WIDE COMMUNICATION PROJECT ACTIVITIES

WBS ID Activity/Task Name Predecessor Task Dependency


1.1 Property Acquisition/Lease/Rental 1.1 LEGAL TEAM/ROW
1.2 Documentation 1.1 LEGAL TEAM/ROW
1.3 Permitting 1.1 LEGAL TEAM/ROW
2.1 Order & Received 2.1 Procurement
2.2 Materials Delivery 2.1 Procurement
3.1 Planning 3.1 Engineering Design
3.2 Pre-Plan Drawing / Layout 3.1 Engineering Design
3.3 Approved Final Drawing / Layout 4.1 Engineering Design
4.1 Site Survey 3.2 Engineering Design / Implementation
4.2 Assessment Validation 3.2 Engineering Design / Implementation
5.1 Construction 1.3 Implementation
5.2 Construction Team 5.1 Implementation
5.2 Kick off 5.1 Implementation
5.3 Construction Shelter 5.1 Implementation
5.4 Fiber Laying 5.1 Implementation
5.5 Installation of Rack Space & Power 5.1 Implementation
6.1 Pre-Testing 5.1 Implementation /QA
6.2 End to end connectivity testing 5.1 Implementation
6.3 Facilities turn up testing 5.1 Implementation /QA
6.4 Remediation /Finalizing/Validation 6.1 Implementation
7.1 Acceptance 6.1 Implementation
7.2 Closed out packages 7.1 Implementation
S
Duration Start Finish
4 MONTHS 5/1/2022 5/5/2022
3 MONTHS 01/15/2022 04/30/2022
3 MONTHS 1/2/2022 05/30/2022
4 MONTHS 5/1/2022 5/5/2022
4 MONTHS 5/1/2022 5/5/2022
4 MONTHS 5/1/2022 5/5/2022
3 MONTHS 5/1/2022 5/4/2022
1 MONTH 5/4/2020 5/5/2022
2 MONTHS 5/2/2022 5/4/2022
2 MONTHS 5/2/2022 5/4/2022
12 MONTHS 5/3/2022 5/4/2023
2 MONTH 5/1/2022 4/3/2022
4 DAYS 3/3/2022 8/3/2022
7 MONTHS 4/3/2022 4/10/2022
9 MONTHS 4/3/2022 5/12/2022
7 MONTHS 5/5/2022 5/12/2022
2 MONTHS 5/12/2022 5/2/2023
2 MONTHS 5/12/2022 5/2/2023
2 MONTHS 5/12/2022 5/2/2023
2 MONTHS 5/1/2023 5/3/2023
1 MONTH 10/3/2023 10/4/2023
1 MONTH 10/4/2023 10/5/2023