faster And
proper performance of plumbing systems (1)Logbook
6. Philippine Mechanical Engineering Code • Others
✓ Fire Safety Certificate Checklist
RELATIONSHIP TO DOCUMENTS AND DRAWINGS
✓ Location Clearance
Construction Documents- set of drawings that an
Note: 1. All Application Forms, plans, specification,
architect produces during the design development
design and computation, bill of materials should be sign
phase of a construction project; serve as a project
and sealed by duly licensed ARCH, CE, SE, PEE, Master
manual during the construction phase; assist permitting
plumber, master Electrician. 2. In case of large-scale
agencies and inspectors from local governments, who
Development subdivision, secure Development permit
have to clear the project; An architect must produce
form in Sangguniang Bayan. 3. Photocopy of PRC ID and
two sets of this, one set is construction set (remains in
PTR
construction), another is permit set (for local permit).
COMMON SPECIFICATION INFORMATION
Certificate of Occupancy: required for a building to be
available for occupants. Design Documentation: is prepared so to allow the
construction to be accurate. This include: design
Building Permit- document issued by the building
planning, bill of quantities, & technical specifications.
official to an owner/applicant to proceed w/ the
construction, installation, addition, alteration, removal, Design drawings: are developed to a level of detail
etc. necessary to prepare a clear, coordinated visual
depiction of all aspects of the works.
Under Chapter 3, Sec. 301 of PD 1096: Building permit
from building official is required for construction; Major project elements include overall layout,
permits shall expire if construction does not start after earthworks equipment, mechanical, electrical,
one year after having the permit or abandoned after structural, and water supply systems; are designed and
120 days after its start. depicted through coordinated scale drawings and
detailed elevations and plans.
Requirements for Building Permit
Lot feeder may engage consultants to ensure well-
✓ Barangay Clearance/Certification, Association
coordinated drawings and bill of quantities are
Certificate, Consent of owner, SPA.
prepared.
✓ Transfer Certificate of Title, Tax Declaration,
Deed of Absolute Sale, Waiver of Rights, Technical specifications are prepared to provide
Contract of Lot Award, DENR Tagging Entry consistency and to instruct construction contractors on
Pass/Stub. how the works are to be carried out, the quality of the
✓ Contract/Agreement (should include contract workmanship and methods of quality assurance for the
price) with general contractor. construction; describe the project design and
✓ Contract/Agreement (should include contract construction practices, technical standards,
price) with sub-contractors for Electrical, specifications and principles to be followed during
Mechanical, Sanitary/Plumbing, Elevators, and construction; may specify a performance goal (a
all other services required by the developer. performance specification) or procedures used to meet
✓ Fully accomplished application forms: the performance goal (design specification); depend on
• Building the nature and complexity of the project; should form
• Sanitary/Plumbing part of all construction projects.
• Electrical
Objectives of the design drawings and technical
• Mechanical
specifications
• Fencing
• 5 Sets Of Building Plans And Specification: 1. provide a detailed record of the design of the
o Location Plan, Site project.
Development plan, Vicinity Map 2. set standards for the technical aspects required
o Architectural Plans in the construction.
o Structural Plans 3. set standards for the execution of the
o Sanitary/Plumbing construction.
o Electrical Plans 4. set standards for documenting the design,
o Mechanical Plans/Fire tendering and construction process.
Protection Plan (if Applicable)
✓ 5 Sets Of Design drawings and technical specifications should
• Structural Design and Computations include:
• Bill of Materials/Cost Estimates 1. Design Drawings
• Specification 2. Bill of Quantities
3. Material specifications Division 16: Furniture
4. Requirements for Material Testing Division 17:
5. Construction and installation methods Division 18: Warranty
6. Development approval conditions that have to III. Statement of Compliance
be complied with throughout the construction
COORDINATION OF ARCHITECTURAL DRAWINGS WITH
Design documents relate to the design, construction STRUCTURAL, ELECTRICAL, MECHANICAL AND
and commissioning of the project works. PLUMBING PLANS

the documents should include: Architectural design- done by architect; means building
appearance, functions based on client’s vision. Design
1. design drawings- Design drawings for
process: (1) consultation w/ client (project’s budget,
construction contain all the information
expected finish date, visual appearance, spatial
necessary for the construction contractor to bid
requirements, functional program, and other design
on and build a particular project. A contract or
objectives are addressed.)
tender document often references design
drawings; show details on layout, Structural design- done by structural engineer; support
measurements, plan, cross-sectional and the building’s dead, live, and environmental loads, thus
vertical profiles; prepared as scale drawings of enabling it to remain upright.
the works to be constructed. Design drawings
Mechanical, electrical, and plumbing (MEP) design-
should be presented in such a way that:
done by MEP engineers; drawings before the projects
understandable, communicate the concept
are issued for permitting and construction.
visually to the lot feeder and the construction
contractor, legible, include all information from Other disciplines- include landscapers, civil engineers,
previous revisions and updates. The design communications engineers, acoustic and specialty
drawings should include the following aspects: consultants etc.
site layout and the location of the works to be
constructed, plan views, detailed designs and Coordination issues, also known as clashing, arise when
cross-sectional profiles of the works, the drawings don’t align well with one another.
dimensions and units gradients, titles and Examples include: columns obstructing views or
scales that meet the required standards and passage, misaligned slab edges, mechanical ducts
units, adequate labelling, dated and signed by running through structural members, etc.
the designer. How to improve coordination?
The lot feeder ensures all parties responsible
for the creation, processing or supply of To ensure effective integration between disciplines, the
drawings and diagrams standardize the layout right expectations must be laid out before the project
and content of these drawings. begins. The architect should commit to furnishing the
2. construction specifications engineer with some of the following critical information:
Sample specifications the structural design & overall design.
I. INTENT AND APPLICATION OF THE Building Information Modelling (BIM) integrate various
PROVISION OF THIS SECTION design inputs, facilitating and improving the accuracy of
II. GENERAL CONDITIONS OF PLANS AND clash detection. Peer reviews are also helpful in
SPECIFICATIONS identifying systemization flaws and getting them fixed.
Division 1: General Requirements
Division 2: Scope of Work INTRODUCTION TO BRIDGE DRAWING
Division 3: Site Work
Bridge: Structure that covers a gap; carry a load across a
Division 4: Masonry
natural or artificial obstacle i.e., river, canal, railway,
Division 5: Metal
other road; carry a free flow of transport; most
Division 6: Wood and Plastics
significant component of transportation system.
Division 7: Thermal and Moisture
Protection Parts of the Bridge:
Division 8: Doors and interior Viewing
1. Substructure
Windows
1.1. Foundation (Pile/Spread Footing)
Division 9: Finishes
1.2. Pier (Column)
Division 10: Specialties
1.3. Abutment
Division 11: Toilets
2. Superstructure (any structure above bearing;
Division 12: Electrical Specifications
wearing surface)
Division 13: PLUMBING / SANITARY
WORKS 3 TYPES OF BRIDGE
Division 14: Mechanical Works
Division 15: Fire Protection 1. Short span (6-30 m)
2. Medium span (30-100 m) ✓ Function
3. Long span (> 100m) ✓ Proportion
✓ Harmony
Span >6 m -→ Bridge; Span <6m→ Culvert
✓ Order & Rhythm
Examples of Bridge: ✓ Contrast & Texture

Bristol Bridge: UK Process of Making Bridge:


Avon Mouth Bridge: UK
Establish requirements → Understand Context→
Golden Gate Bridge: USA
Electric Wharf Footbridge: UK Setting design objectives and Principles→ Develop
London Millennium Footbridge: UK Design→ Analysis of Design→ Design Refinement→
The Forth Railway Bridge: Scotland Implementation Plan
Thames Ditton Railway Bridge
INTRO TO BIM (Building Information Modelling)

BASIC TYPES BASED ON TRUCTURAL FORM


BIM - used to design and document building and
• Arch- has abutments (used to support the arch
infrastructure designs; helps stakeholders understand
part of the bridge); most common: VIADUCT
what the finished product will be – highlighting key
(long bridge made up of many arches); arch
steps of the construction process along the way; ensure
span lateral pressure → abutment e.g. Gaoliang
all parties involved are kept up-to-date with the
Bridge of the Summer palace, China
project’s progress. an intelligent 3D model-based
• Beam/Girder Bridge- simplest type e.g. Iowa
process that provides AEC professionals with every
River Bridge
detail need to plan, design, construct, and manage
• Cantilever- “canti” inclination
buildings and infrastructure; also known as Virtual
• Truss- load bearing structure; incorporates building or Building Simulation.
truss; incorporates triangular sections of truss
(this absorbs tension and compression to create BIM Process
a stressed structure able to accommodate
1. Plan- capture real-world data and generate
dynamic loads) e.g., Francis Scott Key Bridge,
context models
Baltimore, USA
2. Design- conceptual design, analysis, detailing
• Cable-stayed- dependent upon towers/pylons
and documentation are performed;
which are the load-bearing element of the
preconstruction process begins
structure e.g., Rio Antirrio Bridge, Greece
3. Build - fabrication begins using BIM
• Suspension- deck- load-bearing element; specifications
vertical suspension- held in place deck; support 4. Operate
cables (suspension cables) e.g., Great East River
Suspension Bridge Uses and benefits
• Tied Arch- incorporate arch structures (usually
1. used to manage information on a construction
metal) supported by vertical ties e.g., Infinity
project across the project lifecycle
Bridge in Stockton-on-Tees, England
2. digital description of every aspect of the built
CONSIDERATIONS IN BUILDING BRIDGE: asset
3. provides modelling and management
✓ Span length information
✓ Bridge length 4. enables all the parties to work to the same
✓ Beam Spacing standard and to be kept in the loop regarding
✓ Material Available any updates and changes
✓ Site conditions 5. better project coordination and collaboration
✓ Speed of Construction with stakeholders
✓ Aesthetics 6. efficient workflows
✓ Cost 7. 3D virtualizations
✓ Access for Maintenance 8. overall improved project outcomes
CONSIDERATIONS IN BUILDING AESTHETIC BRIDGE: Who uses?
✓ Context 1. Contractors and sub-contractors
✓ Comprehension 2. Project Managers
✓ Cost 3. Claims and litigation legal firms
✓ Constructibility 4. Quantity surveyors
CONSIDERATIONS IN BUILDING AESTHETIC BRIDGE: BIM objects are the components that make up a BIM
mode.
FEATURES OF BIM OBJECTS a. Excavation
b. Embankment
• Information content that defines a product.
c. Backfilling
• Product properties, such as thermal performance. d. Gravel Fill
e. Hauling of Waste Materials
• Geometry representing the products physical
characteristics. 3. FORMS AND SCAFFOLDINGS

•Visualization data giving the object a recognizable DIRECT COST


appearance.
a. Materials Cost
• Functional data, such as detection zones, that enables b. Labor Cost
the object to be positioned and behave in the same
INDIRECT COST
manner as the product itself.
a. Project Supervision
b. Tax
BIM LEVELS
4. REINFORCED CONCRETE WORKS
Level 0- no collaboration; using 2D CAD and working
a. Footing
with drawings/digital prints
DIRECT COST
Level 1- 3D CAD is being used for concept work, while
2D CAD is used for drafting production information a. Materials Cost
b. Labor Cost
Level 2- all parties involved utilize 3D CAD models, and
c. Equipment Rental Cost
the way stakeholders exchange their data varies from
other levels; Information is shared through a common INDIRECT COST
file format, and all firms involved combine this with
a. Project Supervision
their own data.
b. Tax
Level 3- everyone on the project uses one, shared
b. Footing Tie Beam
project model instead of working on their own 3D
model independently; open BIM; most collaborative c. Columns
BILL OF MATERIALS AND DETAILED COST ESTIMATE d. Roof Beams
1. GENERAL REQUIREMENTS e. Suspended Floor Slab
a. Mobilization/Demobilization
f. Slab on Fill
DIRECT COST
5. MASONRY WORKS
a. Labor Cost
a. CHB 6" for all exterior walls and fire wall
INDIRECT COST
DIRECT COST
a. Project Supervision
b. b. Tax a. Materials Cost
b. Labor Cost
b. Construction Safety and Health c. Equipment Rental Cost
DIRECT COST INDIRECT COST
a. Materials Cost a. Project Supervision
b. Labor Cost b. Tax
INDIRECT COST b. CHB 4" for all interior walls
a. Project Supervision 6. PLASTERING WORKS
b. Tax
c. Project Photographs DIRECT COST
DIRECT COST a. Materials Cost
a. Materials Cost b. Labor Cost
INDIRECT COST c. Equipment Rental Cost

a. Project Supervision INDIRECT COST


b. Tax a. Project Supervision
2. SITE WORKS b. Tax
7. ARCHITECTURAL DOORS AND WINDOWS
a. Doors
b. Windows
8. TILEWORKS
a. Comfort Rooms (floors and walls)
b. Floor Tiles (Bedroom)
c. Floor Area
d. Outdoor
9. METAL ROOFING WORKS
a. Metal Truss and Accessories
b. Corrugated G.I. Roofing
10. CEILING WORKS
11. PAINTING WORKS
12. WATERPROOFING WORKS
13. PLUMBING, SANITARY AND DRAINAGE SYSTEM
a. Plumbing Fixtures
b. Plumbing Fixtures
c. Sanitary and Storm Drainage System
d. Septic Tank and Catch Basin
14. ELECTRICAL WORKS

Sub-Total of Direct Cost (Materials+Labor+Equipment


Rental)

Sub-Total of Indirect Cost (Contractor's Profit+Tax)

SUMMARY OF ESTIMATES

DIRECT COST

Total Materials Cost

Total Labor Cost

Equipment Expenses

INDIRECT COST

Project Supervision

Tax

TOTAL PROJECT COST

Prepared by john Good luck engineer

You might also like