DDA 305 – ASSIGNMENT NUMBER 1

JEROME CASEM ORATE


CLUSTER HEAD
UNION GALVASTEEL CORPORATION-LA UNION
 MANUFACTURE OF GALVANIZED STEEL PRODUCTS
 SUPPLY AND INSTALLATION

1. Program Evaluation Review Technique (PERT)


ONSITE ROLLFORMING OF ~12,000 SQM PROJECT
ID TASK TYPE DEPENDENT DURATION START FINISH
ON
A PROJECT ASSESSMENT (INTERNAL AND EXTERNAL) SEQUENTIA 2
L
B COST ESTIMATES SEQUENTIA A 1
L
C PREPARATION OF SALES QUOTATION SEQUENTIA B 0.5
L
D APPROVALS/AUTHORITY TO QUOTE SEQUENTIA C 0.5
L
E REVISIONS SEQUENTIA C, D 0.5
L
F CONTRACT/MEMORANDUM OF AGREEMENT PREPARATION SEQUENTIA D 0.5
L
G SCHEDULING OF MACHINE AND MANPOWER PARALLEL A, F 0.5
H LOGISTICS PLANNING PARALLEL A, F 0.5
I SITE SET-UP SEQUENTIA F 0.5
L
J DELIVERY SEQUENTIA I 1
L
K PROJECT IMPLEMENTATION SEQUENTIA G, H 7
L
L PROJECT EVALUATION PARALLEL K 0.5
M ADJUSTMENTS PARALLEL K 0.5
N DECOMISSIONING OF MACHINE AND MANPOWER FROM PROJECT SITE SEQUENTIA K 0.25
L
O FINISHED PROJECT INSPECTION SEQUENTIA N 0.25
DDA 305 – ASSIGNMENT NUMBER 1

L
P RECTIFICATION PARALLEL O 1
Q NOTICE OF COMPLETION SEQUENTIA P 0.25
L
COMPLETION 16.25 DAYS

2. Critical Path Method (CPM)


3. Forecasting