1.1 GENERAL DELAY ANALYSIS
Building 2
1. Caisson foundation zone 2B finish January 06, 2024
2. Footing foundation finish January 27, 2024
3. Backfill January 29-February 02, 2024 (Backhoeloader)
4. Beam on ground finish February 15, 2024
5. Steel Building Structure February 19-26, 2024 (Crane 55 t)
6. Architectural Works finish July 15, 2024
7. MEP Works finish July 08, 2024
Building 3
1. Backfill December 13-22, 2023 (Backhoeloader)
2. Beam on Ground finish January 06, 2024
3. Steel Building Structure January 07-21, 2024 (Crane 55 t)
4. Architectural Works finish 04 June 04, 2024
5. MEP Works finish May 28, 2024
Building 4
1. Footing foundation finish January 10, 2024
2. Backfill January 12-17, 2024 (Backhoe loader)
3. Beam on Ground finish January 31, 2024
4. Steel Building Structure February 02-16 2024 (Crane 55 t)
5. Architectural Works finish June 30, 2024
6. MEP Works finish 23 June 23, 2024
Building 5
1. Caisson foundation finish Januari 04, 2024
N
2. Footing foundation finish 31 January 31, 2024
3. Backfill February 02-07, 2024 (Backhoeloader)
4. Beam on Ground finish February 15, 2024
5. Steel Building Structure February 29-March 14, 2024 (Crane 55 t)
6. Architectural Works finish July 15, 2024
7. MEP Works finish July 08, 2024
Mitigation :
1. To achieve the work target required for steel erection and material
shrouds, 2 cranes are needed Mar 08-14, 2024
2. Supporting heavy equipment for moving steel material from the
laydown area to the installation location using a boom truck or
trailler
3. To speed up steel installation without using scaffolding tools,
needed a boom lift
4. Installation of the sub beam uses a manual system with lifelines and Dec 23-29, 2023
ropes that tie the steel
5. The manpower requirement for steel installation is 12 person
Dec 13,2023-Jan 05,2024