Risk Delay Analysis &

Project Evaluation
EPC of 160 Room Senior
Staff Accomodation
Camp At Batu Hijau
1.1 GENERAL DELAY ANALYSIS

EPC of 160 Room Senior Staff Accomodation Camp at Batu Hijau


METHOD OF WORKS 01
1.2 DELAY ANALYSIS
Acset Factor AMNT Factor
• The Contract Site Access Badge consists of : • The need for heavy equipment according to
1. Staff 35 person impact analysis are not achieved:
2. Worker 20 person 1. Excavator PC 200 2 unit
Fulfilling labour needs in October cannot be 2. Excavator PC75 2 unit
full support 3. Crane 1 Unit (tambahan)
• The heavy equipment like backhoeloader and
crane seems unable to reach daily targets
because of :
1. Average working hours are only 5 hours
(in-out)
2. Contrained by operator roster and no
replacement
3. When the operator is there the rigger is not
there N
• Steel erection uses scaffolding tools due to
the unavailability of telehandlers and
boomlifts, it takes 2 days for 1 line and the
scaffolding manpower is not full support.

EPC of 160 Room Senior Staff Accomodation Camp at Batu Hijau


METHOD OF WORKS 02
1.3 PLAN TARGET
Building 1
1. Steel Building Structure December 13, 2023-January 5, 2024 (Crane 55 t)
2. Architectural Works finish April 30, 2024
3. MEP Works finish April 23, 2024

Building 2
1. Caisson foundation zone 2B finish January 06, 2024
2. Footing foundation finish January 27, 2024
3. Backfill January 29-February 02, 2024 (Backhoeloader)
4. Beam on ground finish February 15, 2024
5. Steel Building Structure February 19-26, 2024 (Crane 55 t)
6. Architectural Works finish July 15, 2024
7. MEP Works finish July 08, 2024

Building 3
1. Backfill December 13-22, 2023 (Backhoeloader)
2. Beam on Ground finish January 06, 2024
3. Steel Building Structure January 07-21, 2024 (Crane 55 t)
4. Architectural Works finish 04 June 04, 2024
5. MEP Works finish May 28, 2024

Building 4
1. Footing foundation finish January 10, 2024
2. Backfill January 12-17, 2024 (Backhoe loader)
3. Beam on Ground finish January 31, 2024
4. Steel Building Structure February 02-16 2024 (Crane 55 t)
5. Architectural Works finish June 30, 2024
6. MEP Works finish 23 June 23, 2024

Building 5
1. Caisson foundation finish Januari 04, 2024
N
2. Footing foundation finish 31 January 31, 2024
3. Backfill February 02-07, 2024 (Backhoeloader)
4. Beam on Ground finish February 15, 2024
5. Steel Building Structure February 29-March 14, 2024 (Crane 55 t)
6. Architectural Works finish July 15, 2024
7. MEP Works finish July 08, 2024

EPC of 160 Room Senior Staff Accomodation Camp at Batu Hijau


METHOD OF WORKS 03
1.4 SEQUENCE BACKFILLING
Mitigasi :
1. Backfill uses excavated soil from the planned road area on the south side
2. Schedule backhhoe loader
a) Excavation caisson foundation zone 5, December 25-30, 2023
b) Excavation caisson foundation zone 2, December 31, 2023- January 07,
2024
c) Building 1
Stone sand January 26-February 02, 2024
d) Building 2
Backfill January 29-February 02, 2024 (Backhoeloader)
Stone sand March 18-25, 2024
e) Building 3
Stone sand February 20-27, 2024
f) Building 4
Backfill January 12-17, 2024 (Backhoe loader)
Stone sand March 8-15,2024
g) Building 5
Backfill February 02-07, 2024 (Backhoeloader)
Stone sand March 28-April 03, 2024

EPC of 160 Room Senior Staff Accomodation Camp at Batu Hijau


METHOD OF WORKS 04
1.5 LIFTING CRANE POSITION

Jan 07-14, 2024 Feb 19-26, 2024

Feb 10-16, 2024

Mitigation :
1. To achieve the work target required for steel erection and material
shrouds, 2 cranes are needed Mar 08-14, 2024
2. Supporting heavy equipment for moving steel material from the
laydown area to the installation location using a boom truck or
trailler
3. To speed up steel installation without using scaffolding tools,
needed a boom lift
4. Installation of the sub beam uses a manual system with lifelines and Dec 23-29, 2023
ropes that tie the steel
5. The manpower requirement for steel installation is 12 person
Dec 13,2023-Jan 05,2024

Feb 2-9, 2024

Feb 29-March 7, 2024


Jan 15-21 2024

EPC of 160 Room Senior Staff Accomodation Camp at Batu Hijau


METHOD OF WORKS 05
1.6 NEED SUPPORT FROM CLIENT

EPC of 160 Room Senior Staff Accomodation Camp at Batu Hijau


METHOD OF WORKS 06
The true sign of intelligence
is not knowledge but imagination.
Albert Einstein

EPC of 160 Room Senior Staff Accomodation Camp at Batu Hijau


METHOD OF WORKS