June Work Status

1/6/2021 Tuesday 1. Reposition jacking aligment toward Mh54 (RP) and service cutterhead.
2/6/2021 Wednesday 1. Hacking thrust wall to jack toward mh54(RP)
3/6/2021 Thursday 1. Continue setup jacking aligment towards MH54(RP)
4/6/2021 Friday 1. Continue setup jacking aligment towards MH54(RP)
5/6/2021 Saturday 1. Continue setup jacking aligment towards MH54(RP)
6/6/2021 Sunday N/A
7/6/2021 Monday 1. Continue setup jacking aligment towards MH54(RP)
8/6/2021 Tuesday 1. Start Jacking work from MH10-2 to MH54(RP) up to pipe no.6/43.
9/6/2021 Wednesday 1. Pipe jacking work start for MH10-2 to Mh54(RP), stop at pipe no.14/43
10/6/2021 Thursday 1. Pipe jacking work start for MH10-2 to Mh54(RP), stop at pipe no.19/43
11/6/2021 Friday 1. Pipe jacking work start for MH10-2 to Mh54(RP), stop at pipe no.24/43
12/6/2021 Saturday 1. Pipe jacking work start for MH10-2 to Mh54(RP), stop at pipe no.32/43
13/6/2021 Sunday N/A
14/6/2021 Monday 1. Pipe jacking work start for MH10-2 to Mh54(RP), stop at pipe no.40/43
15/6/2021 Tuesday 1. Pipe jacking work start for MH10-2 to Mh54(RP), stop at pipe no.41/43 and hit
16/6/2021 Wednesday 1. Site Monitoring and site safety preparation before start work in MH54(RP).
17/6/2021 Thursday 1. Start hacking work at MH54(RP) in order to receive cuttethead out.
18/6/2021 Friday 1. House keeping at MH10-2.
19/6/2021 Saturday 1.Continue hacking work towards mh54 existing sewer manholes
20/6/2021 Sunday N/A
21/6/2021 Monday 1.Continue hacking work towards mh54 existing sewer manholes
22/6/2021 Tuesday 1.Continue hacking work towards mh54 existing sewer manholes
1.Continue hacking work towards mh54 existing sewer manholes.
23/6/2021 Wednesday
2. Continue jacking pipe at no.43/43
1.Continue hacking work towards mh54 existing sewer manholes.
24/6/2021 Thursday 2. Continue jacking pipe at no.44/44.
3. Install base slab BRC & formwork for sewer manhole Mh10-2
25/6/2021 Friday 1. Install base slab BRC & formwork for sewer manhole Mh10-1
26/6/2021 Saturday 1. Concrete Base for Sewer Mh10-1 and Mh10-2
27/6/2021 Sunday N/A
28/6/2021 Monday 1. Install Caisson for sewer Manhole Mh10-1 & Mh10-2