SESSION PLAN

Sector: Construction Sector


Qualification Tittle: Carpentry NC II
Unit of Competency: Fabricate Formworks
Module Title: Fabricating Formworks

Learning Outcomes:
At the end of this session, the learners/trainees will be able to:
a) Prepare materials for fabricating formworks
b) Lay-out and cut to dimension of form sheathing and stiffeners
c) Assemble form panels
A. Introduction
This unit covers the knowledge, skills and attitudes in fabricating formworks. It includes preparing materials, lay-
outing, fabricating and assembling formworks.
B. Learning Activities
LO1: PREPARE MATERIALS FOR FABRICATING FORMWORKS
Learning Content Methodology Presentation Practice Feedback Resources Time
Personal Protective Modular Read information Answer self- Check the
Equipment sheet 2. 1-1 of check 2. 1- answers with
the modules to 1 the provided
know the answer key 2. CBLM 2
appropriate usage 1-1 hours
of Personal
Protective
Equipment.

Construction plans Modular Read information Answer self- Check the


and details 2. 1-2 to interpret check 2.1-2 answers with CBLM 2
the construction the provided hours
plans and details. answer key 2.
1-2
Materials for Modular Read information Answer self- Check the
fabricating sheet 2. 1-3 on check 2. 1- answers with
formworks the modules to 3 the provided CBLM 2
determine answer key 2. hours
materials used 1-3
for fabricating
formworks.
Power and hand Modular Read information Answer self- Check the
tools and sheet 2. 1-4 on check 2. 1- answers with CBLM 2
equipment the modules 4 the provided hours
different power answer key 2.
and hand tools 1-4
and equipment
used for
fabricating
formworks
LO2: LAY-OUT AND CUT TO DIMENSIONS OF FORM SHEATHING AND STIFFENERS
Learning Content Methodology Presentation Practice Feedback Resources Time
Formworks Modular Read information Answer self- Check the CBLM
sheet 2. 2-1 on check 2.2-1 answers with
the modules to the provided
know the answer key
different types of 2.2-1
formworks.
Lay-out and cut Modular Read information Answer self- Check the 10
formworks sheet 2. 2-2 on check 2. 2- answers with hours
the modules to 2 the provided
know and answer key
understand the 12.2-2 CBLM
different lay out
and cutting tools
and procedures
in prefabricating
formworks.
Demonstratio Follow the correct Perform Compare the  Portable
n procedures in task sheet performance circular saw
prefabricating 2. 2-2 based on the  Portable planer
formworks performance  Hand saw
panels. criteria  Hammer
checklist 2.2-2  Wrecking bar
Read task sheet  Folding rule
2. 2-2 on  Try square
prefabricate form  Measuring
panels and rods
stiffeners.
 Personal
Protective
Equipment

 Lumber
 Plywood
 Fasteners
 Working
drawing/plan
LO3: ASSEMBLE FORM PANELS
Learning Content Methodology Presentation Practice Feedback Resources Time
Assembling form Modular Read Information Answer self- Compare the
panels and Sheet 2.3-1 on check 2. 3- answers with
stiffeners the modules to 1 the provided CBLM
know the answer key 2.
procedures in 3-1
assembling form
panels and
stiffeners.
Demonstratio Follow the correct Perform Compare the  Hammer
n procedures in task sheet performance  Marking tools
assembling form 2. 3-1 based on the  Measuring
panels and performance tools
stiffeners. criteria  PPE
checklist 2.3-1
Read task sheet  Working 12
2. 3-1 on drawing/plan hours
assemble form  Lumber
panels and  Plywood
stiffeners.  Fasteners
Measurement for Demonstratio Follow the Perform Compare the  Nylon string
fabricated n appropriate task sheet performance  Chalk line reel
formworks measurement in 2. 3-2 based on the  Pull-push rule
fabricating performance  Framing
formworks. criteria square
checklist 2.3-2.  Try square
Read task sheet  Spirit level
2. 3-2 on
Checking and
fixing
fabricated
formworks
for levelness,
alignment,
squareness and
control
dimension to
specified
tolerance.
Safety practices Modular Read information Answer self- Compare the CBLM
sheet 2. 3-3 on check 2. 3- answers in the
the modules to 3. provided
familiarize safety answer key 2.
practices in 3-3.
fabricating
formworks
C. Assessment Plan:
 Written Tests
 Performance/Practical Tests
 Testing Condition
Tools: Equipment’s: Supplies and Materials:
 Claw hammer  Portable circular saw  Working drawings/plan
 Pencil/ marking pen  Portable planer  Lumber
 Pull-push rule  Personal Protective  Plywood
 Nylon string Equipment  Fasteners
 Plumb bob
 Steel square
 Try square
 Hand saw
 Chalk line
 Hand saw
 Wrecking bar
 Folding rule
 Measuring rods
 Framing square
 Spirit level
 Venue of the Evaluation
 Workstation 2
 Practical Work Area
 Type of Evidence
 Self-Checks/Task Sheets
 Performance Criteria Checklist
 Trainer’s Self-Reflection of the Session

Prepared by:

SANDRA JAY B.BANTAYAN


Carpentry NC II Trainer

You might also like